| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| Asphalt pavement | TON | 31 | $170.64 | $115.00 to $431.00 | Bids- 2026-06-30 · LaDOTD · BANKENS ROAD OVER BAYOU ARCENEAUX · $214.00 per TON · qty 283 · bid tab
- 2026-06-10 · LaDOTD · LA 109: GULLY BRIDGE · $250.00 per TON · qty 305.30 · bid tab
- 2026-06-10 · LaDOTD · LA 109: GULLY BRIDGE · $1,950.00 per TON · qty 2.80 · bid tab outlier, not in the median
- 2026-04-08 · LaDOTD · LA 397: LA 14 - US 90 · $170.00 per TON · qty 1,233.30 · bid tab
- 2026-04-08 · LaDOTD · LA 397: LA 14 - US 90 · $121.00 per TON · qty 8,779.10 · bid tab
- 2026-04-08 · LaDOTD · US 90X: BROAD ST. - FRUGE RD. (PAMCO RD) · $198.00 per TON · qty 3,776.10 · bid tab
- 2025-12-10 · LaDOTD · LA 1256 @ PATCH ST/W. CAL BLVD INT IMPR · $260.00 per TON · qty 779.40 · bid tab
- 2025-11-12 · LaDOTD · LA 14: LA 397 - GERSTNER MEMORIAL · $131.50 per TON · qty 4,986 · bid tab
- 2025-11-12 · LaDOTD · LA 14: LA 397 - GERSTNER MEMORIAL · $154.00 per TON · qty 1,367.50 · bid tab
- 2025-11-12 · LaDOTD · LA 14: LA 397 - GERSTNER MEMORIAL · $145.00 per TON · qty 9,486.10 · bid tab
(10 most recent of 31 shown; all in the Hubstake feed) |
| Concrete pavement | SY | 7 | $75.00 | $27.00 to $260.00 | Bids- 2026-06-10 · LaDOTD · LA 1138-2: LAKE ST. - RYAN ST. · $75.00 per SY · qty 296.80 · bid tab
- 2026-04-08 · LaDOTD · US 90X: BROAD ST. - FRUGE RD. (PAMCO RD) · $13.50 per SY · qty 8,108.90 · bid tab outlier, not in the median
- 2026-04-08 · LaDOTD · US 90X: BROAD ST. - FRUGE RD. (PAMCO RD) · $10.00 per SY · qty 8,108.90 · bid tab outlier, not in the median
- 2025-10-15 · LaDOTD · LA3092: GAUTHIER RD @ LAKE ST ROUNDABOUT · $260.00 per SY · qty 468.70 · bid tab
- 2024-11-13 · LaDOTD · LA 397: US 90 - 400' N LEBLEU CEMETERY RD · $188.00 per SY · qty 253.60 · bid tab
- 2024-11-13 · LaDOTD · LA 397: US 90 - 400' N LEBLEU CEMETERY RD · $33.50 per SY · qty 1,293.80 · bid tab
- 2024-07-10 · LaDOTD · LA 14: POWER CENTER PKWY - US 90 · $27.00 per SY · qty 5,336.50 · bid tab
|
| Curb gutter | LF | 20 | $47.98 | $20.00 to $175.00 | Bids- 2026-06-10 · LaDOTD · LA 1138-2: LAKE ST. - RYAN ST. · $65.00 per LF · qty 782 · bid tab
- 2026-06-10 · LaDOTD · LA 1138-2: LAKE ST. - RYAN ST. · $20.00 per LF · qty 1,957 · bid tab
- 2026-04-08 · LaDOTD · LA 397: LA 14 - US 90 · $175.00 per LF · qty 54 · bid tab
- 2026-04-08 · LaDOTD · US 90X: BROAD ST. - FRUGE RD. (PAMCO RD) · $97.00 per LF · qty 117 · bid tab
- 2026-04-08 · LaDOTD · US 90X: BROAD ST. - FRUGE RD. (PAMCO RD) · $40.00 per LF · qty 1,211 · bid tab
- 2026-02-11 · LaDOTD · US 171: US 90 - MOELING · $100.00 per LF · qty 27 · bid tab
- 2026-02-11 · LaDOTD · US 171: US 90 - MOELING · $150.00 per LF · qty 238 · bid tab
- 2025-12-10 · LaDOTD · LA 1256 @ PATCH ST/W. CAL BLVD INT IMPR · $135.00 per LF · qty 114 · bid tab
- 2025-11-12 · LaDOTD · LA 14: LA 397 - GERSTNER MEMORIAL · $32.00 per LF · qty 188.76 · bid tab
- 2025-10-15 · LaDOTD · LA3092: GAUTHIER RD @ LAKE ST ROUNDABOUT · $25.00 per LF · qty 1,744.80 · bid tab
(10 most recent of 20 shown; all in the Hubstake feed) |
| Excavation embankment | CY | 15 | $47.50 | $22.55 to $112.00 | Bids- 2026-09-17 · LaDOTD · LA 14: DITCH CLEANING AND GRADING · $45.00 per CY · qty 35 · bid tab
- 2026-06-30 · LaDOTD · BANKENS ROAD OVER BAYOU ARCENEAUX · $41.50 per CY · qty 517 · bid tab
- 2026-06-10 · LaDOTD · LA 109: GULLY BRIDGE · $82.25 per CY · qty 336 · bid tab
- 2026-04-08 · LaDOTD · LA 397: LA 14 - US 90 · $170.00 per CY · qty 100 · bid tab outlier, not in the median
- 2025-12-10 · LaDOTD · LA 1256 @ PATCH ST/W. CAL BLVD INT IMPR · $112.00 per CY · qty 9 · bid tab
- 2025-11-12 · LaDOTD · LA 14: LA 397 - GERSTNER MEMORIAL · $157.00 per CY · qty 266 · bid tab outlier, not in the median
- 2025-11-12 · LaDOTD · LA 14: LA 397 - GERSTNER MEMORIAL · $125.00 per CY · qty 87.50 · bid tab outlier, not in the median
- 2025-10-15 · LaDOTD · LA3092: GAUTHIER RD @ LAKE ST ROUNDABOUT · $30.00 per CY · qty 2,272 · bid tab
- 2025-09-10 · LaDOTD · US 90: LA 397 - JEFFERSON DAVIS P/L · $60.00 per CY · qty 230 · bid tab
- 2025-09-10 · LaDOTD · US 90: LA 397 - JEFFERSON DAVIS P/L · $45.00 per CY · qty 62 · bid tab
(10 most recent of 15 shown; all in the Hubstake feed) |
| Flexible base | SY | 5 | $46.50 | $13.20 to $78.00 | Bids- 2026-06-10 · LaDOTD · LA 109: GULLY BRIDGE · $55.00 per SY · qty 1,449.80 · bid tab
- 2025-10-15 · LaDOTD · LA3092: GAUTHIER RD @ LAKE ST ROUNDABOUT · $78.00 per SY · qty 5,141.10 · bid tab
- 2025-02-27 · LaDOTD · Drainage System Repairs · $46.50 per SY · qty 47.90 · bid tab
- 2024-03-13 · LaDOTD · DIST 07 HQ BLDG · $13.20 per SY · qty 4,242.50 · bid tab
- 2023-12-13 · LaDOTD · DIST 07 HQ BLDG · $18.86 per SY · qty 4,242.50 · bid tab
|
| Inlet headwall | EA | 4 | $21,000.00 | $20,000.00 to $22,000.00 | Bids- 2026-06-30 · LaDOTD · BANKENS ROAD OVER BAYOU ARCENEAUX · $60,000.00 per EA · qty 2 · bid tab outlier, not in the median
- 2026-06-10 · LaDOTD · LA 109: GULLY BRIDGE · $45,000.00 per EA · qty 2 · bid tab outlier, not in the median
- 2025-11-12 · LaDOTD · LA 14: LA 397 - GERSTNER MEMORIAL · $20,000.00 per EA · qty 2 · bid tab
- 2025-11-12 · LaDOTD · LA 14: LA 397 - GERSTNER MEMORIAL · $22,000.00 per EA · qty 2 · bid tab
|
| Lime cement stabilization | SY | 2 | $5.00 | $4.00 to $6.00 | Bids- 2026-06-30 · LaDOTD · BANKENS ROAD OVER BAYOU ARCENEAUX · $6.00 per SY · qty 1,285.90 · bid tab
- 2026-06-10 · LaDOTD · LA 109: GULLY BRIDGE · $4.00 per SY · qty 1,450 · bid tab
|
| Lime cement stabilization | TON | 2 | $237.50 | $225.00 to $250.00 | Bids- 2026-06-30 · LaDOTD · BANKENS ROAD OVER BAYOU ARCENEAUX · $225.00 per TON · qty 18.23 · bid tab
- 2026-06-10 · LaDOTD · LA 109: GULLY BRIDGE · $250.00 per TON · qty 20.55 · bid tab
|
| Manhole | EA | 14 | $6,400.00 | $1,953.54 to $15,485.00 | Bids- 2026-06-10 · LaDOTD · LA 109: GULLY BRIDGE · $8,000.00 per EA · qty 1 · bid tab
- 2025-11-12 · LaDOTD · LA 14: LA 397 - GERSTNER MEMORIAL · $5,400.00 per EA · qty 8 · bid tab
- 2024-11-13 · LaDOTD · LAKE CHARLES SRTS PROJ. - BARBE ELEM. · $8,500.00 per EA · qty 1 · bid tab
- 2024-09-18 · LaDOTD · LA 397: GAYLE RD - LA 27 · $12,524.00 per EA · qty 4 · bid tab
- 2024-08-14 · LaDOTD · I-210 HURRICANE LAURA LIGHTING REPAIRS · $2,000.00 per EA · qty 50 · bid tab
- 2024-08-14 · LaDOTD · I-210 HURRICANE LAURA LIGHTING REPAIRS · $23,490.00 per EA · qty 49 · bid tab outlier, not in the median
- 2024-08-14 · LaDOTD · I-210 HURRICANE LAURA LIGHTING REPAIRS · $1,953.54 per EA · qty 24 · bid tab
- 2024-08-14 · LaDOTD · I-210 HURRICANE LAURA LIGHTING REPAIRS · $13,850.00 per EA · qty 8 · bid tab
- 2024-08-14 · LaDOTD · I-210 HURRICANE LAURA LIGHTING REPAIRS · $15,485.00 per EA · qty 1 · bid tab
- 2024-08-14 · LaDOTD · I-210 HURRICANE LAURA LIGHTING REPAIRS · $2,279.75 per EA · qty 5 · bid tab
(10 most recent of 14 shown; all in the Hubstake feed) |
| Sidewalk | EA | 3 | $757.00 | $605.00 to $909.00 | Bids- 2025-08-13 · LaDOTD · US 90 & LA 3256: ASPHALT OVERLAYS · $909.00 per EA · qty 1 · bid tab
- 2024-03-13 · LaDOTD · DIST 07 HQ BLDG · $605.00 per EA · qty 7 · bid tab
- 2023-12-13 · LaDOTD · DIST 07 HQ BLDG · $538.90 per EA · qty 7 · bid tab outlier, not in the median
|