| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| Asphalt pavement | TON | 21 | $193.50 | $90.00 to $325.00 | Bids- 2026-06-24 · LaDOTD · LA 16: CURVE REALIGNMENT AT GOURDON LANE · $245.00 per TON · qty 226.90 · bid tab
- 2026-06-24 · LaDOTD · LA 16: CURVE REALIGNMENT AT GOURDON LANE · $130.00 per TON · qty 1,637.30 · bid tab
- 2026-06-10 · LaDOTD · LA 1026: LA 16 - FORREST DELATTE RD. · $195.00 per TON · qty 806.10 · bid tab
- 2026-06-10 · LaDOTD · LA 1026: LA 16 - FORREST DELATTE RD. · $105.00 per TON · qty 4,452.70 · bid tab
- 2026-06-10 · LaDOTD · PENDARVIS LANE IMPROVEMENTS PHASE II · $280.00 per TON · qty 216.30 · bid tab
- 2026-06-10 · LaDOTD · PENDARVIS LANE IMPROVEMENTS PHASE II · $159.00 per TON · qty 866.10 · bid tab
- 2026-05-13 · LaDOTD · I-12: HOG BRANCH BRIDGE REPLACEMENT · $200.00 per TON · qty 393.40 · bid tab
- 2026-05-13 · LaDOTD · I-12: HOG BRANCH BRIDGE REPLACEMENT · $116.00 per TON · qty 44,115.60 · bid tab
- 2026-03-11 · LaDOTD · LA 1026: CREEK BRIDGE · $129.25 per TON · qty 741.70 · bid tab
- 2026-03-11 · LaDOTD · LA 1026: CREEK BRIDGE · $178.00 per TON · qty 83 · bid tab
(10 most recent of 21 shown; all in the Hubstake feed) |
| Concrete pavement | SY | 2 | $111.00 | $110.00 to $112.00 | Bids- 2025-10-15 · LaDOTD · CENTERVILLE ST. NW IMPROVEMENTS · $112.00 per SY · qty 149.80 · bid tab
- 2025-01-08 · LaDOTD · LA 3002: U-TURN · $110.00 per SY · qty 912.60 · bid tab
|
| Curb gutter | LF | 4 | $68.50 | $14.00 to $100.00 | Bids- 2026-06-10 · LaDOTD · LA 1026: LA 16 - FORREST DELATTE RD. · $60.00 per LF · qty 162 · bid tab
- 2025-10-15 · LaDOTD · CENTERVILLE ST. NW IMPROVEMENTS · $77.00 per LF · qty 274.40 · bid tab
- 2025-01-08 · LaDOTD · LA 3002: U-TURN · $14.00 per LF · qty 1,217.40 · bid tab
- 2024-12-11 · LaDOTD · W. COLYELL BRIDGE REPLACEMENT · $100.00 per LF · qty 64 · bid tab
|
| Excavation embankment | CY | 8 | $50.00 | $36.00 to $100.00 | Bids- 2026-06-24 · LaDOTD · LA 16: CURVE REALIGNMENT AT GOURDON LANE · $38.00 per CY · qty 9,161 · bid tab
- 2026-06-10 · LaDOTD · LA 1026: LA 16 - FORREST DELATTE RD. · $50.00 per CY · qty 506 · bid tab
- 2026-06-10 · LaDOTD · LA 1026: LA 16 - FORREST DELATTE RD. · $100.00 per CY · qty 120.60 · bid tab
- 2026-05-13 · LaDOTD · I-12: HOG BRANCH BRIDGE REPLACEMENT · $80.00 per CY · qty 17,217 · bid tab
- 2025-08-13 · LaDOTD · LA 442: LA 63 - W. JCT. LA 441 · $50.00 per CY · qty 53.60 · bid tab
- 2025-08-13 · LaDOTD · LA 442: LA 63 - W. JCT. LA 441 · $36.00 per CY · qty 1,766 · bid tab
- 2025-03-12 · LaDOTD · LA 43: I-12 - US 190 · $100.00 per CY · qty 50 · bid tab
- 2024-09-18 · LaDOTD · LA 1029: US 190 - LA 447 · $43.00 per CY · qty 331 · bid tab
|
| Flexible base | CY | 1 | $225.00 | $225.00 to $225.00 | Bids- 2024-12-11 · LaDOTD · W. COLYELL BRIDGE REPLACEMENT · $225.00 per CY · qty 341 · bid tab
|
| Flexible base | SY | 4 | $35.75 | $24.00 to $54.00 | Bids- 2026-05-13 · LaDOTD · I-12: HOG BRANCH BRIDGE REPLACEMENT · $24.00 per SY · qty 36,539.80 · bid tab
- 2026-05-13 · LaDOTD · I-12: HOG BRANCH BRIDGE REPLACEMENT · $54.00 per SY · qty 5,764.60 · bid tab
- 2026-05-13 · LaDOTD · I-12: HOG BRANCH BRIDGE REPLACEMENT · $28.00 per SY · qty 36,539.80 · bid tab
- 2025-01-08 · LaDOTD · LA 3002: U-TURN · $43.50 per SY · qty 1,012 · bid tab
|
| Inlet headwall | EA | 2 | $3,163.00 | $3,163.00 to $3,163.00 | Bids- 2026-03-11 · LaDOTD · LA 1026: CREEK BRIDGE · $81,400.00 per EA · qty 2 · bid tab outlier, not in the median
- 2025-10-15 · LaDOTD · CENTERVILLE ST. NW IMPROVEMENTS · $3,163.00 per EA · qty 4 · bid tab
|
| Lime cement stabilization | SY | 6 | $12.00 | $7.00 to $25.00 | Bids- 2026-03-11 · LaDOTD · LA 1026: CREEK BRIDGE · $1.00 per SY · qty 1,232 · bid tab outlier, not in the median
- 2025-10-15 · LaDOTD · CENTERVILLE ST. NW IMPROVEMENTS · $12.00 per SY · qty 1,868 · bid tab
- 2025-08-13 · LaDOTD · LA 442: LA 63 - W. JCT. LA 441 · $25.00 per SY · qty 792 · bid tab
- 2025-08-13 · LaDOTD · LA 442: LA 63 - W. JCT. LA 441 · $12.00 per SY · qty 39,786 · bid tab
- 2025-01-08 · LaDOTD · LA 3002: U-TURN · $7.00 per SY · qty 506 · bid tab
- 2024-12-11 · LaDOTD · W. COLYELL BRIDGE REPLACEMENT · $10.00 per SY · qty 1,559 · bid tab
|
| Lime cement stabilization | TON | 4 | $462.50 | $325.00 to $600.00 | Bids- 2026-03-11 · LaDOTD · LA 1026: CREEK BRIDGE · $10.00 per TON · qty 17.45 · bid tab outlier, not in the median
- 2025-10-15 · LaDOTD · CENTERVILLE ST. NW IMPROVEMENTS · $12.00 per TON · qty 26.44 · bid tab outlier, not in the median
- 2025-01-08 · LaDOTD · LA 3002: U-TURN · $325.00 per TON · qty 7.18 · bid tab
- 2024-12-11 · LaDOTD · W. COLYELL BRIDGE REPLACEMENT · $600.00 per TON · qty 22.10 · bid tab
|
| Manhole | EA | 10 | $1,800.00 | $900.00 to $4,500.00 | Bids- 2026-05-13 · LaDOTD · I-12: HOG BRANCH BRIDGE REPLACEMENT · $30,000.00 per EA · qty 2 · bid tab outlier, not in the median
- 2026-04-08 · LaDOTD · I-12: ESSEN LANE TO WALKER ROAD ITS RAMP METER UPGRADES · $1,508.00 per EA · qty 2 · bid tab multi-county contract
- 2026-04-08 · LaDOTD · I-12: ESSEN LANE TO WALKER ROAD ITS RAMP METER UPGRADES · $900.00 per EA · qty 4 · bid tab multi-county contract
- 2026-04-08 · LaDOTD · I-12: ESSEN LANE TO WALKER ROAD ITS RAMP METER UPGRADES · $1,242.00 per EA · qty 1 · bid tab multi-county contract
- 2025-10-15 · LaDOTD · CENTERVILLE ST. NW IMPROVEMENTS · $1,335.00 per EA · qty 8 · bid tab
- 2025-10-15 · LaDOTD · CENTERVILLE ST. NW IMPROVEMENTS · $3,278.00 per EA · qty 4 · bid tab
- 2025-10-15 · LaDOTD · CENTERVILLE ST. NW IMPROVEMENTS · $3,660.00 per EA · qty 2 · bid tab
- 2025-10-15 · LaDOTD · CENTERVILLE ST. NW IMPROVEMENTS · $2,830.00 per EA · qty 1 · bid tab
- 2025-03-12 · LaDOTD · LA 43: I-12 - US 190 · $1,800.00 per EA · qty 1 · bid tab
- 2025-01-08 · LaDOTD · LA 3002: U-TURN · $4,500.00 per EA · qty 1 · bid tab
|
| Sidewalk | EA | 1 | $784.00 | $784.00 to $784.00 | Bids- 2025-10-15 · LaDOTD · CENTERVILLE ST. NW IMPROVEMENTS · $784.00 per EA · qty 6 · bid tab
|