Site-work prices, Jefferson County, TN
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 29 | $160.00 | $16.03 to $468.93 | Bids- 2026-05-08 · TDOT · CN261038 · $152.00 per TON · qty 5408.0 · bid tab
- 2026-05-08 · TDOT · CN261038 · $125.00 per TON · qty 1082.0 · bid tab
- 2025-06-27 · TDOT · CNZ175 · $158.00 per TON · qty 986.0 · bid tab
- 2025-06-27 · TDOT · CNZ175 · $156.00 per TON · qty 6574.0 · bid tab
- 2025-03-21 · TDOT · CNZ085 · $434.20 per TON · qty 351.0 · bid tab
- 2025-03-21 · TDOT · CNZ085 · $347.36 per TON · qty 73.0 · bid tab
- 2025-03-21 · TDOT · CNZ085 · $16.03 per TON · qty 181.0 · bid tab
- 2025-03-21 · TDOT · CNZ085 · $347.36 per TON · qty 112.0 · bid tab
- 2024-12-06 · TDOT · CNY294 · $85.00 per TON · qty 931.0 · bid tab
- 2024-12-06 · TDOT · CNY294 · $160.00 per TON · qty 387.0 · bid tab
(10 most recent of 29 shown; all in the Hubstake feed) |
| curb gutter | C.Y. | 3 | $685.00 | $650.00 to $750.00 | Bids- 2024-12-06 · TDOT · CNY294 · $750.00 per C.Y. · qty 117.0 · bid tab
- 2024-12-06 · TDOT · CNY294 · $650.00 per C.Y. · qty 79.0 · bid tab
- 2024-02-09 · TDOT · CNY006 · $685.00 per C.Y. · qty 110.0 · bid tab
|
| fire hydrant | EACH | 1 | $11,500.00 | $11,500.00 to $11,500.00 | Bids- 2024-12-06 · TDOT · CNY294 · $11,500.00 per EACH · qty 1.0 · bid tab
|
| manhole | EACH | 9 | $6,875.00 | $1,850.00 to $25,000.00 | Bids- 2024-12-06 · TDOT · CNY294 · $12,000.00 per EACH · qty 1.0 · bid tab
- 2024-12-06 · TDOT · CNY294 · $1,850.00 per EACH · qty 2.0 · bid tab
- 2024-12-06 · TDOT · CNY294 · $2,200.00 per EACH · qty 2.0 · bid tab
- 2024-12-06 · TDOT · CNY294 · $8,600.00 per EACH · qty 5.0 · bid tab
- 2024-12-06 · TDOT · CNY294 · $25,000.00 per EACH · qty 1.0 · bid tab
- 2024-12-06 · TDOT · CNY294 · $6,875.00 per EACH · qty 3.0 · bid tab
- 2024-02-09 · TDOT · CNY006 · $6,500.00 per EACH · qty 1.0 · bid tab
- 2024-02-09 · TDOT · CNY006 · $8,000.00 per EACH · qty 1.0 · bid tab
- 2024-02-09 · TDOT · CNY006 · $6,700.00 per EACH · qty 8.0 · bid tab
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.