Site-work prices, Pembina County, ND

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON18$212.50$38.40 to $575.00
Bids
  • 2026-06-12 · NDDOT · CERP-FXS-3411(063) · $400.00 per TON · qty 88.0 · bid tab
  • 2026-05-08 · NDDOT · BRC-3411(062) · $230.00 per TON · qty 477.0 · bid tab
  • 2026-02-27 · NDDOT · BRC-BRJ-3400(051) · $195.00 per TON · qty 177.0 · bid tab
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $440.00 per TON · qty 425.0 · bid tab
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $93.50 per TON · qty 6751.0 · bid tab
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $135.00 per TON · qty 200.0 · bid tab
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $70.00 per TON · qty 47154.0 · bid tab
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $415.00 per TON · qty 2469.8 · bid tab
  • 2025-07-18 · NDDOT · CERP-3404(060) · $321.00 per TON · qty 146.0 · bid tab
  • 2025-03-14 · NDDOT · H-6-066(036)124 · $547.00 per TON · qty 25.0 · bid tab
(10 most recent of 18 shown; all in the Hubstake feed)
concrete pavementSY2$5.02$3.99 to $6.05
Bids
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $3.99 per SY · qty 8611.0 · bid tab
  • 2024-03-15 · NDDOT · IM-6-029(175)187 · $6.05 per SY · qty 8101.0 · bid tab
curb gutterLF3$85.00$81.00 to $163.20
Bids
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $85.00 per LF · qty 80.0 · bid tab
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $163.20 per LF · qty 60.0 · bid tab
  • 2024-03-15 · NDDOT · SS-6-032(069)219 · $81.00 per LF · qty 80.0 · bid tab
curb gutterSF1$450.00$450.00 to $450.00
Bids
  • 2024-04-12 · NDDOT · H-6-066(035)138 · $450.00 per SF · qty 58.0 · bid tab
excavation embankmentCY13$16.50$7.00 to $53.00
Bids
  • 2026-06-12 · NDDOT · CERP-FXS-3411(063) · $9.00 per CY · qty 348.0 · bid tab
  • 2026-06-12 · NDDOT · CERP-FXS-3411(063) · $30.00 per CY · qty 1689.0 · bid tab
  • 2026-05-08 · NDDOT · BRC-3411(062) · $27.00 per CY · qty 109.0 · bid tab
  • 2026-05-08 · NDDOT · BRC-3411(062) · $53.00 per CY · qty 15.0 · bid tab
  • 2026-05-08 · NDDOT · BRC-3411(062) · $16.50 per CY · qty 4608.0 · bid tab
  • 2026-02-27 · NDDOT · BRC-BRJ-3400(051) · $14.00 per CY · qty 240.0 · bid tab
  • 2026-02-27 · NDDOT · BRC-BRJ-3400(051) · $18.00 per CY · qty 245.0 · bid tab
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $14.00 per CY · qty 942.0 · bid tab
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $7.00 per CY · qty 5938.0 · bid tab
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $14.75 per CY · qty 18221.0 · bid tab
(10 most recent of 13 shown; all in the Hubstake feed)
flexible baseCY3$59.65$45.00 to $70.00
Bids
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $70.00 per CY · qty 124.0 · bid tab
  • 2025-03-14 · NDDOT · H-6-066(036)124 · $59.65 per CY · qty 836.0 · bid tab
  • 2024-06-14 · NDDOT · H-6-066(034)124 · $45.00 per CY · qty 349.0 · bid tab
flexible baseTON8$28.43$20.00 to $99.00
Bids
  • 2026-06-12 · NDDOT · CERP-FXS-3411(063) · $99.00 per TON · qty 68.0 · bid tab
  • 2026-05-08 · NDDOT · BRC-3411(062) · $20.00 per TON · qty 1340.0 · bid tab
  • 2026-02-27 · NDDOT · BRC-BRJ-3400(051) · $21.15 per TON · qty 611.0 · bid tab
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $28.25 per TON · qty 9346.0 · bid tab
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $42.00 per TON · qty 508.0 · bid tab
  • 2025-07-18 · NDDOT · CERP-3404(060) · $28.60 per TON · qty 199.0 · bid tab
  • 2024-03-15 · NDDOT · IM-6-029(175)187 · $85.00 per TON · qty 140.0 · bid tab
  • 2024-03-15 · NDDOT · SS-6-032(069)219 · $24.40 per TON · qty 2852.0 · bid tab
lime cement stabilizationACRE1$418.00$418.00 to $418.00
Bids
  • 2024-03-15 · NDDOT · SS-6-032(069)219 · $418.00 per ACRE · qty 14.0 · bid tab
lime cement stabilizationSY1$1.89$1.89 to $1.89
Bids
  • 2024-03-15 · NDDOT · SS-6-032(069)219 · $1.89 per SY · qty 202929.0 · bid tab
sidewalkEA1$65.00$65.00 to $65.00
Bids
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $65.00 per EA · qty 2.0 · bid tab
sidewalkSY1$172.98$172.98 to $172.98
Bids
  • 2025-10-10 · NDDOT · IM-6-029(163)197 · $172.98 per SY · qty 13.0 · bid tab
storm pipe 24-inchLF1$275.00$275.00 to $275.00
Bids
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $275.00 per LF · qty 12.0 · bid tab
storm pipe 30-inchLF1$220.00$220.00 to $220.00
Bids
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $220.00 per LF · qty 92.0 · bid tab
storm pipe (diameter not stated)LF3$2,070.00$1,190.00 to $4,185.00
Bids
  • 2026-02-27 · NDDOT · BRC-BRJ-3400(051) · $4,185.00 per LF · qty 72.0 · bid tab
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $2,070.00 per LF · qty 66.0 · bid tab
  • 2025-11-14 · NDDOT · SS-6-018(081)239 · $1,190.00 per LF · qty 66.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.