| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 21 | $107.90 | $92.90 to $275.00 | Bids- 2026-07-01 · TxDOT (Tyler district) · A00206448 · $150.00 per TON · qty 234.0 · bid tab
- 2026-07-01 · TxDOT (Tyler district) · A00206448 · $275.00 per TON · qty 304.0 · bid tab
- 2026-07-01 · TxDOT (Tyler district) · A00206448 · $150.00 per TON · qty 432.0 · bid tab
- 2025-08-08 · TxDOT (Tyler district) · A00196862 · $275.00 per TON · qty 4.0 · bid tab
- 2025-03-04 · TxDOT (Tyler district) · A00213855 · $123.00 per TON · qty 50.0 · bid tab
- 2025-03-04 · TxDOT (Tyler district) · A00213855 · $113.00 per TON · qty 50.0 · bid tab
- 2025-03-04 · TxDOT (Tyler district) · A00213855 · $107.90 per TON · qty 200.0 · bid tab
- 2025-03-04 · TxDOT (Tyler district) · A00213855 · $107.90 per TON · qty 200.0 · bid tab
- 2025-03-04 · TxDOT (Tyler district) · A00213855 · $102.90 per TON · qty 10000.0 · bid tab
- 2025-03-04 · TxDOT (Tyler district) · A00213855 · $92.90 per TON · qty 6000.0 · bid tab
(10 most recent of 21 shown; all in the Hubstake feed) |
| excavation embankment | CY | 7 | $40.00 | $15.00 to $45.00 | Bids- 2026-07-01 · TxDOT (Tyler district) · A00206448 · $40.00 per CY · qty 634.0 · bid tab
- 2026-07-01 · TxDOT (Tyler district) · A00206448 · $25.00 per CY · qty 10.0 · bid tab
- 2025-10-21 · TxDOT (Tyler district) · A00216543 · $45.00 per CY · qty 24.0 · bid tab
- 2025-08-08 · TxDOT (Tyler district) · A00196862 · $38.33 per CY · qty 11869.0 · bid tab
- 2025-08-08 · TxDOT (Tyler district) · A00196862 · $15.00 per CY · qty 200.0 · bid tab
- 2025-02-07 · TxDOT (Tyler district) · A00064408 · $42.00 per CY · qty 814.0 · bid tab
- 2025-02-07 · TxDOT (Tyler district) · A00064408 · $42.00 per CY · qty 244.0 · bid tab
|
| flexible base | CY | 17 | $49.50 | $38.50 to $49.50 | Bids- 2025-01-21 · TxDOT (Tyler district) · A00212866 · $49.50 per CY · qty 500.0 · bid tab
- 2025-01-21 · TxDOT (Tyler district) · A00212866 · $49.50 per CY · qty 400.0 · bid tab
- 2025-01-21 · TxDOT (Tyler district) · A00212866 · $49.50 per CY · qty 2000.0 · bid tab
- 2025-01-21 · TxDOT (Tyler district) · A00212866 · $49.50 per CY · qty 500.0 · bid tab
- 2025-01-21 · TxDOT (Tyler district) · A00212866 · $49.50 per CY · qty 100.0 · bid tab
- 2025-01-21 · TxDOT (Tyler district) · A00212866 · $49.50 per CY · qty 700.0 · bid tab
- 2025-01-21 · TxDOT (Tyler district) · A00212866 · $49.50 per CY · qty 500.0 · bid tab
- 2025-01-21 · TxDOT (Tyler district) · A00212866 · $49.50 per CY · qty 500.0 · bid tab
- 2025-01-21 · TxDOT (Tyler district) · A00212866 · $49.50 per CY · qty 1000.0 · bid tab
- 2025-01-21 · TxDOT (Tyler district) · A00212866 · $38.50 per CY · qty 1400.0 · bid tab
(10 most recent of 17 shown; all in the Hubstake feed) |
| inlet headwall | EA | 5 | $25,000.00 | $10,400.00 to $47,348.00 | Bids- 2026-07-01 · TxDOT (Tyler district) · A00206448 · $12,000.00 per EA · qty 1.0 · bid tab
- 2026-07-01 · TxDOT (Tyler district) · A00206448 · $10,400.00 per EA · qty 1.0 · bid tab
- 2026-07-01 · TxDOT (Tyler district) · A00206448 · $25,000.00 per EA · qty 1.0 · bid tab
- 2025-08-08 · TxDOT (Tyler district) · A00196862 · $37,276.17 per EA · qty 12.0 · bid tab
- 2025-08-08 · TxDOT (Tyler district) · A00196862 · $47,348.00 per EA · qty 2.0 · bid tab
|
| sidewalk | SY | 4 | $70.50 | $50.00 to $140.97 | Bids- 2026-07-01 · TxDOT (Tyler district) · A00206448 · $50.00 per SY · qty 472.0 · bid tab
- 2025-08-08 · TxDOT (Tyler district) · A00196862 · $140.97 per SY · qty 127.0 · bid tab
- 2025-08-08 · TxDOT (Tyler district) · A00196862 · $55.00 per SY · qty 2623.0 · bid tab
- 2025-02-07 · TxDOT (Tyler district) · A00064408 · $86.00 per SY · qty 416.0 · bid tab
|
| storm pipe 18-inch | LF | 3 | $65.00 | $63.56 to $68.00 | Bids- 2026-07-01 · TxDOT (Tyler district) · A00206448 · $68.00 per LF · qty 74.0 · bid tab
- 2025-08-08 · TxDOT (Tyler district) · A00196862 · $63.56 per LF · qty 1921.0 · bid tab
- 2025-02-07 · TxDOT (Tyler district) · A00064408 · $65.00 per LF · qty 130.0 · bid tab
|
| storm pipe 24-inch | LF | 3 | $86.00 | $83.68 to $210.00 | Bids- 2026-07-01 · TxDOT (Tyler district) · A00206448 · $86.00 per LF · qty 30.0 · bid tab
- 2025-08-08 · TxDOT (Tyler district) · A00196862 · $83.68 per LF · qty 372.0 · bid tab
- 2025-02-07 · TxDOT (Tyler district) · A00064408 · $210.00 per LF · qty 36.0 · bid tab
|
| storm pipe 30-inch | LF | 2 | $158.47 | $106.94 to $210.00 | Bids- 2026-07-01 · TxDOT (Tyler district) · A00206448 · $210.00 per LF · qty 4.0 · bid tab
- 2025-08-08 · TxDOT (Tyler district) · A00196862 · $106.94 per LF · qty 8.0 · bid tab
|
| storm pipe 36-inch | LF | 1 | $139.19 | $139.19 to $139.19 | Bids- 2025-08-08 · TxDOT (Tyler district) · A00196862 · $139.19 per LF · qty 12.0 · bid tab
|
| storm pipe 48-inch | LF | 1 | $214.08 | $214.08 to $214.08 | Bids- 2025-08-08 · TxDOT (Tyler district) · A00196862 · $214.08 per LF · qty 24.0 · bid tab
|
| storm pipe (diameter not stated) | LF | 1 | $112.00 | $112.00 to $112.00 | Bids- 2025-08-08 · TxDOT (Tyler district) · A00196862 · $112.00 per LF · qty 63.0 · bid tab
|