Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | Ton | 4 | $103.10 | $35.13 to $672.00 | Bids- 2025-11-05 · SDDOT · 06QE · $35.13 per Ton · qty 34859.0 · bid tab
- 2025-11-05 · SDDOT · 06QE · $70.91 per Ton · qty 1214.0 · bid tab
- 2025-11-05 · SDDOT · 06QE · $135.29 per Ton · qty 1375.0 · bid tab
- 2025-11-05 · SDDOT · 06QE · $672.00 per Ton · qty 1781.2 · bid tab
|
| excavation embankment | CuYd | 8 | $15.00 | $4.81 to $30.00 | Bids- 2026-05-20 · SDDOT · 09A9 · $30.00 per CuYd · qty 358.0 · bid tab
- 2026-05-20 · SDDOT · 09A9 · $15.00 per CuYd · qty 5559.0 · bid tab
- 2026-05-20 · SDDOT · 09A9 · $15.00 per CuYd · qty 640.0 · bid tab
- 2025-11-05 · SDDOT · 06QE · $4.81 per CuYd · qty 10483.0 · bid tab
- 2025-11-05 · SDDOT · 06QE · $12.83 per CuYd · qty 6535.0 · bid tab
- 2025-11-05 · SDDOT · 06QE · $15.00 per CuYd · qty 405.0 · bid tab
- 2025-10-01 · SDDOT · 09A8 · $7.50 per CuYd · qty 2972.0 · bid tab
- 2025-10-01 · SDDOT · 09A8 · $23.00 per CuYd · qty 889.0 · bid tab
|
| flexible base | Ton | 1 | $16.04 | $16.04 to $16.04 | Bids- 2025-11-05 · SDDOT · 06QE · $16.04 per Ton · qty 8084.0 · bid tab
|
| lime cement stabilization | Ton | 1 | $313.00 | $313.00 to $313.00 | Bids- 2025-11-05 · SDDOT · 06QE · $313.00 per Ton · qty 357.2 · bid tab
|
| storm pipe 18-inch | Ft | 4 | $43.72 | $32.08 to $75.00 | Bids- 2026-05-20 · SDDOT · 09A9 · $50.00 per Ft · qty 40.0 · bid tab
- 2026-05-20 · SDDOT · 09A9 · $75.00 per Ft · qty 40.0 · bid tab
- 2025-11-05 · SDDOT · 06QE · $32.08 per Ft · qty 28.0 · bid tab
- 2025-11-05 · SDDOT · 06QE · $37.43 per Ft · qty 28.0 · bid tab
|
| storm pipe 24-inch | Ft | 2 | $58.01 | $51.86 to $64.16 | Bids- 2025-11-05 · SDDOT · 06QE · $64.16 per Ft · qty 76.0 · bid tab
- 2025-11-05 · SDDOT · 06QE · $51.86 per Ft · qty 76.0 · bid tab
|
| storm pipe 36-inch | Ft | 2 | $80.20 | $74.85 to $85.55 | Bids- 2025-11-05 · SDDOT · 06QE · $85.55 per Ft · qty 86.0 · bid tab
- 2025-11-05 · SDDOT · 06QE · $74.85 per Ft · qty 86.0 · bid tab
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.