Site-work prices, Bee County, TX
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| asphalt pavement | TON | 2 | $87.75 | $86.75 to $88.75 | |
| excavation embankment | CY | 2 | $26.50 | $18.00 to $35.00 | |
| flexible base | CY | 1 | $109.50 | $109.50 to $109.50 | Bids
|
| flexible base | TON | 2 | $35.45 | $33.85 to $37.05 | |
| lime cement stabilization | CY | 1 | $195.00 | $195.00 to $195.00 | Bids
|
| lime cement stabilization | SY | 2 | $3.20 | $2.40 to $4.00 | |
| lime cement stabilization | TON | 2 | $304.50 | $215.00 to $394.00 | |
| storm pipe 18-inch | LF | 1 | $84.00 | $84.00 to $84.00 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.