Site-work prices, Nacogdoches County, TX

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON30$158.00$112.90 to $465.45
Bids
  • 2026-09-30 · TxDOT (Lufkin district) · A00223227 · $218.05 per TON · qty 4000.0 · bid tab
  • 2026-08-04 · TxDOT (Lufkin district) · A00219817 · $188.00 per TON · qty 2394.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $148.00 per TON · qty 14220.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $152.00 per TON · qty 28518.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $159.00 per TON · qty 17331.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $162.00 per TON · qty 56836.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $157.00 per TON · qty 57206.0 · bid tab
  • 2026-05-07 · TxDOT (Lufkin district) · A00133189 · $160.00 per TON · qty 14420.0 · bid tab
  • 2026-05-07 · TxDOT (Lufkin district) · A00193137 · $154.35 per TON · qty 7257.0 · bid tab
  • 2026-05-07 · TxDOT (Lufkin district) · A00193137 · $163.23 per TON · qty 17637.0 · bid tab
(10 most recent of 30 shown; all in the Hubstake feed)
curb gutterLF2$60.50$17.00 to $104.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $17.00 per LF · qty 48.0 · bid tab
  • 2024-06-06 · TxDOT · 06243217 · $104.00 per LF · qty 330.0 · bid tab
excavation embankmentCY9$10.00$3.00 to $100.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $3.00 per CY · qty 50.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $3.00 per CY · qty 77.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $8.50 per CY · qty 188030.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $3.00 per CY · qty 114847.0 · bid tab
  • 2026-05-07 · TxDOT (Lufkin district) · A00193137 · $22.30 per CY · qty 2892.0 · bid tab
  • 2026-05-06 · TxDOT (Lufkin district) · A00193119 · $22.00 per CY · qty 3000.0 · bid tab
  • 2025-05-01 · TxDOT (Lufkin district) · A00061563 · $10.00 per CY · qty 2370.0 · bid tab
  • 2025-05-01 · TxDOT (Lufkin district) · A00061563 · $10.00 per CY · qty 4252.0 · bid tab
  • 2024-10-31 · TxDOT (Lufkin district) · A00211669 · $100.00 per CY · qty 4.0 · bid tab
flexible baseSY2$50.50$25.00 to $76.00
Bids
  • 2025-05-01 · TxDOT (Lufkin district) · A00061563 · $76.00 per SY · qty 2073.0 · bid tab
  • 2025-05-01 · TxDOT (Lufkin district) · A00061563 · $25.00 per SY · qty 1654.0 · bid tab
flexible baseTON2$57.00$54.00 to $60.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $60.00 per TON · qty 86805.0 · bid tab
  • 2026-05-06 · TxDOT (Lufkin district) · A00193119 · $54.00 per TON · qty 14168.0 · bid tab
inlet headwallEA19$12,000.00$8,000.00 to $40,000.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $14,000.00 per EA · qty 3.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $8,000.00 per EA · qty 2.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $10,000.00 per EA · qty 1.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $28,000.00 per EA · qty 2.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $10,000.00 per EA · qty 2.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $10,000.00 per EA · qty 2.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $9,000.00 per EA · qty 1.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $9,000.00 per EA · qty 1.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $40,000.00 per EA · qty 4.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $16,000.00 per EA · qty 2.0 · bid tab
(10 most recent of 19 shown; all in the Hubstake feed)
lime cement stabilizationCY3$260.00$120.00 to $270.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $120.00 per CY · qty 2056.0 · bid tab
  • 2026-05-06 · TxDOT (Lufkin district) · A00193119 · $270.00 per CY · qty 44.0 · bid tab
  • 2025-05-01 · TxDOT (Lufkin district) · A00061563 · $260.00 per CY · qty 384.0 · bid tab
lime cement stabilizationSY10$3.12$2.50 to $8.85
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $2.50 per SY · qty 70083.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $2.50 per SY · qty 4528.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $2.50 per SY · qty 4602.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $2.50 per SY · qty 1354.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $5.00 per SY · qty 70083.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $2.50 per SY · qty 137162.0 · bid tab
  • 2026-05-07 · TxDOT (Lufkin district) · A00193137 · $8.85 per SY · qty 9994.0 · bid tab
  • 2026-05-06 · TxDOT (Lufkin district) · A00193119 · $3.75 per SY · qty 42362.0 · bid tab
  • 2025-05-01 · TxDOT (Lufkin district) · A00061563 · $5.00 per SY · qty 3727.0 · bid tab
  • 2025-05-01 · TxDOT (Lufkin district) · A00061563 · $5.00 per SY · qty 3848.0 · bid tab
lime cement stabilizationTON5$230.00$220.00 to $350.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $230.00 per TON · qty 3774.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $350.00 per TON · qty 1752.0 · bid tab
  • 2026-05-07 · TxDOT (Lufkin district) · A00193137 · $220.00 per TON · qty 184.0 · bid tab
  • 2026-05-06 · TxDOT (Lufkin district) · A00193119 · $220.00 per TON · qty 763.0 · bid tab
  • 2025-05-01 · TxDOT (Lufkin district) · A00061563 · $300.00 per TON · qty 126.0 · bid tab
sidewalkEA1$500.00$500.00 to $500.00
Bids
  • 2026-02-11 · TxDOT (Lufkin district) · A00217726 · $500.00 per EA · qty 2.0 · bid tab
sidewalkSY4$66.91$53.00 to $170.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $60.00 per SY · qty 9061.0 · bid tab
  • 2026-05-06 · TxDOT (Lufkin district) · A00193119 · $170.00 per SY · qty 832.0 · bid tab
  • 2026-05-06 · TxDOT (Lufkin district) · A00193119 · $53.00 per SY · qty 10145.0 · bid tab
  • 2025-05-01 · TxDOT (Lufkin district) · A00061563 · $73.83 per SY · qty 389.0 · bid tab
storm pipe 18-inchLF3$60.00$59.00 to $80.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $80.00 per LF · qty 3382.0 · bid tab
  • 2026-05-06 · TxDOT (Lufkin district) · A00193119 · $59.00 per LF · qty 1512.0 · bid tab
  • 2025-05-01 · TxDOT (Lufkin district) · A00061563 · $60.00 per LF · qty 144.0 · bid tab
storm pipe 24-inchLF2$95.50$91.00 to $100.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $100.00 per LF · qty 993.0 · bid tab
  • 2026-05-06 · TxDOT (Lufkin district) · A00193119 · $91.00 per LF · qty 316.0 · bid tab
storm pipe 30-inchLF1$130.00$130.00 to $130.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $130.00 per LF · qty 290.0 · bid tab
storm pipe 36-inchLF1$180.00$180.00 to $180.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $180.00 per LF · qty 85.0 · bid tab
storm pipe (diameter not stated)LF1$50.00$50.00 to $50.00
Bids
  • 2026-02-11 · TxDOT (Lufkin district) · A00217726 · $50.00 per LF · qty 75.0 · bid tab
water main 2-inchLF1$30.00$30.00 to $30.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $30.00 per LF · qty 1055.0 · bid tab
water main 4-inchLF1$33.00$33.00 to $33.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $33.00 per LF · qty 10690.0 · bid tab
water main 6-inchLF1$35.00$35.00 to $35.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $35.00 per LF · qty 5380.0 · bid tab
water main 8-inchLF2$97.50$45.00 to $150.00
Bids
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $150.00 per LF · qty 300.0 · bid tab
  • 2026-07-02 · TxDOT (Lufkin district) · A00064356 · $45.00 per LF · qty 3920.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.