Site-work prices, Williams County, ND

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON12$349.50$52.00 to $750.00
Bids
  • 2026-04-10 · NDDOT · HES-7-804(077)340 · $720.00 per TON · qty 126.0 · bid tab
  • 2026-04-10 · NDDOT · HES-7-804(077)340 · $122.00 per TON · qty 2091.0 · bid tab
  • 2026-02-27 · NDDOT · NH-7-002(172)053 · $335.00 per TON · qty 142.0 · bid tab
  • 2025-07-18 · NDDOT · HES-7-804(075)330 · $750.00 per TON · qty 248.0 · bid tab
  • 2025-07-18 · NDDOT · HES-7-804(075)330 · $99.75 per TON · qty 4116.0 · bid tab
  • 2025-05-09 · NDDOT · BRP-BRC-5300(018) · $364.00 per TON · qty 382.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $190.00 per TON · qty 2275.0 · bid tab
  • 2024-12-20 · NDDOT · SU-7-993(061) · $124.00 per TON · qty 1305.0 · bid tab
  • 2024-12-20 · NDDOT · SU-7-993(061) · $500.00 per TON · qty 78.0 · bid tab
  • 2024-10-11 · NDDOT · TAC-0053(084) · $440.00 per TON · qty 20.0 · bid tab
(10 most recent of 12 shown; all in the Hubstake feed)
concrete pavementSY5$95.51$4.25 to $169.50
Bids
  • 2026-06-12 · NDDOT · NH-7-002(193)012 · $5.78 per SY · qty 83691.0 · bid tab
  • 2026-05-15 · NDDOT · NH-7-002(195)022 · $4.25 per SY · qty 76778.0 · bid tab
  • 2025-07-18 · NDDOT · HES-7-804(075)330 · $169.50 per SY · qty 227.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $112.00 per SY · qty 61855.0 · bid tab
  • 2024-02-16 · NDDOT · HEN-7-002(176)000 · $95.51 per SY · qty 19962.0 · bid tab
curb gutterLF13$70.00$14.14 to $90.00
Bids
  • 2026-02-27 · NDDOT · NH-7-002(172)053 · $85.85 per LF · qty 75.0 · bid tab
  • 2026-02-27 · NDDOT · NH-7-002(172)053 · $85.85 per LF · qty 18.0 · bid tab
  • 2026-02-06 · NDDOT · TAU-7-993(062) · $59.35 per LF · qty 99.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $45.00 per LF · qty 14675.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $90.00 per LF · qty 50.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $75.00 per LF · qty 164.0 · bid tab
  • 2024-12-20 · NDDOT · SU-7-993(061) · $70.00 per LF · qty 420.0 · bid tab
  • 2024-10-11 · NDDOT · TAC-0053(084) · $86.51 per LF · qty 14.0 · bid tab
  • 2024-10-11 · NDDOT · TAC-0053(084) · $59.61 per LF · qty 129.0 · bid tab
  • 2024-10-11 · NDDOT · TAC-0053(084) · $14.14 per LF · qty 50.0 · bid tab
(10 most recent of 13 shown; all in the Hubstake feed)
excavation embankmentCY21$22.00$3.98 to $175.00
Bids
  • 2026-04-10 · NDDOT · HES-7-804(077)340 · $36.00 per CY · qty 1505.0 · bid tab
  • 2026-04-10 · NDDOT · HES-7-804(077)340 · $29.00 per CY · qty 2261.0 · bid tab
  • 2026-02-06 · NDDOT · TAU-7-993(062) · $19.36 per CY · qty 888.0 · bid tab
  • 2025-07-18 · NDDOT · HES-7-804(075)330 · $34.90 per CY · qty 782.0 · bid tab
  • 2025-07-18 · NDDOT · HES-7-804(075)330 · $12.35 per CY · qty 3347.0 · bid tab
  • 2025-05-09 · NDDOT · BRP-BRC-5300(018) · $18.00 per CY · qty 200.0 · bid tab
  • 2025-05-09 · NDDOT · BRP-BRC-5300(018) · $12.00 per CY · qty 1518.0 · bid tab
  • 2025-05-09 · NDDOT · BRP-BRC-5300(018) · $9.60 per CY · qty 1045.0 · bid tab
  • 2025-05-09 · NDDOT · BRP-BRC-5300(018) · $26.19 per CY · qty 1468.0 · bid tab
  • 2025-02-07 · NDDOT · BRJ-0053(079) · $22.00 per CY · qty 178.0 · bid tab
(10 most recent of 21 shown; all in the Hubstake feed)
flexible baseCY2$117.03$89.07 to $145.00
Bids
  • 2024-12-20 · NDDOT · SU-7-993(061) · $145.00 per CY · qty 67.0 · bid tab
  • 2024-10-11 · NDDOT · TAC-0053(084) · $89.07 per CY · qty 394.0 · bid tab
flexible baseTON8$32.50$18.00 to $72.50
Bids
  • 2026-04-10 · NDDOT · HES-7-804(077)340 · $32.00 per TON · qty 5904.0 · bid tab
  • 2026-02-27 · NDDOT · NH-7-002(172)053 · $72.50 per TON · qty 167.0 · bid tab
  • 2026-02-06 · NDDOT · TAU-7-993(062) · $58.45 per TON · qty 450.0 · bid tab
  • 2025-07-18 · NDDOT · HES-7-804(075)330 · $27.60 per TON · qty 12151.0 · bid tab
  • 2025-05-09 · NDDOT · BRP-BRC-5300(018) · $33.00 per TON · qty 748.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $18.00 per TON · qty 37154.0 · bid tab
  • 2024-02-16 · NDDOT · HEN-7-002(176)000 · $23.13 per TON · qty 28309.0 · bid tab
  • 2023-11-17 · NDDOT · TAU-7-993(060) · $48.08 per TON · qty 326.0 · bid tab
inlet headwallEA12$4,500.00$2,400.00 to $11,700.00
Bids
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $4,600.00 per EA · qty 3.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $4,400.00 per EA · qty 1.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $2,600.00 per EA · qty 3.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $4,300.00 per EA · qty 1.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $7,600.00 per EA · qty 7.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $8,200.00 per EA · qty 2.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $2,400.00 per EA · qty 1.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $4,700.00 per EA · qty 1.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $11,700.00 per EA · qty 1.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $5,250.00 per EA · qty 1.0 · bid tab
(10 most recent of 12 shown; all in the Hubstake feed)
inlet headwallL SUM1$4,950.00$4,950.00 to $4,950.00
Bids
  • 2024-10-11 · NDDOT · TAC-0053(084) · $4,950.00 per L SUM · qty 1.0 · bid tab
manholeEA7$9,500.00$2,100.00 to $30,000.00
Bids
  • 2025-07-18 · NDDOT · HES-7-804(075)330 · $10,025.26 per EA · qty 1.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $5,200.00 per EA · qty 1.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $30,000.00 per EA · qty 1.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $16,000.00 per EA · qty 4.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $9,500.00 per EA · qty 1.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $5,200.00 per EA · qty 8.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $2,100.00 per EA · qty 5.0 · bid tab
sewer main 15-inchLF1$315.00$315.00 to $315.00
Bids
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $315.00 per LF · qty 1214.0 · bid tab
sidewalkEA4$73.27$50.00 to $82.50
Bids
  • 2026-02-06 · NDDOT · TAU-7-993(062) · $80.53 per EA · qty 4.0 · bid tab
  • 2024-12-20 · NDDOT · SU-7-993(061) · $50.00 per EA · qty 28.0 · bid tab
  • 2024-10-11 · NDDOT · TAC-0053(084) · $82.50 per EA · qty 4.0 · bid tab
  • 2023-11-17 · NDDOT · TAU-7-993(060) · $66.00 per EA · qty 1.0 · bid tab
sidewalkSY9$144.42$74.59 to $217.38
Bids
  • 2026-02-06 · NDDOT · TAU-7-993(062) · $74.59 per SY · qty 1439.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $90.00 per SY · qty 3772.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $120.00 per SY · qty 652.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $160.00 per SY · qty 89.0 · bid tab
  • 2024-12-20 · NDDOT · SU-7-993(061) · $180.00 per SY · qty 338.0 · bid tab
  • 2024-10-11 · NDDOT · TAC-0053(084) · $217.38 per SY · qty 115.0 · bid tab
  • 2024-10-11 · NDDOT · TAC-0053(084) · $144.42 per SY · qty 942.0 · bid tab
  • 2023-11-17 · NDDOT · TAU-7-993(060) · $148.93 per SY · qty 22.0 · bid tab
  • 2023-11-17 · NDDOT · TAU-7-993(060) · $127.98 per SY · qty 1026.0 · bid tab
storm pipe 24-inchLF3$440.00$314.78 to $820.25
Bids
  • 2025-07-18 · NDDOT · HES-7-804(075)330 · $820.25 per LF · qty 8.0 · bid tab
  • 2024-10-11 · NDDOT · TAC-0053(084) · $440.00 per LF · qty 6.0 · bid tab
  • 2024-02-16 · NDDOT · HEN-7-002(176)000 · $314.78 per LF · qty 72.0 · bid tab
storm pipe 30-inchLF2$511.25$397.25 to $625.25
Bids
  • 2025-07-18 · NDDOT · HES-7-804(075)330 · $625.25 per LF · qty 10.0 · bid tab
  • 2024-02-16 · NDDOT · HEN-7-002(176)000 · $397.25 per LF · qty 116.0 · bid tab
storm pipe 36-inchLF1$537.39$537.39 to $537.39
Bids
  • 2024-02-16 · NDDOT · HEN-7-002(176)000 · $537.39 per LF · qty 12.0 · bid tab
storm pipe 54-inchLF1$790.69$790.69 to $790.69
Bids
  • 2024-02-16 · NDDOT · HEN-7-002(176)000 · $790.69 per LF · qty 20.0 · bid tab
storm pipe (diameter not stated)LF4$3,377.50$1,260.00 to $4,935.00
Bids
  • 2025-05-09 · NDDOT · BRP-BRC-5300(018) · $4,445.00 per LF · qty 52.0 · bid tab
  • 2025-02-07 · NDDOT · BRJ-0053(079) · $4,935.00 per LF · qty 55.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $2,310.00 per LF · qty 62.0 · bid tab
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $1,260.00 per LF · qty 62.0 · bid tab
water main 8-inchLF1$350.00$350.00 to $350.00
Bids
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $350.00 per LF · qty 500.0 · bid tab
water serviceLF1$80.00$80.00 to $80.00
Bids
  • 2025-01-10 · NDDOT · NHU-SU-CPU-7-002(178)019 · $80.00 per LF · qty 86.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.