| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | CY | 3 | $12.00 | $6.65 to $13.50 | Bids- 2026-03-12 · WYDOT · Buffalo - Gillette (Rawhide Creek) · $13.50 per CY · qty 1620.0 · bid tab
- 2025-03-13 · WYDOT · Gillette – Moorcroft (Rozet Section) · $6.65 per CY · qty 3560.0 · bid tab
- 2023-12-14 · WYDOT · Gillette - Savageton (Hoe Springs Section) · $12.00 per CY · qty 2540.0 · bid tab
|
| asphalt pavement | TON | 15 | $128.00 | $59.00 to $700.00 | Bids- 2026-09-10 · WYDOT · Gillette - Montana State Line (Olmstead Creek Section) · $175.00 per TON · qty 820.0 · bid tab
- 2026-09-10 · WYDOT · Gillette - Montana State Line (Olmstead Creek Section) · $98.00 per TON · qty 26738.0 · bid tab
- 2026-09-10 · WYDOT · Gillette - Montana State Line (Olmstead Creek Section) · $80.00 per TON · qty 9630.0 · bid tab
- 2026-09-10 · WYDOT · Gillette - Montana State Line (Olmstead Creek Section) · $670.00 per TON · qty 2043.0 · bid tab
- 2026-09-10 · WYDOT · Gillette - Montana State Line (Olmstead Creek Section) · $165.00 per TON · qty 634.0 · bid tab
- 2026-03-12 · WYDOT · Buffalo - Gillette (Rawhide Creek) · $180.00 per TON · qty 292.0 · bid tab
- 2026-03-12 · WYDOT · Buffalo - Gillette (Rawhide Creek) · $560.00 per TON · qty 527.0 · bid tab
- 2026-03-12 · WYDOT · Buffalo - Gillette (Rawhide Creek) · $67.00 per TON · qty 6310.0 · bid tab
- 2026-03-12 · WYDOT · Buffalo - Gillette (Rawhide Creek) · $65.00 per TON · qty 2940.0 · bid tab
- 2025-03-13 · WYDOT · Gillette – Moorcroft (Rozet Section) · $128.00 per TON · qty 395.0 · bid tab
(10 most recent of 15 shown; all in the Hubstake feed) |
| concrete pavement | SY | 1 | $166.00 | $166.00 to $166.00 | Bids- 2025-08-14 · WYDOT · Gillette Streets (WYO 59 & US 14/16) · $166.00 per SY · qty 4350.0 · bid tab
|
| curb gutter | FT | 1 | $95.00 | $95.00 to $95.00 | Bids- 2025-08-14 · WYDOT · Gillette Streets (WYO 59 & US 14/16) · $95.00 per FT · qty 360.0 · bid tab
|
| excavation embankment | CY | 1 | $3.25 | $3.25 to $3.25 | Bids- 2026-09-10 · WYDOT · Gillette - Montana State Line (Olmstead Creek Section) · $3.25 per CY · qty 181424.0 · bid tab
|
| inlet headwall | EA | 1 | $16,500.00 | $16,500.00 to $16,500.00 | Bids- 2024-05-09 · WYDOT · District 4 Culvert Lining (Buffalo - Gillette) · $16,500.00 per EA · qty 1.0 · bid tab
|
| lime cement stabilization | TON | 4 | $245.00 | $235.00 to $300.00 | Bids- 2026-09-10 · WYDOT · Gillette - Montana State Line (Olmstead Creek Section) · $300.00 per TON · qty 350.0 · bid tab
- 2026-03-12 · WYDOT · Buffalo - Gillette (Rawhide Creek) · $250.00 per TON · qty 90.0 · bid tab
- 2025-03-13 · WYDOT · Gillette – Moorcroft (Rozet Section) · $235.00 per TON · qty 185.0 · bid tab
- 2023-12-14 · WYDOT · Gillette - Savageton (Hoe Springs Section) · $240.00 per TON · qty 85.0 · bid tab
|
| storm pipe 18-inch | FT | 2 | $101.00 | $95.00 to $107.00 | Bids- 2026-09-10 · WYDOT · Gillette - Montana State Line (Olmstead Creek Section) · $107.00 per FT · qty 636.0 · bid tab
- 2024-05-09 · WYDOT · District 4 Culvert Lining (Buffalo - Gillette) · $95.00 per FT · qty 2480.0 · bid tab
|
| storm pipe 24-inch | FT | 2 | $143.50 | $140.00 to $147.01 | Bids- 2026-09-10 · WYDOT · Gillette - Montana State Line (Olmstead Creek Section) · $147.01 per FT · qty 168.0 · bid tab
- 2024-05-09 · WYDOT · District 4 Culvert Lining (Buffalo - Gillette) · $140.00 per FT · qty 1300.0 · bid tab
|
| storm pipe 30-inch | FT | 3 | $180.00 | $164.18 to $255.00 | Bids- 2026-09-10 · WYDOT · Gillette - Montana State Line (Olmstead Creek Section) · $164.18 per FT · qty 268.0 · bid tab
- 2024-05-09 · WYDOT · District 4 Culvert Lining (Buffalo - Gillette) · $255.00 per FT · qty 420.0 · bid tab
- 2024-05-09 · WYDOT · District 4 Culvert Lining (Buffalo - Gillette) · $180.00 per FT · qty 10.0 · bid tab
|
| storm pipe 36-inch | FT | 2 | $230.75 | $186.50 to $275.00 | Bids- 2026-09-10 · WYDOT · Gillette - Montana State Line (Olmstead Creek Section) · $186.50 per FT · qty 34.0 · bid tab
- 2024-05-09 · WYDOT · District 4 Culvert Lining (Buffalo - Gillette) · $275.00 per FT · qty 550.0 · bid tab
|
| storm pipe 42-inch | FT | 2 | $278.75 | $172.50 to $385.00 | Bids- 2026-09-10 · WYDOT · Gillette - Montana State Line (Olmstead Creek Section) · $172.50 per FT · qty 50.0 · bid tab
- 2024-05-09 · WYDOT · District 4 Culvert Lining (Buffalo - Gillette) · $385.00 per FT · qty 160.0 · bid tab
|
| storm pipe 48-inch | FT | 1 | $198.00 | $198.00 to $198.00 | Bids- 2026-09-10 · WYDOT · Gillette - Montana State Line (Olmstead Creek Section) · $198.00 per FT · qty 40.0 · bid tab
|
| storm pipe 78-inch | FT | 1 | $1,806.00 | $1,806.00 to $1,806.00 | Bids- 2026-09-10 · WYDOT · Gillette - Montana State Line (Olmstead Creek Section) · $1,806.00 per FT · qty 214.0 · bid tab
|