Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTon7$150.00$25.18 to $860.02
Bids
  • 2025-12-03 · SDDOT · 07CF · $208.00 per Ton · qty 1385.6 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $225.22 per Ton · qty 3727.7 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $860.02 per Ton · qty 1137.1 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $100.78 per Ton · qty 1915.5 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $25.18 per Ton · qty 13611.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $86.84 per Ton · qty 26901.7 · bid tab
  • 2024-03-20 · SDDOT · 09LG · $150.00 per Ton · qty 392.0 · bid tab
curb gutterFt1$124.36$124.36 to $124.36
Bids
  • 2025-02-05 · SDDOT · 06QK · $124.36 per Ft · qty 453.0 · bid tab
excavation embankmentCuYd6$25.04$11.48 to $64.66
Bids
  • 2025-12-03 · SDDOT · 07CF · $15.00 per CuYd · qty 100.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $15.00 per CuYd · qty 631.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $35.08 per CuYd · qty 778.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $11.48 per CuYd · qty 26207.0 · bid tab
  • 2024-12-11 · SDDOT · 08NT · $64.66 per CuYd · qty 296.0 · bid tab
  • 2024-12-11 · SDDOT · 08NT · $44.11 per CuYd · qty 1132.0 · bid tab
flexible baseTon4$52.30$39.74 to $76.50
Bids
  • 2025-12-03 · SDDOT · 07CF · $50.00 per Ton · qty 4664.3 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $39.74 per Ton · qty 14025.4 · bid tab
  • 2024-12-11 · SDDOT · 08NT · $54.60 per Ton · qty 533.8 · bid tab
  • 2024-03-20 · SDDOT · 09LG · $76.50 per Ton · qty 954.0 · bid tab
inlet headwallEach3$350.00$350.00 to $1,885.93
Bids
  • 2025-12-03 · SDDOT · 07CF · $350.00 per Each · qty 1.0 · bid tab
  • 2025-12-03 · SDDOT · 07CF · $350.00 per Each · qty 1.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $1,885.93 per Each · qty 1.0 · bid tab
lime cement stabilizationAcre1$2,963.23$2,963.23 to $2,963.23
Bids
  • 2025-02-05 · SDDOT · 06QK · $2,963.23 per Acre · qty 0.7 · bid tab
lime cement stabilizationTon1$218.67$218.67 to $218.67
Bids
  • 2025-02-05 · SDDOT · 06QK · $218.67 per Ton · qty 292.7 · bid tab
storm pipe 12-inchFt2$106.75$26.00 to $187.50
Bids
  • 2024-03-20 · SDDOT · 09LG · $187.50 per Ft · qty 26.0 · bid tab
  • 2024-03-20 · SDDOT · 09LG · $26.00 per Ft · qty 26.0 · bid tab
storm pipe 18-inchFt4$42.44$38.00 to $200.00
Bids
  • 2025-02-05 · SDDOT · 06QK · $40.87 per Ft · qty 182.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $44.01 per Ft · qty 182.0 · bid tab
  • 2024-03-20 · SDDOT · 09LG · $38.00 per Ft · qty 24.0 · bid tab
  • 2024-03-20 · SDDOT · 09LG · $200.00 per Ft · qty 24.0 · bid tab
storm pipe 24-inchFt6$78.86$47.00 to $106.87
Bids
  • 2025-12-03 · SDDOT · 07CF · $47.00 per Ft · qty 208.0 · bid tab
  • 2025-12-03 · SDDOT · 07CF · $51.00 per Ft · qty 208.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $106.87 per Ft · qty 262.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $93.59 per Ft · qty 262.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $94.72 per Ft · qty 594.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $64.12 per Ft · qty 594.0 · bid tab
storm pipe 30-inchFt2$93.52$88.01 to $99.03
Bids
  • 2025-02-05 · SDDOT · 06QK · $99.03 per Ft · qty 124.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $88.01 per Ft · qty 124.0 · bid tab
storm pipe 36-inchFt2$125.00$119.44 to $130.57
Bids
  • 2025-02-05 · SDDOT · 06QK · $130.57 per Ft · qty 104.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $119.44 per Ft · qty 104.0 · bid tab
storm pipe 42-inchFt4$165.01$122.64 to $207.45
Bids
  • 2025-02-05 · SDDOT · 06QK · $201.17 per Ft · qty 148.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $128.85 per Ft · qty 148.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $207.45 per Ft · qty 122.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $122.64 per Ft · qty 122.0 · bid tab
storm pipe 54-inchFt2$210.87$189.13 to $232.60
Bids
  • 2025-02-05 · SDDOT · 06QK · $232.60 per Ft · qty 70.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $189.13 per Ft · qty 70.0 · bid tab
storm pipe 60-inchFt2$212.13$107.45 to $316.81
Bids
  • 2024-12-11 · SDDOT · 08NT · $316.81 per Ft · qty 96.0 · bid tab
  • 2024-12-11 · SDDOT · 08NT · $107.45 per Ft · qty 96.0 · bid tab
storm pipe 72-inchFt2$283.73$190.27 to $377.19
Bids
  • 2025-02-05 · SDDOT · 06QK · $377.19 per Ft · qty 80.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $190.27 per Ft · qty 80.0 · bid tab
storm pipe 84-inchFt2$552.19$412.88 to $691.51
Bids
  • 2025-02-05 · SDDOT · 06QK · $691.51 per Ft · qty 66.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $412.88 per Ft · qty 66.0 · bid tab
storm pipe (diameter not stated)Ft6$693.40$20.15 to $1,651.24
Bids
  • 2025-02-05 · SDDOT · 06QK · $20.15 per Ft · qty 380.0 · bid tab
  • 2025-02-05 · SDDOT · 06QK · $160.01 per Ft · qty 380.0 · bid tab
  • 2024-12-11 · SDDOT · 08NT · $1,034.71 per Ft · qty 42.0 · bid tab
  • 2024-12-11 · SDDOT · 08NT · $1,173.20 per Ft · qty 12.0 · bid tab
  • 2024-12-11 · SDDOT · 08NT · $352.09 per Ft · qty 42.0 · bid tab
  • 2024-12-11 · SDDOT · 08NT · $1,651.24 per Ft · qty 12.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.