| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 18 | $128.00 | $96.00 to $205.00 | Bids- 2026-02-04 · TxDOT (Tyler district) · A00179604 · $145.00 per TON · qty 8931.0 · bid tab
- 2026-02-04 · TxDOT (Tyler district) · A00179604 · $196.00 per TON · qty 14134.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $150.00 per TON · qty 1862.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $125.00 per TON · qty 17169.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $130.00 per TON · qty 7323.0 · bid tab
- 2025-03-05 · TxDOT (Tyler district) · A00213858 · $131.00 per TON · qty 200.0 · bid tab
- 2025-03-05 · TxDOT (Tyler district) · A00213858 · $96.00 per TON · qty 500.0 · bid tab
- 2025-03-05 · TxDOT (Tyler district) · A00213858 · $121.00 per TON · qty 4000.0 · bid tab
- 2025-03-05 · TxDOT (Tyler district) · A00213858 · $125.00 per TON · qty 200.0 · bid tab
- 2025-03-05 · TxDOT (Tyler district) · A00213858 · $117.00 per TON · qty 4000.0 · bid tab
(10 most recent of 18 shown; all in the Hubstake feed) |
| curb gutter | LF | 2 | $48.50 | $46.00 to $51.00 | Bids- 2025-03-11 · TxDOT (Tyler district) · A00210436 · $46.00 per LF · qty 138.0 · bid tab
- 2025-03-11 · TxDOT (Tyler district) · A00210436 · $51.00 per LF · qty 522.0 · bid tab
|
| excavation embankment | CY | 7 | $25.00 | $17.00 to $65.00 | Bids- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $17.00 per CY · qty 25152.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $25.00 per CY · qty 1000.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $17.00 per CY · qty 9579.0 · bid tab
- 2025-01-08 · TxDOT (Tyler district) · A00187856 · $30.00 per CY · qty 136.0 · bid tab
- 2025-01-08 · TxDOT (Tyler district) · A00187856 · $20.00 per CY · qty 50.0 · bid tab
- 2025-01-07 · TxDOT (Tyler district) · A00178624 · $65.00 per CY · qty 120.0 · bid tab
- 2025-01-07 · TxDOT (Tyler district) · A00178624 · $35.00 per CY · qty 4622.0 · bid tab
|
| flexible base | CY | 6 | $51.00 | $23.00 to $60.00 | Bids- 2026-04-21 · TxDOT (Tyler district) · A00220493 · $47.00 per CY · qty 1000.0 · bid tab
- 2026-04-21 · TxDOT (Tyler district) · A00220493 · $60.00 per CY · qty 600.0 · bid tab
- 2026-04-21 · TxDOT (Tyler district) · A00220493 · $23.00 per CY · qty 1000.0 · bid tab
- 2026-04-21 · TxDOT (Tyler district) · A00220493 · $42.00 per CY · qty 1000.0 · bid tab
- 2026-04-21 · TxDOT (Tyler district) · A00220493 · $55.00 per CY · qty 1200.0 · bid tab
- 2026-04-21 · TxDOT (Tyler district) · A00220493 · $60.00 per CY · qty 500.0 · bid tab
|
| flexible base | SY | 1 | $35.00 | $35.00 to $35.00 | Bids- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $35.00 per SY · qty 19692.0 · bid tab
|
| inlet headwall | EA | 11 | $13,000.00 | $7,000.00 to $35,000.00 | Bids- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $13,000.00 per EA · qty 1.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $10,000.00 per EA · qty 4.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $22,000.00 per EA · qty 1.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $20,000.00 per EA · qty 2.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $14,000.00 per EA · qty 1.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $8,000.00 per EA · qty 1.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $9,000.00 per EA · qty 2.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $35,000.00 per EA · qty 1.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $7,000.00 per EA · qty 4.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $30,000.00 per EA · qty 1.0 · bid tab
(10 most recent of 11 shown; all in the Hubstake feed) |
| lime cement stabilization | CY | 2 | $325.00 | $300.00 to $350.00 | Bids- 2025-01-08 · TxDOT (Tyler district) · A00187856 · $300.00 per CY · qty 69.0 · bid tab
- 2025-01-07 · TxDOT (Tyler district) · A00178624 · $350.00 per CY · qty 14.0 · bid tab
|
| lime cement stabilization | SY | 3 | $5.00 | $5.00 to $8.00 | Bids- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $5.00 per SY · qty 12406.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $5.00 per SY · qty 12406.0 · bid tab
- 2025-01-08 · TxDOT (Tyler district) · A00187856 · $8.00 per SY · qty 816.0 · bid tab
|
| lime cement stabilization | TON | 3 | $300.00 | $250.00 to $325.00 | Bids- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $250.00 per TON · qty 223.31 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $325.00 per TON · qty 223.31 · bid tab
- 2025-01-08 · TxDOT (Tyler district) · A00187856 · $300.00 per TON · qty 17.0 · bid tab
|
| sidewalk | SY | 3 | $150.00 | $30.00 to $210.00 | Bids- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $210.00 per SY · qty 875.0 · bid tab
- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $30.00 per SY · qty 8095.0 · bid tab
- 2025-01-07 · TxDOT (Tyler district) · A00178624 · $150.00 per SY · qty 251.0 · bid tab
|
| storm pipe 18-inch | LF | 1 | $60.00 | $60.00 to $60.00 | Bids- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $60.00 per LF · qty 2323.0 · bid tab
|
| storm pipe 24-inch | LF | 2 | $112.50 | $100.00 to $125.00 | Bids- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $100.00 per LF · qty 8.0 · bid tab
- 2025-01-07 · TxDOT (Tyler district) · A00178624 · $125.00 per LF · qty 42.0 · bid tab
|
| storm pipe 30-inch | LF | 1 | $125.00 | $125.00 to $125.00 | Bids- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $125.00 per LF · qty 36.0 · bid tab
|
| storm pipe 36-inch | LF | 1 | $150.00 | $150.00 to $150.00 | Bids- 2025-11-06 · TxDOT (Tyler district) · A00059355 · $150.00 per LF · qty 70.0 · bid tab
|
| storm pipe (diameter not stated) | LF | 1 | $100.00 | $100.00 to $100.00 | Bids- 2025-01-07 · TxDOT (Tyler district) · A00178624 · $100.00 per LF · qty 100.0 · bid tab
|