| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | SY | 9 | $43.10 | $3.67 to $72.65 | Bids- 2026-05-12 · WisDOT · 20260512015 · $17.45 per SY · qty 270.0 · bid tab
- 2026-05-12 · WisDOT · 20260512015 · $59.52 per SY · qty 11.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $20.00 per SY · qty 193.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $62.41 per SY · qty 33.0 · bid tab
- 2025-12-09 · WisDOT · 20251209043 · $58.17 per SY · qty 12.0 · bid tab
- 2025-03-11 · WisDOT · 20250311040 · $6.25 per SY · qty 3750.0 · bid tab
- 2025-03-11 · WisDOT · 20250311040 · $43.10 per SY · qty 460.0 · bid tab
- 2024-02-13 · WisDOT · 20240213038 · $3.67 per SY · qty 162902.0 · bid tab
- 2024-02-13 · WisDOT · 20240213038 · $72.65 per SY · qty 16.0 · bid tab
|
| asphalt pavement | TON | 27 | $135.17 | $4.09 to $356.02 | Bids- 2026-05-12 · WisDOT · 20260512015 · $155.21 per TON · qty 1639.0 · bid tab
- 2026-05-12 · WisDOT · 20260512015 · $89.30 per TON · qty 25732.0 · bid tab
- 2026-05-12 · WisDOT · 20260512015 · $94.43 per TON · qty 22125.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $126.67 per TON · qty 1535.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $135.17 per TON · qty 356.0 · bid tab
- 2026-01-13 · WisDOT · 20260113050 · $215.60 per TON · qty 50.0 · bid tab
- 2025-12-09 · WisDOT · 20251209043 · $174.91 per TON · qty 86.0 · bid tab
- 2025-11-11 · WisDOT · 20251111027 · $94.48 per TON · qty 15550.0 · bid tab
- 2025-11-11 · WisDOT · 20251111027 · $99.36 per TON · qty 13791.0 · bid tab
- 2025-11-11 · WisDOT · 20251111027 · $356.02 per TON · qty 22.0 · bid tab
(10 most recent of 27 shown; all in the Hubstake feed) |
| concrete pavement | DOL | 3 | $1.00 | $1.00 to $1.00 | Bids- 2026-01-13 · WisDOT · 20260113050 · $1.00 per DOL · qty 150.0 · bid tab
- 2025-03-11 · WisDOT · 20250311040 · $1.00 per DOL · qty 548.0 · bid tab
- 2025-01-14 · WisDOT · 20250114031 · $1.00 per DOL · qty 1000.0 · bid tab
|
| concrete pavement | LF | 2 | $3.50 | $2.00 to $5.00 | Bids- 2026-01-13 · WisDOT · 20260113050 · $5.00 per LF · qty 45.0 · bid tab
- 2025-03-11 · WisDOT · 20250311040 · $2.00 per LF · qty 415.0 · bid tab
|
| concrete pavement | SY | 9 | $127.29 | $74.68 to $288.37 | Bids- 2026-02-10 · WisDOT · 20260210035 · $105.00 per SY · qty 61.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $240.00 per SY · qty 103.0 · bid tab
- 2026-01-13 · WisDOT · 20260113050 · $123.78 per SY · qty 35.0 · bid tab
- 2026-01-13 · WisDOT · 20260113050 · $279.70 per SY · qty 120.0 · bid tab
- 2025-03-11 · WisDOT · 20250311040 · $109.42 per SY · qty 250.0 · bid tab
- 2025-03-11 · WisDOT · 20250311040 · $171.00 per SY · qty 1170.0 · bid tab
- 2025-03-11 · WisDOT · 20250311040 · $74.68 per SY · qty 405.0 · bid tab
- 2025-01-14 · WisDOT · 20250114031 · $127.29 per SY · qty 84.0 · bid tab
- 2025-01-14 · WisDOT · 20250114031 · $288.37 per SY · qty 194.0 · bid tab
|
| curb gutter | LF | 37 | $32.17 | $1.00 to $101.25 | Bids- 2026-05-12 · WisDOT · 20260512015 · $73.00 per LF · qty 155.0 · bid tab
- 2026-05-12 · WisDOT · 20260512015 · $71.15 per LF · qty 30.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $22.00 per LF · qty 864.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $1.00 per LF · qty 1005.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $65.00 per LF · qty 144.0 · bid tab
- 2026-01-13 · WisDOT · 20260113050 · $64.24 per LF · qty 45.0 · bid tab
- 2026-01-13 · WisDOT · 20260113050 · $50.00 per LF · qty 561.0 · bid tab
- 2026-01-13 · WisDOT · 20260113050 · $11.00 per LF · qty 65.0 · bid tab
- 2026-01-13 · WisDOT · 20260113050 · $2.00 per LF · qty 215.0 · bid tab
- 2026-01-13 · WisDOT · 20260113050 · $64.24 per LF · qty 215.0 · bid tab
(10 most recent of 37 shown; all in the Hubstake feed) |
| excavation embankment | CY | 12 | $20.88 | $14.40 to $39.50 | Bids- 2026-05-12 · WisDOT · 20260512015 · $20.33 per CY · qty 6169.0 · bid tab
- 2026-05-12 · WisDOT · 20260512015 · $22.69 per CY · qty 551.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $20.00 per CY · qty 4040.0 · bid tab
- 2025-12-09 · WisDOT · 20251209043 · $15.50 per CY · qty 168.0 · bid tab
- 2025-10-14 · WisDOT · 20251014026 · $19.00 per CY · qty 2503.0 · bid tab
- 2025-10-14 · WisDOT · 20251014027 · $14.40 per CY · qty 271.0 · bid tab
- 2025-05-13 · WisDOT · 20250513038 · $21.10 per CY · qty 90.0 · bid tab
- 2025-05-13 · WisDOT · 20250513038 · $20.65 per CY · qty 177.0 · bid tab
- 2025-03-11 · WisDOT · 20250311040 · $39.50 per CY · qty 151.0 · bid tab
- 2024-11-12 · WisDOT · 20241112046 · $30.00 per CY · qty 99.0 · bid tab
(10 most recent of 12 shown; all in the Hubstake feed) |
| inlet headwall | EACH | 8 | $1,060.00 | $950.00 to $2,460.00 | Bids- 2026-02-10 · WisDOT · 20260210035 · $1,175.00 per EACH · qty 1.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $1,060.00 per EACH · qty 2.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $1,060.00 per EACH · qty 3.0 · bid tab
- 2025-10-14 · WisDOT · 20251014026 · $950.00 per EACH · qty 5.0 · bid tab
- 2025-03-11 · WisDOT · 20250311040 · $1,230.00 per EACH · qty 4.0 · bid tab
- 2025-03-11 · WisDOT · 20250311040 · $2,460.00 per EACH · qty 4.0 · bid tab
- 2025-03-11 · WisDOT · 20250311040 · $995.00 per EACH · qty 3.0 · bid tab
- 2023-11-14 · WisDOT · 20231114044 · $950.00 per EACH · qty 3.0 · bid tab
|
| lime cement stabilization | ACRE | 1 | $11,000.00 | $11,000.00 to $11,000.00 | Bids- 2025-05-13 · WisDOT · 20250513038 · $11,000.00 per ACRE · qty 0.07 · bid tab
|
| manhole | EACH | 6 | $2,325.00 | $700.00 to $7,500.00 | Bids- 2026-02-10 · WisDOT · 20260210035 · $1,950.00 per EACH · qty 1.0 · bid tab
- 2025-10-14 · WisDOT · 20251014026 · $700.00 per EACH · qty 2.0 · bid tab
- 2025-10-14 · WisDOT · 20251014026 · $700.00 per EACH · qty 1.0 · bid tab
- 2025-10-14 · WisDOT · 20251014026 · $5,000.00 per EACH · qty 1.0 · bid tab
- 2025-10-14 · WisDOT · 20251014026 · $7,500.00 per EACH · qty 2.0 · bid tab
- 2024-11-12 · WisDOT · 20241112046 · $2,700.00 per EACH · qty 9.0 · bid tab
|
| sidewalk | EACH | 11 | $200.00 | $10.00 to $4,000.00 | Bids- 2026-02-10 · WisDOT · 20260210035 · $50.00 per EACH · qty 1.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $100.00 per EACH · qty 1.0 · bid tab
- 2026-01-13 · WisDOT · 20260113050 · $2,300.00 per EACH · qty 1.0 · bid tab
- 2025-11-11 · WisDOT · 20251111027 · $500.00 per EACH · qty 1.0 · bid tab
- 2025-11-11 · WisDOT · 20251111027 · $100.00 per EACH · qty 6.0 · bid tab
- 2025-10-14 · WisDOT · 20251014026 · $1,250.00 per EACH · qty 1.0 · bid tab
- 2025-10-14 · WisDOT · 20251014026 · $200.00 per EACH · qty 5.0 · bid tab
- 2024-11-12 · WisDOT · 20241112046 · $10.00 per EACH · qty 47.0 · bid tab
- 2024-11-12 · WisDOT · 20241112046 · $4,000.00 per EACH · qty 1.0 · bid tab
- 2023-11-14 · WisDOT · 20231114044 · $400.00 per EACH · qty 1.0 · bid tab
(10 most recent of 11 shown; all in the Hubstake feed) |
| sidewalk | SF | 13 | $20.31 | $8.00 to $74.30 | Bids- 2026-02-10 · WisDOT · 20260210035 · $8.25 per SF · qty 5128.0 · bid tab
- 2026-01-13 · WisDOT · 20260113050 · $15.16 per SF · qty 325.0 · bid tab
- 2025-11-11 · WisDOT · 20251111027 · $20.31 per SF · qty 928.0 · bid tab
- 2025-11-11 · WisDOT · 20251111027 · $74.30 per SF · qty 84.0 · bid tab
- 2025-11-11 · WisDOT · 20251111027 · $60.61 per SF · qty 10.0 · bid tab
- 2025-10-14 · WisDOT · 20251014026 · $8.00 per SF · qty 4280.0 · bid tab
- 2025-10-14 · WisDOT · 20251014026 · $60.00 per SF · qty 60.0 · bid tab
- 2025-10-14 · WisDOT · 20251014026 · $12.00 per SF · qty 212.0 · bid tab
- 2024-11-12 · WisDOT · 20241112046 · $9.34 per SF · qty 29362.0 · bid tab
- 2024-11-12 · WisDOT · 20241112046 · $67.84 per SF · qty 68.0 · bid tab
(10 most recent of 13 shown; all in the Hubstake feed) |
| sidewalk | SY | 2 | $86.65 | $78.80 to $94.50 | Bids- 2026-02-10 · WisDOT · 20260210035 · $94.50 per SY · qty 24.0 · bid tab
- 2024-11-12 · WisDOT · 20241112046 · $78.80 per SY · qty 537.0 · bid tab
|
| storm pipe 12-inch | LF | 3 | $97.00 | $69.00 to $145.00 | Bids- 2026-02-10 · WisDOT · 20260210035 · $69.00 per LF · qty 57.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $97.00 per LF · qty 32.0 · bid tab
- 2025-10-14 · WisDOT · 20251014026 · $145.00 per LF · qty 28.0 · bid tab
|
| storm pipe 15-inch | LF | 3 | $110.00 | $72.00 to $112.00 | Bids- 2026-02-10 · WisDOT · 20260210035 · $72.00 per LF · qty 80.0 · bid tab
- 2025-10-14 · WisDOT · 20251014026 · $112.00 per LF · qty 74.0 · bid tab
- 2023-11-14 · WisDOT · 20231114044 · $110.00 per LF · qty 92.0 · bid tab
|
| storm pipe 18-inch | LF | 4 | $75.94 | $43.85 to $200.00 | Bids- 2026-05-12 · WisDOT · 20260512015 · $65.88 per LF · qty 52.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $86.00 per LF · qty 41.0 · bid tab
- 2025-10-14 · WisDOT · 20251014026 · $200.00 per LF · qty 24.0 · bid tab
- 2025-03-11 · WisDOT · 20250311040 · $43.85 per LF · qty 378.0 · bid tab
|
| storm pipe 24-inch | LF | 4 | $204.06 | $122.50 to $264.11 | Bids- 2026-05-12 · WisDOT · 20260512015 · $248.11 per LF · qty 138.0 · bid tab
- 2026-05-12 · WisDOT · 20260512015 · $264.11 per LF · qty 56.0 · bid tab
- 2024-02-13 · WisDOT · 20240213038 · $122.50 per LF · qty 244.0 · bid tab
- 2024-02-13 · WisDOT · 20240213038 · $160.00 per LF · qty 64.0 · bid tab
|
| storm pipe 30-inch | LF | 3 | $263.48 | $107.00 to $296.02 | Bids- 2026-05-12 · WisDOT · 20260512015 · $263.48 per LF · qty 128.0 · bid tab
- 2026-05-12 · WisDOT · 20260512015 · $296.02 per LF · qty 56.0 · bid tab
- 2026-02-10 · WisDOT · 20260210035 · $107.00 per LF · qty 104.0 · bid tab
|
| storm pipe 36-inch | LF | 1 | $326.19 | $326.19 to $326.19 | Bids- 2026-05-12 · WisDOT · 20260512015 · $326.19 per LF · qty 14.0 · bid tab
|
| storm pipe 42-inch | LF | 1 | $409.24 | $409.24 to $409.24 | Bids- 2026-05-12 · WisDOT · 20260512015 · $409.24 per LF · qty 58.0 · bid tab
|
| storm pipe 6-inch | LF | 1 | $1,043.50 | $1,043.50 to $1,043.50 | Bids- 2026-05-12 · WisDOT · 20260512015 · $1,043.50 per LF · qty 74.0 · bid tab
|
| storm pipe 91-inch | LF | 1 | $916.11 | $916.11 to $916.11 | Bids- 2026-05-12 · WisDOT · 20260512015 · $916.11 per LF · qty 82.0 · bid tab
|