PadstakeGet the fee reports
Menu

Site-work prices, Anderson County, TX

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON12$124.00$97.00 to $172.00
Bids
  • 2026-01-07 · TxDOT (Tyler district) · A00196226 · $172.00 per TON · qty 1585.0 · bid tab
  • 2026-01-07 · TxDOT (Tyler district) · A00196226 · $148.00 per TON · qty 3067.0 · bid tab
  • 2025-11-05 · TxDOT (Tyler district) · A00217882 · $126.00 per TON · qty 1000.0 · bid tab
  • 2025-11-05 · TxDOT (Tyler district) · A00217882 · $126.00 per TON · qty 100.0 · bid tab
  • 2025-11-05 · TxDOT (Tyler district) · A00217882 · $122.00 per TON · qty 100.0 · bid tab
  • 2025-11-05 · TxDOT (Tyler district) · A00217882 · $126.00 per TON · qty 100.0 · bid tab
  • 2025-11-05 · TxDOT (Tyler district) · A00217882 · $122.00 per TON · qty 100.0 · bid tab
  • 2025-11-05 · TxDOT (Tyler district) · A00217882 · $126.00 per TON · qty 100.0 · bid tab
  • 2025-11-05 · TxDOT (Tyler district) · A00217882 · $122.00 per TON · qty 7000.0 · bid tab
  • 2025-11-05 · TxDOT (Tyler district) · A00217882 · $97.00 per TON · qty 4300.0 · bid tab
(10 most recent of 12 shown; all in the Hubstake feed)
curb gutterLF3$71.50$53.50 to $105.00
Bids
  • 2026-07-21 · TxDOT (Tyler district) · A00220736 · $105.00 per LF · qty 21.0 · bid tab
  • 2026-07-02 · TxDOT (Tyler district) · A00215720 · $53.50 per LF · qty 909.0 · bid tab
  • 2026-01-07 · TxDOT (Tyler district) · A00196226 · $71.50 per LF · qty 150.0 · bid tab
excavation embankmentCY6$35.00$20.00 to $500.00
Bids
  • 2026-10-13 · TxDOT (Tyler district) · A00223040 · $30.00 per CY · qty 516.0 · bid tab
  • 2026-07-21 · TxDOT (Tyler district) · A00220736 · $84.00 per CY · qty 30.0 · bid tab
  • 2025-10-21 · TxDOT (Tyler district) · A00216166 · $500.00 per CY · qty 3.0 · bid tab
  • 2025-10-21 · TxDOT (Tyler district) · A00216166 · $20.00 per CY · qty 73.0 · bid tab
  • 2025-07-01 · TxDOT (Tyler district) · A00193092 · $20.00 per CY · qty 1330.0 · bid tab
  • 2025-07-01 · TxDOT (Tyler district) · A00193092 · $40.00 per CY · qty 50.0 · bid tab
inlet headwallEA12$22,000.00$10,000.00 to $50,000.00
Bids
  • 2026-10-13 · TxDOT (Tyler district) · A00223040 · $24,000.00 per EA · qty 1.0 · bid tab
  • 2026-10-13 · TxDOT (Tyler district) · A00223040 · $20,000.00 per EA · qty 1.0 · bid tab
  • 2026-10-13 · TxDOT (Tyler district) · A00223040 · $26,000.00 per EA · qty 1.0 · bid tab
  • 2026-10-13 · TxDOT (Tyler district) · A00223040 · $22,000.00 per EA · qty 1.0 · bid tab
  • 2026-10-13 · TxDOT (Tyler district) · A00223040 · $22,000.00 per EA · qty 2.0 · bid tab
  • 2026-10-13 · TxDOT (Tyler district) · A00223040 · $20,000.00 per EA · qty 1.0 · bid tab
  • 2025-07-01 · TxDOT (Tyler district) · A00193092 · $10,000.00 per EA · qty 1.0 · bid tab
  • 2025-07-01 · TxDOT (Tyler district) · A00193092 · $20,000.00 per EA · qty 2.0 · bid tab
  • 2025-07-01 · TxDOT (Tyler district) · A00193092 · $20,000.00 per EA · qty 1.0 · bid tab
  • 2025-07-01 · TxDOT (Tyler district) · A00193092 · $30,000.00 per EA · qty 1.0 · bid tab
(10 most recent of 12 shown; all in the Hubstake feed)
lime cement stabilizationCY1$525.00$525.00 to $525.00
Bids
  • 2026-07-21 · TxDOT (Tyler district) · A00220736 · $525.00 per CY · qty 17.0 · bid tab
lime cement stabilizationSY1$9.20$9.20 to $9.20
Bids
  • 2026-01-07 · TxDOT (Tyler district) · A00196226 · $9.20 per SY · qty 10934.0 · bid tab
lime cement stabilizationTON1$275.00$275.00 to $275.00
Bids
  • 2026-01-07 · TxDOT (Tyler district) · A00196226 · $275.00 per TON · qty 197.0 · bid tab
sidewalkSY3$100.00$50.00 to $145.00
Bids
  • 2026-01-07 · TxDOT (Tyler district) · A00196226 · $145.00 per SY · qty 360.0 · bid tab
  • 2025-07-01 · TxDOT (Tyler district) · A00193092 · $100.00 per SY · qty 682.0 · bid tab
  • 2025-07-01 · TxDOT (Tyler district) · A00193092 · $50.00 per SY · qty 2405.0 · bid tab
storm pipe 18-inchLF1$65.00$65.00 to $65.00
Bids
  • 2025-07-01 · TxDOT (Tyler district) · A00193092 · $65.00 per LF · qty 1346.0 · bid tab
storm pipe 24-inchLF2$157.50$95.00 to $220.00
Bids
  • 2026-10-13 · TxDOT (Tyler district) · A00223040 · $220.00 per LF · qty 30.0 · bid tab
  • 2025-07-01 · TxDOT (Tyler district) · A00193092 · $95.00 per LF · qty 304.0 · bid tab
storm pipe 30-inchLF2$200.00$150.00 to $250.00
Bids
  • 2026-10-13 · TxDOT (Tyler district) · A00223040 · $250.00 per LF · qty 126.0 · bid tab
  • 2025-07-01 · TxDOT (Tyler district) · A00193092 · $150.00 per LF · qty 132.0 · bid tab
storm pipe 36-inchLF1$300.00$300.00 to $300.00
Bids
  • 2026-10-13 · TxDOT (Tyler district) · A00223040 · $300.00 per LF · qty 30.0 · bid tab
storm pipe (diameter not stated)LF1$98.44$98.44 to $98.44
Bids
  • 2025-07-01 · TxDOT (Tyler district) · A00193092 · $98.44 per LF · qty 100.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.