Site-work prices, Campbell County, SD
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | Ton | 7 | $66.18 | $5.58 to $691.64 | Bids- 2026-03-04 · SDDOT · 06RG · $51.43 per Ton · qty 26462.9 · bid tab
- 2026-03-04 · SDDOT · 06RG · $75.00 per Ton · qty 558.8 · bid tab
- 2026-03-04 · SDDOT · 06RG · $597.30 per Ton · qty 1349.4 · bid tab
- 2026-03-04 · SDDOT · 06RG · $25.04 per Ton · qty 1708.8 · bid tab
- 2026-03-04 · SDDOT · 06RG · $5.58 per Ton · qty 1708.8 · bid tab
- 2026-03-04 · SDDOT · 06RG · $66.18 per Ton · qty 2025.6 · bid tab
- 2024-04-17 · SDDOT · 0972 · $691.64 per Ton · qty 452.3 · bid tab
|
| excavation embankment | CuYd | 2 | $32.50 | $15.00 to $50.00 | Bids- 2026-03-04 · SDDOT · 06RG · $15.00 per CuYd · qty 683.0 · bid tab
- 2026-03-04 · SDDOT · 06RG · $50.00 per CuYd · qty 144.0 · bid tab
|
| flexible base | Ton | 2 | $20.03 | $17.01 to $23.05 | Bids- 2026-03-04 · SDDOT · 06RG · $23.05 per Ton · qty 1307.0 · bid tab
- 2026-03-04 · SDDOT · 06RG · $17.01 per Ton · qty 1610.4 · bid tab
|
| lime cement stabilization | Ton | 1 | $299.51 | $299.51 to $299.51 | Bids- 2026-03-04 · SDDOT · 06RG · $299.51 per Ton · qty 276.9 · bid tab
|
| storm pipe (diameter not stated) | Ft | 2 | $55.00 | $20.00 to $90.00 | Bids- 2026-03-04 · SDDOT · 06RG · $20.00 per Ft · qty 286.0 · bid tab
- 2026-03-04 · SDDOT · 06RG · $90.00 per Ft · qty 286.0 · bid tab
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.