Site-work prices, McPherson County, SD
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across winning line items; outliers (below 20% or above 500% of the national median for the category and unit) are listed but left out of the median and range. Each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| Asphalt pavement | TON | 3 | $665.78 | $665.78 to $665.78 | Bids
|
| Excavation embankment | CY | 1 | $22.75 | $22.75 to $22.75 | Bids
|
| Flexible base | TON | 1 | $29.25 | $29.25 to $29.25 | Bids
|
| Storm pipe 18-inch | LF | 2 | $80.00 | $55.00 to $105.00 | |
| Storm pipe 24-inch | LF | 2 | $55.50 | $41.00 to $70.00 | |
| Storm pipe 30-inch | LF | 2 | $70.00 | $55.00 to $85.00 |
Source file sitework_prices.csv, sha256 2bb4664a6765. Engineer's estimates are excluded. Not a quote.