| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| Asphalt pavement | TON | 9 | $59.50 | $56.50 to $637.97 | Bids- 2026-04-15 · SDDOT · 09WL · $669.62 per TON · qty 2,212 · bid tab multi-county contract outlier, not in the median
- 2025-05-21 · SDDOT · 09L3 · $637.97 per TON · qty 942.40 · bid tab multi-county contract
- 2024-11-20 · SDDOT · 08YD · $56.50 per TON · qty 46,370.70 · bid tab multi-county contract
- 2024-11-20 · SDDOT · 08YD · $9.50 per TON · qty 2,194 · bid tab multi-county contract outlier, not in the median
- 2024-11-20 · SDDOT · 08YD · $59.50 per TON · qty 1,227 · bid tab multi-county contract
- 2024-11-20 · SDDOT · 08YD · $13.25 per TON · qty 2,194 · bid tab multi-county contract outlier, not in the median
- 2024-11-20 · SDDOT · 08YD · $710.00 per TON · qty 2,419 · bid tab multi-county contract outlier, not in the median
- 2024-11-20 · SDDOT · 08YD · $710.00 per TON · qty 63.40 · bid tab multi-county contract outlier, not in the median
- 2024-03-20 · SDDOT · 0973 · $702.54 per TON · qty 1,483.30 · bid tab multi-county contract outlier, not in the median
|
| Concrete pavement | LF | 1 | $2.56 | $2.56 to $2.56 | Bids- 2025-05-21 · SDDOT · 09FP · $2.56 per LF · qty 475,432 · bid tab multi-county contract
|
| Concrete pavement | MILE | 1 | $30,245.00 | $30,245.00 to $30,245.00 | Bids- 2025-05-21 · SDDOT · 09FP · $30,245.00 per MILE · qty 90 · bid tab multi-county contract
|
| Excavation embankment | CY | 3 | $22.75 | $15.00 to $65.50 | Bids- 2024-11-20 · SDDOT · 08YD · $15.00 per CY · qty 1,793 · bid tab multi-county contract
- 2024-11-20 · SDDOT · 08YD · $65.50 per CY · qty 160 · bid tab multi-county contract
- 2024-03-20 · SDDOT · 08KR · $22.75 per CY · qty 35,410 · bid tab multi-county contract
|
| Flexible base | TON | 2 | $22.88 | $16.50 to $29.25 | Bids- 2024-11-20 · SDDOT · 08YD · $16.50 per TON · qty 7,556.80 · bid tab multi-county contract
- 2024-03-20 · SDDOT · 08KR · $29.25 per TON · qty 180 · bid tab multi-county contract
|
| Storm pipe 18-inch | LF | 2 | $80.00 | $55.00 to $105.00 | Bids- 2024-03-20 · SDDOT · 08KR · $55.00 per LF · qty 8 · bid tab multi-county contract
- 2024-03-20 · SDDOT · 08KR · $105.00 per LF · qty 8 · bid tab multi-county contract
|
| Storm pipe 24-inch | LF | 2 | $55.50 | $41.00 to $70.00 | Bids- 2024-03-20 · SDDOT · 08KR · $41.00 per LF · qty 8 · bid tab multi-county contract
- 2024-03-20 · SDDOT · 08KR · $70.00 per LF · qty 8 · bid tab multi-county contract
|
| Storm pipe 30-inch | LF | 2 | $70.00 | $55.00 to $85.00 | Bids- 2024-03-20 · SDDOT · 08KR · $85.00 per LF · qty 18 · bid tab multi-county contract
- 2024-03-20 · SDDOT · 08KR · $55.00 per LF · qty 18 · bid tab multi-county contract
|