Site-work prices, Humphreys County, TN

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON25$150.00$20.00 to $300.00
Bids
  • 2026-10-02 · TDOT · CN263065 · $300.00 per TON · qty 81.0 · bid tab
  • 2026-10-02 · TDOT · CN263065 · $300.00 per TON · qty 15.0 · bid tab
  • 2026-10-02 · TDOT · CN263065 · $300.00 per TON · qty 95.0 · bid tab
  • 2026-03-20 · TDOT · CN263029 · $20.00 per TON · qty 7179.0 · bid tab
  • 2026-03-20 · TDOT · CN263029 · $134.70 per TON · qty 6092.0 · bid tab
  • 2026-03-20 · TDOT · CN263029 · $99.00 per TON · qty 10302.0 · bid tab
  • 2025-06-27 · TDOT · CNZ192 · $195.00 per TON · qty 3494.0 · bid tab
  • 2025-06-27 · TDOT · CNZ192 · $168.00 per TON · qty 989.0 · bid tab
  • 2025-06-27 · TDOT · CNZ192 · $172.00 per TON · qty 1349.0 · bid tab
  • 2025-06-27 · TDOT · CNZ192 · $188.00 per TON · qty 1019.0 · bid tab
(10 most recent of 25 shown; all in the Hubstake feed)
inlet headwallEACH1$1,200.00$1,200.00 to $1,200.00
Bids
  • 2024-12-06 · TDOT · CNY906 · $1,200.00 per EACH · qty 24.0 · bid tab
lime cement stabilizationL.F.1$14.12$14.12 to $14.12
Bids
  • 2024-12-06 · TDOT · CNY906 · $14.12 per L.F. · qty 500.0 · bid tab
lime cement stabilizationS.Y.2$4.88$2.50 to $7.25
Bids
  • 2024-12-06 · TDOT · CNY906 · $7.25 per S.Y. · qty 2875.0 · bid tab
  • 2024-05-10 · TDOT · CNY140 · $2.50 per S.Y. · qty 22778.0 · bid tab
manholeEACH2$12,500.00$7,000.00 to $18,000.00
Bids
  • 2024-12-06 · TDOT · CNY906 · $18,000.00 per EACH · qty 1.0 · bid tab
  • 2024-05-10 · TDOT · CNY140 · $7,000.00 per EACH · qty 7.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.