Site-work prices, Lyman, Tripp County, SD

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTon7$167.18$39.87 to $722.20
Bids
  • 2025-12-10 · SDDOT · 090U · $325.00 per Ton · qty 483.2 · bid tab
  • 2025-01-22 · SDDOT · 06Q8 · $722.20 per Ton · qty 46.0 · bid tab
  • 2025-01-22 · SDDOT · 06Q8 · $722.20 per Ton · qty 1060.3 · bid tab
  • 2025-01-22 · SDDOT · 06Q8 · $167.18 per Ton · qty 240.4 · bid tab
  • 2025-01-22 · SDDOT · 06Q8 · $46.59 per Ton · qty 1000.0 · bid tab
  • 2025-01-22 · SDDOT · 06Q8 · $53.78 per Ton · qty 1427.4 · bid tab
  • 2025-01-22 · SDDOT · 06Q8 · $39.87 per Ton · qty 19874.5 · bid tab
excavation embankmentCuYd4$23.25$15.00 to $33.44
Bids
  • 2025-12-10 · SDDOT · 090U · $27.00 per CuYd · qty 371.0 · bid tab
  • 2025-12-10 · SDDOT · 090U · $19.50 per CuYd · qty 76.0 · bid tab
  • 2025-01-22 · SDDOT · 06Q8 · $33.44 per CuYd · qty 693.0 · bid tab
  • 2025-01-22 · SDDOT · 06Q8 · $15.00 per CuYd · qty 476.0 · bid tab
flexible baseTon3$33.44$28.00 to $33.44
Bids
  • 2025-12-10 · SDDOT · 090U · $28.00 per Ton · qty 162.5 · bid tab
  • 2025-01-22 · SDDOT · 06Q8 · $33.44 per Ton · qty 1171.3 · bid tab
  • 2025-01-22 · SDDOT · 06Q8 · $33.44 per Ton · qty 672.5 · bid tab
lime cement stabilizationTon2$320.29$320.29 to $320.29
Bids
  • 2025-01-22 · SDDOT · 06Q8 · $320.29 per Ton · qty 220.3 · bid tab
  • 2025-01-22 · SDDOT · 06Q8 · $320.29 per Ton · qty 10.0 · bid tab
storm pipe 18-inchFt2$75.23$66.87 to $83.59
Bids
  • 2025-01-22 · SDDOT · 06Q8 · $66.87 per Ft · qty 132.0 · bid tab
  • 2025-01-22 · SDDOT · 06Q8 · $83.59 per Ft · qty 132.0 · bid tab
storm pipe 24-inchFt2$125.38$89.16 to $161.60
Bids
  • 2025-01-22 · SDDOT · 06Q8 · $89.16 per Ft · qty 154.0 · bid tab
  • 2025-01-22 · SDDOT · 06Q8 · $161.60 per Ft · qty 154.0 · bid tab
storm pipe (diameter not stated)Ft1$117.02$117.02 to $117.02
Bids
  • 2025-01-22 · SDDOT · 06Q8 · $117.02 per Ft · qty 200.0 · bid tab