Site-work prices, Clarendon County, SC

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON31$105.00$73.95 to $900.00
Bids
  • 2026-08-11 · SCDOT · 1477330 · $240.00 per TON · qty 25.0 · bid tab
  • 2026-08-11 · SCDOT · 1477330 · $80.75 per TON · qty 1255.573 · bid tab
  • 2026-08-11 · SCDOT · 1477330 · $900.00 per TON · qty 73.485 · bid tab
  • 2025-12-09 · SCDOT · 1475000 · $670.00 per TON · qty 2320.733 · bid tab
  • 2025-12-09 · SCDOT · 1475000 · $133.50 per TON · qty 26707.412 · bid tab
  • 2025-12-09 · SCDOT · 1475000 · $99.00 per TON · qty 13105.0 · bid tab
  • 2025-12-09 · SCDOT · 1475000 · $91.50 per TON · qty 26707.412 · bid tab
  • 2025-12-09 · SCDOT · 1475000 · $795.00 per TON · qty 1655.86 · bid tab
  • 2025-09-09 · SCDOT · 1474050 · $615.00 per TON · qty 1671.867 · bid tab
  • 2025-09-09 · SCDOT · 1474050 · $73.95 per TON · qty 2192.96 · bid tab
(10 most recent of 31 shown; all in the Hubstake feed)
curb gutterLF9$35.00$1.00 to $65.00
Bids
  • 2025-09-09 · SCDOT · 1474050 · $1.50 per LF · qty 2400.0 · bid tab
  • 2025-09-09 · SCDOT · 1474050 · $43.85 per LF · qty 800.0 · bid tab
  • 2025-02-11 · SCDOT · 1470210 · $40.00 per LF · qty 684.0 · bid tab
  • 2024-11-13 · SCDOT · 1470500 · $1.00 per LF · qty 170.0 · bid tab
  • 2024-09-10 · SCDOT · 1469820 · $29.00 per LF · qty 75.0 · bid tab
  • 2024-09-10 · SCDOT · 1469820 · $2.00 per LF · qty 610.0 · bid tab
  • 2023-11-14 · SCDOT · 1466860 · $36.00 per LF · qty 500.0 · bid tab
  • 2023-11-14 · SCDOT · 1466860 · $35.00 per LF · qty 50.0 · bid tab
  • 2023-11-14 · SCDOT · 1466860 · $65.00 per LF · qty 530.0 · bid tab
excavation embankmentCY10$66.30$12.25 to $104.00
Bids
  • 2026-08-11 · SCDOT · 1477330 · $59.60 per CY · qty 148.0 · bid tab
  • 2025-12-09 · SCDOT · 1475000 · $78.00 per CY · qty 2396.0 · bid tab
  • 2025-09-09 · SCDOT · 1474050 · $41.75 per CY · qty 2446.0 · bid tab
  • 2025-09-09 · SCDOT · 1474050 · $12.25 per CY · qty 760.0 · bid tab
  • 2025-02-11 · SCDOT · 1470210 · $85.00 per CY · qty 514.0 · bid tab
  • 2025-02-11 · SCDOT · 1470210 · $50.00 per CY · qty 90.0 · bid tab
  • 2024-11-13 · SCDOT · 1470500 · $104.00 per CY · qty 250.0 · bid tab
  • 2024-09-10 · SCDOT · 1469820 · $77.00 per CY · qty 2524.0 · bid tab
  • 2024-09-10 · SCDOT · 1469820 · $18.00 per CY · qty 560.0 · bid tab
  • 2023-11-14 · SCDOT · 1466860 · $73.00 per CY · qty 2774.0 · bid tab
inlet headwallEA1$4,500.00$4,500.00 to $4,500.00
Bids
  • 2025-02-11 · SCDOT · 1470210 · $4,500.00 per EA · qty 4.0 · bid tab
lime cement stabilizationLB1$1.00$1.00 to $1.00
Bids
  • 2025-02-11 · SCDOT · 1470210 · $1.00 per LB · qty 12.6 · bid tab
lime cement stabilizationSY4$7.88$6.60 to $20.00
Bids
  • 2025-09-09 · SCDOT · 1474050 · $6.60 per SY · qty 115100.0 · bid tab
  • 2025-02-11 · SCDOT · 1470210 · $20.00 per SY · qty 550.0 · bid tab
  • 2024-09-10 · SCDOT · 1469820 · $8.75 per SY · qty 29940.0 · bid tab
  • 2024-09-10 · SCDOT · 1469820 · $7.00 per SY · qty 57990.0 · bid tab
lime cement stabilizationTON2$216.00$204.00 to $228.00
Bids
  • 2025-09-09 · SCDOT · 1474050 · $228.00 per TON · qty 4030.0 · bid tab
  • 2024-09-10 · SCDOT · 1469820 · $204.00 per TON · qty 3085.0 · bid tab
manholeEA1$4,000.00$4,000.00 to $4,000.00
Bids
  • 2025-02-11 · SCDOT · 1470210 · $4,000.00 per EA · qty 2.0 · bid tab
sidewalkSY9$105.00$68.00 to $195.00
Bids
  • 2025-09-09 · SCDOT · 1474050 · $124.50 per SY · qty 600.0 · bid tab
  • 2025-09-09 · SCDOT · 1474050 · $113.50 per SY · qty 190.0 · bid tab
  • 2025-09-09 · SCDOT · 1474050 · $190.55 per SY · qty 200.0 · bid tab
  • 2025-02-11 · SCDOT · 1470210 · $75.00 per SY · qty 20.0 · bid tab
  • 2025-02-11 · SCDOT · 1470210 · $195.00 per SY · qty 50.0 · bid tab
  • 2024-09-10 · SCDOT · 1469820 · $68.00 per SY · qty 55.0 · bid tab
  • 2024-09-10 · SCDOT · 1469820 · $105.00 per SY · qty 75.0 · bid tab
  • 2023-11-14 · SCDOT · 1466860 · $88.00 per SY · qty 50.0 · bid tab
  • 2023-11-14 · SCDOT · 1466860 · $86.00 per SY · qty 125.0 · bid tab
storm pipe 18-inchLF1$85.00$85.00 to $85.00
Bids
  • 2025-02-11 · SCDOT · 1470210 · $85.00 per LF · qty 1089.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.