Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON6$189.64$127.16 to $225.81
Bids
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $204.78 per TON · qty 561.0 · bid tab
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $211.28 per TON · qty 1205.0 · bid tab
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $174.50 per TON · qty 1354.0 · bid tab
  • 2024-12-11 · VDOT (Hampton Roads (5)) · CM525PMF125606 · $225.81 per TON · qty 7293.4 · bid tab
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $127.16 per TON · qty 2021.0 · bid tab
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $159.69 per TON · qty 1298.0 · bid tab
curb gutterLF5$52.31$49.69 to $60.00
Bids
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $49.69 per LF · qty 131.0 · bid tab
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $52.31 per LF · qty 115.0 · bid tab
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $52.31 per LF · qty 2474.0 · bid tab
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $59.99 per LF · qty 2333.0 · bid tab
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $60.00 per LF · qty 593.0 · bid tab
excavation embankmentCY2$76.41$60.50 to $92.33
Bids
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $92.33 per CY · qty 800.0 · bid tab
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $60.50 per CY · qty 294.0 · bid tab
fire hydrantEA1$8,420.29$8,420.29 to $8,420.29
Bids
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $8,420.29 per EA · qty 1.0 · bid tab
inlet headwallEA16$10,572.24$5,753.78 to $13,218.23
Bids
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $5,753.78 per EA · qty 1.0 · bid tab
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $10,877.89 per EA · qty 2.0 · bid tab
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $12,185.58 per EA · qty 1.0 · bid tab
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $11,531.73 per EA · qty 2.0 · bid tab
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $11,400.94 per EA · qty 4.0 · bid tab
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $10,017.82 per EA · qty 5.0 · bid tab
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $10,266.58 per EA · qty 4.0 · bid tab
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $9,846.29 per EA · qty 1.0 · bid tab
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $10,910.32 per EA · qty 3.0 · bid tab
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $10,974.52 per EA · qty 3.0 · bid tab
(10 most recent of 16 shown; all in the Hubstake feed)
lime cement stabilizationSY1$3.21$3.21 to $3.21
Bids
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $3.21 per SY · qty 8260.0 · bid tab
lime cement stabilizationTON2$545.36$502.26 to $588.46
Bids
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $588.46 per TON · qty 7.2 · bid tab
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $502.26 per TON · qty 5.33 · bid tab
manholeEA3$5,063.86$3,269.19 to $5,471.89
Bids
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $3,269.19 per EA · qty 4.0 · bid tab
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $5,063.86 per EA · qty 7.0 · bid tab
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $5,471.89 per EA · qty 1.0 · bid tab
sewer main 8-inchLF1$172.79$172.79 to $172.79
Bids
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $172.79 per LF · qty 897.0 · bid tab
sewer serviceLF1$172.03$172.03 to $172.03
Bids
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $172.03 per LF · qty 260.0 · bid tab
storm pipe 15-inchLF2$221.12$147.24 to $295.00
Bids
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $295.00 per LF · qty 296.0 · bid tab
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $147.24 per LF · qty 1095.0 · bid tab
storm pipe 18-inchLF2$200.20$156.91 to $243.49
Bids
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $243.49 per LF · qty 124.0 · bid tab
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $156.91 per LF · qty 453.0 · bid tab
storm pipe 24-inchLF2$221.46$183.65 to $259.28
Bids
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $259.28 per LF · qty 137.0 · bid tab
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $183.65 per LF · qty 164.0 · bid tab
storm pipe 42-inchLF1$1,580.44$1,580.44 to $1,580.44
Bids
  • 2025-01-10 · VDOT (Hampton Roads (5)) · C0000111791C01C · $1,580.44 per LF · qty 9.0 · bid tab
water main 16-inchLF1$322.44$322.44 to $322.44
Bids
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $322.44 per LF · qty 344.0 · bid tab
water main 6-inchLF1$238.48$238.48 to $238.48
Bids
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $238.48 per LF · qty 17.0 · bid tab
water serviceLF1$73.61$73.61 to $73.61
Bids
  • 2023-11-15 · VDOT (Hampton Roads (5)) · C0000016314C01 · $73.61 per LF · qty 334.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.