| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| Asphalt pavement | TON | 1 | n/a | n/a | Bids- 2026-05-19 · NCDOT · C204773 · $1,094.65 per TON · qty 1,380 · bid tab multi-county contract outlier, not in the median
|
| Curb gutter | LF | 2 | $38.79 | $31.94 to $45.63 | Bids- 2026-05-19 · NCDOT · C204773 · $45.63 per LF · qty 300 · bid tab multi-county contract
- 2026-05-19 · NCDOT · C204773 · $31.94 per LF · qty 9,640 · bid tab multi-county contract
|
| Excavation embankment | CY | 1 | $25.04 | $25.04 to $25.04 | Bids- 2026-05-19 · NCDOT · C204773 · $25.04 per CY · qty 114,800 · bid tab multi-county contract
|
| Fire hydrant | EA | 1 | $12,609.40 | $12,609.40 to $12,609.40 | Bids- 2026-05-19 · NCDOT · C204773 · $12,609.40 per EA · qty 1 · bid tab multi-county contract
|
| Fire hydrant | LF | 1 | $229.26 | $229.26 to $229.26 | Bids- 2026-05-19 · NCDOT · C204773 · $229.26 per LF · qty 20 · bid tab multi-county contract
|
| Flexible base | TON | 1 | $58.69 | $58.69 to $58.69 | Bids- 2026-05-19 · NCDOT · C204773 · $58.69 per TON · qty 3,110 · bid tab multi-county contract
|
| Inlet headwall | EA | 1 | $1,211.25 | $1,211.25 to $1,211.25 | Bids- 2026-05-19 · NCDOT · C204773 · $1,211.25 per EA · qty 25 · bid tab multi-county contract
|
| Lime cement stabilization | SY | 2 | $4.28 | $3.81 to $4.75 | Bids- 2026-05-19 · NCDOT · C204773 · $3.81 per SY · qty 3,530 · bid tab multi-county contract
- 2026-05-19 · NCDOT · C204773 · $4.75 per SY · qty 8,520 · bid tab multi-county contract
|
| Lime cement stabilization | TON | 1 | $52.20 | $52.20 to $52.20 | Bids- 2026-05-19 · NCDOT · C204773 · $52.20 per TON · qty 2,380 · bid tab multi-county contract
|
| Manhole | EA | 3 | $1,529.65 | $1,074.83 to $1,984.48 | Bids- 2026-05-19 · NCDOT · C204773 · $39,727.48 per EA · qty 2 · bid tab multi-county contract outlier, not in the median
- 2026-05-19 · NCDOT · C204773 · $1,984.48 per EA · qty 32 · bid tab multi-county contract
- 2026-05-19 · NCDOT · C204773 · $1,074.83 per EA · qty 15 · bid tab multi-county contract
|
| Sidewalk | EA | 1 | $2,965.77 | $2,965.77 to $2,965.77 | Bids- 2026-05-19 · NCDOT · C204773 · $2,965.77 per EA · qty 34 · bid tab multi-county contract
|
| Sidewalk | SY | 2 | $82.70 | $62.74 to $102.66 | Bids- 2026-05-19 · NCDOT · C204773 · $102.66 per SY · qty 280 · bid tab multi-county contract
- 2026-05-19 · NCDOT · C204773 · $62.74 per SY · qty 500 · bid tab multi-county contract
|
| Storm pipe 15-inch | LF | 2 | $103.93 | $100.81 to $107.05 | Bids- 2026-05-19 · NCDOT · C204773 · $107.05 per LF · qty 5,064 · bid tab multi-county contract
- 2026-05-19 · NCDOT · C204773 · $100.81 per LF · qty 664 · bid tab multi-county contract
|
| Storm pipe 18-inch | LF | 2 | $123.72 | $119.90 to $127.53 | Bids- 2026-05-19 · NCDOT · C204773 · $127.53 per LF · qty 936 · bid tab multi-county contract
- 2026-05-19 · NCDOT · C204773 · $119.90 per LF · qty 56 · bid tab multi-county contract
|
| Storm pipe 24-inch | LF | 1 | $174.76 | $174.76 to $174.76 | Bids- 2026-05-19 · NCDOT · C204773 · $174.76 per LF · qty 304 · bid tab multi-county contract
|
| Storm pipe 30-inch | LF | 2 | $225.62 | $222.58 to $228.66 | Bids- 2026-05-19 · NCDOT · C204773 · $228.66 per LF · qty 328 · bid tab multi-county contract
- 2026-05-19 · NCDOT · C204773 · $222.58 per LF · qty 64 · bid tab multi-county contract
|
| Storm pipe 36-inch | LF | 1 | $293.23 | $293.23 to $293.23 | Bids- 2026-05-19 · NCDOT · C204773 · $293.23 per LF · qty 296 · bid tab multi-county contract
|
| Storm pipe 42-inch | LF | 1 | $345.99 | $345.99 to $345.99 | Bids- 2026-05-19 · NCDOT · C204773 · $345.99 per LF · qty 128 · bid tab multi-county contract
|
| Storm pipe 60-inch | LF | 1 | $722.69 | $722.69 to $722.69 | Bids- 2026-05-19 · NCDOT · C204773 · $722.69 per LF · qty 228 · bid tab multi-county contract
|
| Storm pipe 72-inch | LF | 2 | $1,019.63 | $951.70 to $1,087.57 | Bids- 2026-05-19 · NCDOT · C204773 · $951.70 per LF · qty 216 · bid tab multi-county contract
- 2026-05-19 · NCDOT · C204773 · $1,087.57 per LF · qty 60 · bid tab multi-county contract
|
| Water main 12-inch | LF | 1 | $293.46 | $293.46 to $293.46 | Bids- 2026-05-19 · NCDOT · C204773 · $293.46 per LF · qty 417.20 · bid tab multi-county contract
|