Site-work prices, Goshen County, WY
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | CY | 1 | $4.25 | $4.25 to $4.25 | Bids- 2024-10-10 · WYDOT · Guernsey - Fort Laramie (US 26) · $4.25 per CY · qty 1740.0 · bid tab
|
| asphalt pavement | TON | 12 | $410.56 | $57.00 to $970.00 | Bids- 2024-10-10 · WYDOT · Guernsey - Fort Laramie (US 26) · $59.00 per TON · qty 20720.0 · bid tab
- 2024-10-10 · WYDOT · Guernsey - Fort Laramie (US 26) · $57.00 per TON · qty 9566.0 · bid tab
- 2024-10-10 · WYDOT · Guernsey - Fort Laramie (US 26) · $175.00 per TON · qty 825.0 · bid tab
- 2024-10-10 · WYDOT · Guernsey - Fort Laramie (US 26) · $970.00 per TON · qty 225.0 · bid tab
- 2024-10-10 · WYDOT · Guernsey - Fort Laramie (US 26) · $735.00 per TON · qty 2006.0 · bid tab
- 2024-04-11 · WYDOT · Torrington - Nebraska State Line · $80.00 per TON · qty 12800.0 · bid tab
- 2024-04-11 · WYDOT · Torrington - Nebraska State Line · $183.00 per TON · qty 615.0 · bid tab
- 2024-04-11 · WYDOT · Torrington - Nebraska State Line · $680.00 per TON · qty 737.0 · bid tab
- 2024-04-11 · WYDOT · Torrington - Nebraska State Line · $850.00 per TON · qty 150.0 · bid tab
- 2023-12-14 · WYDOT · Cheyenne - Hawk Springs (Hawk Springs South) · $800.30 per TON · qty 165.0 · bid tab
(10 most recent of 12 shown; all in the Hubstake feed) |
| curb gutter | FT | 1 | $48.00 | $48.00 to $48.00 | Bids- 2024-10-10 · WYDOT · Guernsey - Fort Laramie (US 26) · $48.00 per FT · qty 641.0 · bid tab
|
| lime cement stabilization | TON | 3 | $240.00 | $159.00 to $265.00 | Bids- 2024-10-10 · WYDOT · Guernsey - Fort Laramie (US 26) · $265.00 per TON · qty 294.0 · bid tab
- 2024-04-11 · WYDOT · Torrington - Nebraska State Line · $240.00 per TON · qty 123.0 · bid tab
- 2023-12-14 · WYDOT · Cheyenne - Hawk Springs (Hawk Springs South) · $159.00 per TON · qty 142.0 · bid tab
|
| sidewalk | SY | 1 | $70.00 | $70.00 to $70.00 | Bids- 2024-10-10 · WYDOT · Guernsey - Fort Laramie (US 26) · $70.00 per SY · qty 509.0 · bid tab
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.