Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON5$200.00$145.00 to $285.00
Bids
  • 2026-07-22 · VDOT (NOVa (9)) · C0000126560B40 · $250.00 per TON · qty 26.0 · bid tab
  • 2026-07-22 · VDOT (NOVa (9)) · C0000126560B40 · $145.00 per TON · qty 135.0 · bid tab
  • 2026-07-22 · VDOT (NOVa (9)) · C0000126560B40 · $190.00 per TON · qty 31.0 · bid tab
  • 2026-07-22 · VDOT (NOVa (9)) · C0000126560B40 · $285.00 per TON · qty 23.0 · bid tab
  • 2024-08-28 · VDOT (NOVa (9)) · C0000121702B35 · $200.00 per TON · qty 1080.0 · bid tab
curb gutterLF9$71.45$54.02 to $94.10
Bids
  • 2026-07-22 · VDOT (NOVa (9)) · C0000126560B40 · $66.00 per LF · qty 191.0 · bid tab
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $64.48 per LF · qty 828.0 · bid tab
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $71.45 per LF · qty 69.0 · bid tab
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $81.91 per LF · qty 749.0 · bid tab
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $92.36 per LF · qty 1253.0 · bid tab
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $83.65 per LF · qty 208.0 · bid tab
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $94.10 per LF · qty 208.0 · bid tab
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $60.99 per LF · qty 296.0 · bid tab
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $54.02 per LF · qty 1434.0 · bid tab
excavation embankmentCY1$100.00$100.00 to $100.00
Bids
  • 2024-08-28 · VDOT (NOVa (9)) · C0000124958N01 · $100.00 per CY · qty 45.0 · bid tab
flexible baseSY1$150.00$150.00 to $150.00
Bids
  • 2026-07-22 · VDOT (NOVa (9)) · C0000126560B40 · $150.00 per SY · qty 280.0 · bid tab
flexible baseTON1$180.00$180.00 to $180.00
Bids
  • 2026-07-22 · VDOT (NOVa (9)) · C0000126560B40 · $180.00 per TON · qty 47.0 · bid tab
inlet headwallEA1$6,670.00$6,670.00 to $6,670.00
Bids
  • 2026-07-22 · VDOT (NOVa (9)) · C0000126560B40 · $6,670.00 per EA · qty 1.0 · bid tab
manholeEA4$3,842.56$2,819.97 to $9,318.14
Bids
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $3,084.02 per EA · qty 19.0 · bid tab
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $4,601.10 per EA · qty 4.0 · bid tab
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $9,318.14 per EA · qty 2.0 · bid tab
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $2,819.97 per EA · qty 6.0 · bid tab
sidewalkEA1$306.20$306.20 to $306.20
Bids
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $306.20 per EA · qty 14.0 · bid tab
sidewalkSY3$124.00$109.79 to $142.90
Bids
  • 2026-07-22 · VDOT (NOVa (9)) · C0000126560B40 · $124.00 per SY · qty 6.0 · bid tab
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $142.90 per SY · qty 1009.0 · bid tab
  • 2024-12-11 · VDOT (NOVa (9)) · C0000125317N01 · $109.79 per SY · qty 3239.0 · bid tab