Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| asphalt pavement | SY | 1 | $131.11 | $131.11 to $131.11 | Bids
|
| asphalt pavement | TON | 2 | $90.79 | $86.42 to $95.16 | |
| curb gutter | LF | 3 | $20.00 | $0.82 to $28.00 | |
| excavation embankment | CY | 1 | $13.29 | $13.29 to $13.29 | Bids
|
| inlet headwall | EACH | 2 | $1,213.00 | $1,213.00 to $1,213.00 | |
| manhole | EACH | 1 | $1,200.00 | $1,200.00 to $1,200.00 | Bids
|
| sidewalk | EACH | 2 | $320.64 | $215.00 to $426.28 | |
| sidewalk | SF | 2 | $36.75 | $8.50 to $65.00 | |
| sidewalk | SY | 1 | $81.00 | $81.00 to $81.00 | Bids
|
| storm pipe 12-inch | LF | 1 | $224.93 | $224.93 to $224.93 | Bids
|
| storm pipe 15-inch | LF | 1 | $121.94 | $121.94 to $121.94 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.