Site-work prices, Sabine Parish, LA
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across winning line items; outliers (below 20% or above 500% of the national median for the category and unit) are listed but left out of the median and range. Each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| Asphalt pavement | TON | 7 | $135.00 | $75.00 to $174.00 | Bids- 2025-10-21 · LaDOTD · LA 120: MILL/OVERLAY - LOG MILE 4.01-8.00 · $155.00 per TON · qty 3,299.60 · bid tab
- 2025-08-13 · LaDOTD · LA 120: US 171 - ANGELA LANE · $174.00 per TON · qty 3,589 · bid tab
- 2025-08-13 · LaDOTD · LA 120: US 171 - ANGELA LANE · $100.00 per TON · qty 464.40 · bid tab
- 2024-07-10 · LaDOTD · LA 6: US 171 TO NATCHITOCHES P.L. · $154.65 per TON · qty 52,549.20 · bid tab
- 2024-07-10 · LaDOTD · LA 6: US 171 TO NATCHITOCHES P.L. · $109.70 per TON · qty 2,376.90 · bid tab
- 2023-12-13 · LaDOTD · LA 175: N JCT LA 120 - RAY CANTON RD · $75.00 per TON · qty 773 · bid tab
- 2023-12-13 · LaDOTD · LA 175: N JCT LA 120 - RAY CANTON RD · $135.00 per TON · qty 8,563.90 · bid tab
|
| Excavation embankment | CY | 3 | $45.75 | $28.25 to $63.25 | Bids- 2025-08-13 · LaDOTD · LA 120: US 171 - ANGELA LANE · $137.50 per CY · qty 132 · bid tab outlier, not in the median
- 2024-07-10 · LaDOTD · LA 6: US 171 TO NATCHITOCHES P.L. · $63.25 per CY · qty 319 · bid tab
- 2023-12-13 · LaDOTD · LA 175: N JCT LA 120 - RAY CANTON RD · $28.25 per CY · qty 4,645 · bid tab
|
| Lime cement stabilization | SY | 3 | $12.25 | $7.00 to $12.50 | Bids- 2023-12-13 · LaDOTD · LA 175: N JCT LA 120 - RAY CANTON RD · $12.25 per SY · qty 46,421.70 · bid tab
- 2023-12-13 · LaDOTD · LA 175: N JCT LA 120 - RAY CANTON RD · $12.50 per SY · qty 21,033 · bid tab
- 2023-12-13 · LaDOTD · LA 175: N JCT LA 120 - RAY CANTON RD · $7.00 per SY · qty 21,033 · bid tab
|
| Lime cement stabilization | TON | 1 | $300.00 | $300.00 to $300.00 | Bids- 2023-12-13 · LaDOTD · LA 175: N JCT LA 120 - RAY CANTON RD · $300.00 per TON · qty 209.26 · bid tab
|
Source file sitework_prices.csv, sha256 2bb4664a6765. Engineer's estimates are excluded. Not a quote.
All Louisiana site-work prices by county · Louisiana coverage