Site-work prices, Culpeper County, VA

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON5$120.00$110.00 to $750.00
Bids
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127226N01 · $300.00 per TON · qty 20.0 · bid tab
  • 2025-10-22 · VDOT (Culpeper (7)) · C0000127926S01 · $750.00 per TON · qty 1.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $110.00 per TON · qty 575.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $120.00 per TON · qty 1050.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $110.00 per TON · qty 2240.0 · bid tab
curb gutterLF11$35.00$34.00 to $63.00
Bids
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127310N01 · $52.50 per LF · qty 62.0 · bid tab
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127310N01 · $42.00 per LF · qty 15.0 · bid tab
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127310N01 · $63.00 per LF · qty 763.0 · bid tab
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127310N01 · $63.00 per LF · qty 20.0 · bid tab
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127310N01 · $42.00 per LF · qty 465.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $35.00 per LF · qty 1352.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $34.00 per LF · qty 189.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $34.00 per LF · qty 310.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $35.00 per LF · qty 773.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $35.00 per LF · qty 6.0 · bid tab
(10 most recent of 11 shown; all in the Hubstake feed)
excavation embankmentCY4$32.50$20.00 to $100.00
Bids
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127226N01 · $100.00 per CY · qty 8.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $35.00 per CY · qty 7500.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $20.00 per CY · qty 999.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $30.00 per CY · qty 250.0 · bid tab
fire hydrantEA1$15,000.00$15,000.00 to $15,000.00
Bids
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $15,000.00 per EA · qty 1.0 · bid tab
inlet headwallEA5$8,000.00$8,000.00 to $14,000.00
Bids
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $14,000.00 per EA · qty 3.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $10,000.00 per EA · qty 1.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $8,000.00 per EA · qty 1.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $8,000.00 per EA · qty 6.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $8,000.00 per EA · qty 12.0 · bid tab
lime cement stabilizationTON1$300.00$300.00 to $300.00
Bids
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $300.00 per TON · qty 9.18 · bid tab
manholeEA12$4,003.09$2,000.00 to $30,000.00
Bids
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127310N01 · $5,108.34 per EA · qty 2.0 · bid tab
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127310N01 · $2,366.77 per EA · qty 10.0 · bid tab
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127310N01 · $4,869.23 per EA · qty 2.0 · bid tab
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127310N01 · $7,411.95 per EA · qty 2.0 · bid tab
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127310N01 · $3,106.99 per EA · qty 2.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $30,000.00 per EA · qty 1.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $2,000.00 per EA · qty 7.0 · bid tab
  • 2024-01-17 · VDOT (Culpeper (7)) · C0000124376N01 · $3,136.96 per EA · qty 2.0 · bid tab
  • 2024-01-17 · VDOT (Culpeper (7)) · C0000124376N01 · $5,502.97 per EA · qty 2.0 · bid tab
  • 2024-01-17 · VDOT (Culpeper (7)) · C0000124376N01 · $2,944.22 per EA · qty 2.0 · bid tab
(10 most recent of 12 shown; all in the Hubstake feed)
sidewalkEA4$563.06$447.37 to $719.24
Bids
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127310N01 · $515.60 per EA · qty 2.0 · bid tab
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127310N01 · $610.52 per EA · qty 2.0 · bid tab
  • 2024-01-17 · VDOT (Culpeper (7)) · C0000124376N01 · $447.37 per EA · qty 2.0 · bid tab
  • 2024-01-17 · VDOT (Culpeper (7)) · C0000124376N01 · $719.24 per EA · qty 2.0 · bid tab
sidewalkSY3$105.00$70.00 to $356.48
Bids
  • 2025-11-19 · VDOT (Culpeper (7)) · C0000127310N01 · $105.00 per SY · qty 303.0 · bid tab
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $70.00 per SY · qty 437.0 · bid tab
  • 2024-01-17 · VDOT (Culpeper (7)) · C0000124376N01 · $356.48 per SY · qty 10.0 · bid tab
storm pipe 15-inchLF1$160.00$160.00 to $160.00
Bids
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $160.00 per LF · qty 993.0 · bid tab
storm pipe 18-inchLF1$208.00$208.00 to $208.00
Bids
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $208.00 per LF · qty 327.0 · bid tab
storm pipe 24-inchLF1$294.00$294.00 to $294.00
Bids
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $294.00 per LF · qty 94.0 · bid tab
water main 12-inchLF1$500.00$500.00 to $500.00
Bids
  • 2025-01-22 · VDOT (Culpeper (7)) · C0000115474C01 · $500.00 per LF · qty 319.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.