North Dakota site-work prices by county

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake: 2,481 winning line items in 49 counties, plus 171 statewide and multi-district items.

Statewide and multi-district contracts

Contracts let statewide, by district or region, or across many counties, so they don't sit on one county page. Median and range across winning line items; outliers (below 20% or above 500% of the national median for the category and unit) are listed but left out of the median and range. Each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
Asphalt pavementTON43$178.50$31.02 to $600.00
Bids
  • 2026-06-12 · NDDOT · CERP-FXS-3411(063) · $400.00 per TON · qty 88 · Pembina · bid tab
  • 2026-05-08 · NDDOT · NH-4-083(158)157 · $43.06 per TON · qty 97,153 · Mclean, Ward · bid tab
  • 2026-05-08 · NDDOT · NH-4-083(158)157 · $592.00 per TON · qty 4,371 · Mclean, Ward · bid tab
  • 2026-05-08 · NDDOT · BRC-3411(062) · $230.00 per TON · qty 477 · Pembina · bid tab
  • 2026-04-10 · NDDOT · NH-4-002(146)152 · $600.00 per TON · qty 2,189 · Mchenry, Ward · bid tab
  • 2026-04-10 · NDDOT · NH-4-002(146)152 · $41.87 per TON · qty 48,541 · Mchenry, Ward · bid tab
  • 2026-02-27 · NDDOT · BRC-BRJ-3400(051) · $195.00 per TON · qty 177 · Pembina · bid tab
  • 2026-02-27 · NDDOT · NH-4-083(157)181 · $38.78 per TON · qty 39,583 · Ward · bid tab
  • 2026-02-27 · NDDOT · NH-4-083(157)181 · $580.00 per TON · qty 1,781 · Ward · bid tab
  • 2026-02-27 · NDDOT · TAU-4-989(137) · $220.00 per TON · qty 180 · Ward · bid tab
(10 most recent of 43 shown; all in the Hubstake feed)
Concrete pavementSY4$114.50$112.00 to $117.00
Bids
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $3.99 per SY · qty 8,611 · Pembina · bid tab outlier, not in the median
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $112.00 per SY · qty 20,923 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $117.00 per SY · qty 1,369 · Ward · bid tab
  • 2024-03-15 · NDDOT · IM-6-029(175)187 · $6.05 per SY · qty 8,101 · Pembina · bid tab outlier, not in the median
Curb gutterLF14$72.16$48.38 to $163.20
Bids
  • 2026-02-27 · NDDOT · TAU-4-989(137) · $62.00 per LF · qty 813 · Ward · bid tab
  • 2026-02-27 · NDDOT · TAU-4-989(137) · $48.38 per LF · qty 176 · Ward · bid tab
  • 2026-01-16 · NDDOT · SS-6-999(060) · $85.00 per LF · qty 60 · Grand Forks, Pemb · bid tab
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $85.00 per LF · qty 80 · Pembina · bid tab
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $163.20 per LF · qty 60 · Pembina · bid tab
  • 2025-04-11 · NDDOT · NH-CPU-4-083(142)198 · $72.16 per LF · qty 1,632 · Ward · bid tab
  • 2025-04-11 · NDDOT · NH-CPU-4-083(142)198 · $3.10 per LF · qty 1,580 · Ward · bid tab outlier, not in the median
  • 2025-03-21 · NDDOT · TAU-4-989(131) · $107.00 per LF · qty 228 · Ward · bid tab
  • 2025-03-21 · NDDOT · TAU-4-989(131) · $61.25 per LF · qty 1,300 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $49.70 per LF · qty 6,552 · Ward · bid tab
(10 most recent of 14 shown; all in the Hubstake feed)
Curb gutterSF1n/an/a
Bids
  • 2024-04-12 · NDDOT · H-6-066(035)138 · $450.00 per SF · qty 58 · Pembina · bid tab outlier, not in the median
Excavation embankmentCY24$17.65$7.00 to $80.04
Bids
  • 2026-06-12 · NDDOT · CERP-FXS-3411(063) · $9.00 per CY · qty 348 · Pembina · bid tab
  • 2026-06-12 · NDDOT · CERP-FXS-3411(063) · $30.00 per CY · qty 1,689 · Pembina · bid tab
  • 2026-05-08 · NDDOT · BRC-3411(062) · $27.00 per CY · qty 109 · Pembina · bid tab
  • 2026-05-08 · NDDOT · BRC-3411(062) · $53.00 per CY · qty 15 · Pembina · bid tab
  • 2026-05-08 · NDDOT · BRC-3411(062) · $16.50 per CY · qty 4,608 · Pembina · bid tab
  • 2026-02-27 · NDDOT · BRC-BRJ-3400(051) · $14.00 per CY · qty 240 · Pembina · bid tab
  • 2026-02-27 · NDDOT · BRC-BRJ-3400(051) · $18.00 per CY · qty 245 · Pembina · bid tab
  • 2026-02-27 · NDDOT · TAU-4-989(137) · $80.04 per CY · qty 376 · Ward · bid tab
  • 2025-11-14 · NDDOT · HEN-7-052(034)000 · $7.50 per CY · qty 72,849 · Burke, Ward · bid tab
  • 2025-11-14 · NDDOT · HEN-7-052(034)000 · $17.30 per CY · qty 70,119 · Burke, Ward · bid tab
(10 most recent of 24 shown; all in the Hubstake feed)
Fire hydrantEA1$9,270.00$9,270.00 to $9,270.00
Bids
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $9,270.00 per EA · qty 4 · Ward · bid tab
Flexible baseCY5$57.70$45.00 to $70.00
Bids
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $70.00 per CY · qty 124 · Pembina · bid tab
  • 2025-03-14 · NDDOT · H-6-066(036)124 · $59.65 per CY · qty 836 · Pembina · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $57.70 per CY · qty 14,244 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $52.00 per CY · qty 84 · Ward · bid tab
  • 2024-06-14 · NDDOT · H-6-066(034)124 · $45.00 per CY · qty 349 · Pembina · bid tab
Flexible baseTON15$34.25$18.60 to $120.00
Bids
  • 2026-06-12 · NDDOT · CERP-FXS-3411(063) · $99.00 per TON · qty 68 · Pembina · bid tab
  • 2026-05-08 · NDDOT · BRC-3411(062) · $20.00 per TON · qty 1,340 · Pembina · bid tab
  • 2026-02-27 · NDDOT · BRC-BRJ-3400(051) · $21.15 per TON · qty 611 · Pembina · bid tab
  • 2026-02-27 · NDDOT · TAU-4-989(137) · $56.03 per TON · qty 1,143 · Ward · bid tab
  • 2026-01-16 · NDDOT · SS-6-999(060) · $57.75 per TON · qty 511.60 · Grand Forks, Pemb · bid tab
  • 2025-11-14 · NDDOT · HEN-7-052(034)000 · $18.60 per TON · qty 187,403 · Burke, Ward · bid tab
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $28.25 per TON · qty 9,346 · Pembina · bid tab
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $42.00 per TON · qty 508 · Pembina · bid tab
  • 2025-07-18 · NDDOT · CERP-3404(060) · $28.60 per TON · qty 199 · Pembina · bid tab
  • 2025-05-09 · NDDOT · SC-5132(061) · $60.00 per TON · qty 675 · Ward · bid tab
(10 most recent of 15 shown; all in the Hubstake feed)
Inlet headwallEA11$6,940.00$1,600.00 to $18,400.00
Bids
  • 2026-01-16 · NDDOT · SS-6-999(060) · $1,600.00 per EA · qty 4 · Grand Forks, Pemb · bid tab
  • 2025-04-11 · NDDOT · NH-CPU-4-083(142)198 · $7,675.00 per EA · qty 1 · Ward · bid tab
  • 2025-03-21 · NDDOT · TAU-4-989(131) · $3,050.50 per EA · qty 3 · Ward · bid tab
  • 2025-03-21 · NDDOT · TAU-4-989(131) · $2,506.00 per EA · qty 1 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $6,940.00 per EA · qty 1 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $4,870.00 per EA · qty 21 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $7,980.00 per EA · qty 22 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $41,200.00 per EA · qty 3 · Ward · bid tab outlier, not in the median
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $13,700.00 per EA · qty 3 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $18,400.00 per EA · qty 3 · Ward · bid tab
(10 most recent of 11 shown; all in the Hubstake feed)
Inlet headwallLF1n/an/a
Bids
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $119.00 per LF · qty 115 · Ward · bid tab outlier, not in the median
Lime cement stabilizationACRE2$321.76$225.52 to $418.00
Bids
  • 2025-11-14 · NDDOT · HEN-7-052(034)000 · $225.52 per ACRE · qty 238 · Burke, Ward · bid tab
  • 2024-03-15 · NDDOT · SS-6-032(069)219 · $418.00 per ACRE · qty 14 · Pembina · bid tab
Lime cement stabilizationEA2n/an/a
Bids
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $5,100.00 per EA · qty 4 · Ward · bid tab outlier, not in the median
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $1,390.00 per EA · qty 4 · Ward · bid tab outlier, not in the median
Lime cement stabilizationSY2$3.00$3.00 to $3.00
Bids
  • 2025-05-09 · NDDOT · SC-5132(061) · $3.00 per SY · qty 123,605 · Ward · bid tab
  • 2024-03-15 · NDDOT · SS-6-032(069)219 · $1.89 per SY · qty 202,929 · Pembina · bid tab outlier, not in the median
ManholeEA7$11,100.00$5,800.00 to $21,500.00
Bids
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $34,400.00 per EA · qty 1 · Ward · bid tab outlier, not in the median
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $5,800.00 per EA · qty 1 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $13,200.00 per EA · qty 5 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $21,500.00 per EA · qty 1 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $30,800.00 per EA · qty 2 · Ward · bid tab outlier, not in the median
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $9,060.00 per EA · qty 2 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $11,100.00 per EA · qty 7 · Ward · bid tab
SidewalkEA3n/an/a
Bids
  • 2026-01-16 · NDDOT · SS-6-999(060) · $65.00 per EA · qty 2 · Grand Forks, Pemb · bid tab outlier, not in the median
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $65.00 per EA · qty 2 · Pembina · bid tab outlier, not in the median
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $74.00 per EA · qty 8 · Ward · bid tab outlier, not in the median
SidewalkLF2$16.32$14.50 to $18.15
Bids
  • 2026-02-27 · NDDOT · TAU-4-989(137) · $18.15 per LF · qty 300 · Ward · bid tab
  • 2025-03-21 · NDDOT · TAU-4-989(131) · $14.50 per LF · qty 298 · Ward · bid tab
SidewalkSY10$141.19$94.60 to $172.98
Bids
  • 2026-02-27 · NDDOT · TAU-4-989(137) · $142.39 per SY · qty 1,454 · Ward · bid tab
  • 2026-02-27 · NDDOT · TAU-4-989(137) · $142.39 per SY · qty 589 · Ward · bid tab
  • 2026-02-27 · NDDOT · TAU-4-989(137) · $94.60 per SY · qty 1,600 · Ward · bid tab
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $172.98 per SY · qty 13 · Pembina · bid tab
  • 2025-03-21 · NDDOT · TAU-4-989(131) · $122.50 per SY · qty 436 · Ward · bid tab
  • 2025-03-21 · NDDOT · TAU-4-989(131) · $148.00 per SY · qty 528 · Ward · bid tab
  • 2025-03-21 · NDDOT · TAU-4-989(131) · $110.50 per SY · qty 1,453 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $154.00 per SY · qty 288 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $94.90 per SY · qty 3,151 · Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $140.00 per SY · qty 268 · Ward · bid tab
Storm pipe (diameter not stated)LF4$1,190.00$1,190.00 to $1,190.00
Bids
  • 2026-02-27 · NDDOT · BRC-BRJ-3400(051) · $4,185.00 per LF · qty 72 · Pembina · bid tab outlier, not in the median
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $2,070.00 per LF · qty 66 · Pembina · bid tab outlier, not in the median
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $1,190.00 per LF · qty 66 · Pembina · bid tab
  • 2025-04-11 · NDDOT · NH-CPU-4-083(142)198 · $2,515.00 per LF · qty 228 · Ward · bid tab outlier, not in the median
Storm pipe 15-inchLF1$88.10$88.10 to $88.10
Bids
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $88.10 per LF · qty 1,011 · Ward · bid tab
Storm pipe 18-inchLF1$104.00$104.00 to $104.00
Bids
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $104.00 per LF · qty 593 · Ward · bid tab
Storm pipe 24-inchLF3$218.00$140.00 to $275.00
Bids
  • 2025-11-14 · NDDOT · HEN-7-052(034)000 · $218.00 per LF · qty 212 · Burke, Ward · bid tab
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $275.00 per LF · qty 12 · Pembina · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $140.00 per LF · qty 1,010 · Ward · bid tab
Storm pipe 30-inchLF3$220.00$197.00 to $257.50
Bids
  • 2025-11-14 · NDDOT · HEN-7-052(034)000 · $257.50 per LF · qty 126 · Burke, Ward · bid tab
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $220.00 per LF · qty 92 · Pembina · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $197.00 per LF · qty 1,486 · Ward · bid tab
Storm pipe 33-inchLF1$238.00$238.00 to $238.00
Bids
  • 2025-11-14 · NDDOT · HEN-7-052(034)000 · $238.00 per LF · qty 14 · Burke, Ward · bid tab
Storm pipe 36-inchLF2$281.00$269.00 to $293.00
Bids
  • 2025-11-14 · NDDOT · HEN-7-052(034)000 · $293.00 per LF · qty 10 · Burke, Ward · bid tab
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $269.00 per LF · qty 466 · Ward · bid tab
Storm pipe 42-inchLF1$275.00$275.00 to $275.00
Bids
  • 2025-11-14 · NDDOT · HEN-7-052(034)000 · $275.00 per LF · qty 20 · Burke, Ward · bid tab
Storm pipe 48-inchLF1$425.00$425.00 to $425.00
Bids
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $425.00 per LF · qty 281 · Ward · bid tab
Storm pipe 54-inchLF1$580.00$580.00 to $580.00
Bids
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $580.00 per LF · qty 20 · Ward · bid tab
Storm pipe 58-inchLF1$684.00$684.00 to $684.00
Bids
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $684.00 per LF · qty 149 · Ward · bid tab
Storm pipe 60-inchLF1$715.00$715.00 to $715.00
Bids
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $715.00 per LF · qty 137 · Ward · bid tab
Storm pipe 72-inchLF2$943.81$837.62 to $1,050.00
Bids
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $1,050.00 per LF · qty 62 · Ward · bid tab
  • 2025-02-07 · NDDOT · BRJ-0051(057) · $837.62 per LF · qty 372 · Ward · bid tab
Water main 6-inchLF1$130.00$130.00 to $130.00
Bids
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $130.00 per LF · qty 111 · Ward · bid tab
Water main 8-inchLF1$104.00$104.00 to $104.00
Bids
  • 2025-03-14 · NDDOT · SU-NHU-CRP-4-989(134) · $104.00 per LF · qty 42 · Ward · bid tab

Source file sitework_prices.csv, sha256 2bb4664a6765. Engineer's estimates are excluded. Not a quote.