Site-work prices, Obion County, TN
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 22 | $136.05 | $25.10 to $250.00 | Bids- 2026-05-08 · TDOT · CN264035 · $159.00 per TON · qty 6801.0 · bid tab
- 2026-05-08 · TDOT · CN264035 · $115.00 per TON · qty 10793.0 · bid tab
- 2026-05-08 · TDOT · CN264035 · $250.00 per TON · qty 92.0 · bid tab
- 2026-05-08 · TDOT · CN264035 · $30.00 per TON · qty 16766.0 · bid tab
- 2026-03-20 · TDOT · CN264021 · $159.00 per TON · qty 8132.0 · bid tab
- 2026-03-20 · TDOT · CN264021 · $27.25 per TON · qty 20520.0 · bid tab
- 2026-03-20 · TDOT · CN264021 · $137.00 per TON · qty 1229.0 · bid tab
- 2026-03-20 · TDOT · CN264021 · $121.70 per TON · qty 12103.0 · bid tab
- 2026-03-20 · TDOT · CN264022 · $137.00 per TON · qty 3569.0 · bid tab
- 2026-03-20 · TDOT · CN264022 · $25.10 per TON · qty 39903.0 · bid tab
(10 most recent of 22 shown; all in the Hubstake feed) |
| curb gutter | C.Y. | 3 | $2,150.00 | $2,100.00 to $2,415.00 | Bids- 2026-03-20 · TDOT · CN264021 · $2,100.00 per C.Y. · qty 2.0 · bid tab
- 2026-03-20 · TDOT · CN264022 · $2,415.00 per C.Y. · qty 3.9 · bid tab
- 2026-03-20 · TDOT · CN264022 · $2,150.00 per C.Y. · qty 2.6 · bid tab
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.