Site-work prices, Anderson County, SC

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementSY2$3.00$2.05 to $3.95
Bids
  • 2025-12-09 · SCDOT · 0474290 · $3.95 per SY · qty 244080.0 · bid tab
  • 2025-12-09 · SCDOT · 0474290 · $2.05 per SY · qty 449856.101 · bid tab
asphalt pavementTON54$143.75$73.15 to $885.00
Bids
  • 2025-12-09 · SCDOT · 0474290 · $840.00 per TON · qty 3235.352 · bid tab
  • 2025-12-09 · SCDOT · 0474290 · $685.00 per TON · qty 1454.31 · bid tab
  • 2025-12-09 · SCDOT · 0474290 · $136.00 per TON · qty 6320.0 · bid tab
  • 2025-12-09 · SCDOT · 0474290 · $137.50 per TON · qty 46576.639 · bid tab
  • 2025-12-09 · SCDOT · 0474290 · $120.00 per TON · qty 22374.0 · bid tab
  • 2025-10-14 · SCDOT · 0474760 · $105.00 per TON · qty 2848.0 · bid tab
  • 2025-10-14 · SCDOT · 0474760 · $95.00 per TON · qty 556.0 · bid tab
  • 2025-10-14 · SCDOT · 0474760 · $685.00 per TON · qty 411.0 · bid tab
  • 2025-10-14 · SCDOT · 0474760 · $92.50 per TON · qty 142.0 · bid tab
  • 2025-10-14 · SCDOT · 0474760 · $97.50 per TON · qty 2567.0 · bid tab
(10 most recent of 54 shown; all in the Hubstake feed)
concrete pavementSY1$205.00$205.00 to $205.00
Bids
  • 2024-11-13 · SCDOT · 0450000 · $205.00 per SY · qty 599.0 · bid tab
curb gutterLF11$35.00$0.60 to $3,645.00
Bids
  • 2025-09-09 · SCDOT · 0473740 · $0.80 per LF · qty 1480.0 · bid tab
  • 2024-11-13 · SCDOT · 0450000 · $35.00 per LF · qty 4381.0 · bid tab
  • 2024-11-13 · SCDOT · 0450000 · $0.60 per LF · qty 1178.0 · bid tab
  • 2024-11-13 · SCDOT · 0450000 · $60.00 per LF · qty 39.0 · bid tab
  • 2024-11-13 · SCDOT · 0469980 · $1.55 per LF · qty 3200.0 · bid tab
  • 2024-04-09 · SCDOT · 0456381 · $43.86 per LF · qty 1430.0 · bid tab
  • 2024-04-09 · SCDOT · 0456381 · $3,645.00 per LF · qty 32.0 · bid tab
  • 2024-03-12 · SCDOT · 0447750 · $60.00 per LF · qty 63.0 · bid tab
  • 2024-03-12 · SCDOT · 0466130 · $1.10 per LF · qty 2180.0 · bid tab
  • 2023-12-12 · SCDOT · 0451530 · $130.00 per LF · qty 125.0 · bid tab
(10 most recent of 11 shown; all in the Hubstake feed)
excavation embankmentCY17$25.00$8.90 to $230.00
Bids
  • 2025-10-14 · SCDOT · 0474760 · $24.00 per CY · qty 4136.0 · bid tab
  • 2025-10-14 · SCDOT · 0474760 · $135.00 per CY · qty 556.0 · bid tab
  • 2025-09-09 · SCDOT · 0473740 · $230.00 per CY · qty 10745.0 · bid tab
  • 2025-09-09 · SCDOT · 0473740 · $150.00 per CY · qty 475.0 · bid tab
  • 2025-06-10 · SCDOT · 0454510 · $8.90 per CY · qty 1635.0 · bid tab
  • 2025-06-10 · SCDOT · 0454510 · $11.44 per CY · qty 4468.0 · bid tab
  • 2024-11-13 · SCDOT · 0450000 · $16.00 per CY · qty 12973.0 · bid tab
  • 2024-11-13 · SCDOT · 0450000 · $17.68 per CY · qty 2843.0 · bid tab
  • 2024-11-13 · SCDOT · 0451470 · $24.00 per CY · qty 9144.0 · bid tab
  • 2024-11-13 · SCDOT · 0451470 · $12.00 per CY · qty 1832.0 · bid tab
(10 most recent of 17 shown; all in the Hubstake feed)
inlet headwallEA7$4,750.00$1,700.00 to $12,000.00
Bids
  • 2025-10-14 · SCDOT · 0474760 · $12,000.00 per EA · qty 2.0 · bid tab
  • 2024-11-13 · SCDOT · 0450000 · $3,250.00 per EA · qty 4.0 · bid tab
  • 2024-11-13 · SCDOT · 0450000 · $1,700.00 per EA · qty 2.0 · bid tab
  • 2024-04-09 · SCDOT · 0456381 · $6,490.00 per EA · qty 6.0 · bid tab
  • 2024-04-09 · SCDOT · 0456381 · $11,330.00 per EA · qty 1.0 · bid tab
  • 2024-03-12 · SCDOT · 0447750 · $4,750.00 per EA · qty 1.0 · bid tab
  • 2023-12-12 · SCDOT · 0451530 · $4,400.00 per EA · qty 2.0 · bid tab
lime cement stabilizationLB7$0.60$0.50 to $2.20
Bids
  • 2025-10-14 · SCDOT · 0474760 · $1.00 per LB · qty 8840.0 · bid tab
  • 2025-06-10 · SCDOT · 0454510 · $0.56 per LB · qty 6984.0 · bid tab
  • 2024-11-13 · SCDOT · 0450000 · $0.60 per LB · qty 46716.0 · bid tab
  • 2024-11-13 · SCDOT · 0451470 · $0.50 per LB · qty 2757.346 · bid tab
  • 2024-04-09 · SCDOT · 0456381 · $2.20 per LB · qty 995.0 · bid tab
  • 2024-03-12 · SCDOT · 0447750 · $1.15 per LB · qty 400.0 · bid tab
  • 2023-12-12 · SCDOT · 0451530 · $0.50 per LB · qty 7960.0 · bid tab
lime cement stabilizationSY9$17.00$1.00 to $31.80
Bids
  • 2025-10-14 · SCDOT · 0474760 · $31.80 per SY · qty 825.0 · bid tab
  • 2025-10-14 · SCDOT · 0474760 · $12.50 per SY · qty 26398.0 · bid tab
  • 2025-09-09 · SCDOT · 0473740 · $18.00 per SY · qty 8000.0 · bid tab
  • 2025-06-10 · SCDOT · 0454510 · $13.20 per SY · qty 1100.0 · bid tab
  • 2024-11-13 · SCDOT · 0450000 · $17.21 per SY · qty 1100.0 · bid tab
  • 2024-11-13 · SCDOT · 0451470 · $10.00 per SY · qty 550.0 · bid tab
  • 2024-04-09 · SCDOT · 0456381 · $17.00 per SY · qty 550.0 · bid tab
  • 2024-03-12 · SCDOT · 0447750 · $1.00 per SY · qty 550.0 · bid tab
  • 2023-12-12 · SCDOT · 0451530 · $25.75 per SY · qty 275.0 · bid tab
lime cement stabilizationTON2$242.50$235.00 to $250.00
Bids
  • 2025-10-14 · SCDOT · 0474760 · $250.00 per TON · qty 1056.0 · bid tab
  • 2025-09-09 · SCDOT · 0473740 · $235.00 per TON · qty 290.0 · bid tab
manholeEA6$5,400.00$1,000.00 to $7,700.00
Bids
  • 2025-06-10 · SCDOT · 0454510 · $1,000.00 per EA · qty 1.0 · bid tab
  • 2024-11-13 · SCDOT · 0450000 · $3,500.00 per EA · qty 9.0 · bid tab
  • 2024-04-09 · SCDOT · 0456381 · $7,700.00 per EA · qty 1.0 · bid tab
  • 2024-04-09 · SCDOT · 0456381 · $6,750.00 per EA · qty 3.0 · bid tab
  • 2023-12-12 · SCDOT · 0451530 · $5,400.00 per EA · qty 1.0 · bid tab
  • 2023-12-12 · SCDOT · 0451530 · $5,400.00 per EA · qty 1.0 · bid tab
sidewalkSY11$201.00$115.00 to $438.05
Bids
  • 2025-09-09 · SCDOT · 0473740 · $210.00 per SY · qty 100.0 · bid tab
  • 2024-12-10 · SCDOT · 0460340 · $312.00 per SY · qty 420.0 · bid tab
  • 2024-11-13 · SCDOT · 0450000 · $300.00 per SY · qty 29.0 · bid tab
  • 2024-11-13 · SCDOT · 0450000 · $125.00 per SY · qty 102.0 · bid tab
  • 2024-11-13 · SCDOT · 0469980 · $201.00 per SY · qty 50.0 · bid tab
  • 2024-04-09 · SCDOT · 0456381 · $133.00 per SY · qty 190.0 · bid tab
  • 2024-04-09 · SCDOT · 0456381 · $438.05 per SY · qty 50.0 · bid tab
  • 2024-03-12 · SCDOT · 0447750 · $175.00 per SY · qty 100.0 · bid tab
  • 2024-03-12 · SCDOT · 0447750 · $135.00 per SY · qty 63.0 · bid tab
  • 2024-03-12 · SCDOT · 0447750 · $115.00 per SY · qty 260.0 · bid tab
(10 most recent of 11 shown; all in the Hubstake feed)
storm pipe 18-inchLF2$514.00$128.00 to $900.00
Bids
  • 2025-06-10 · SCDOT · 0454510 · $128.00 per LF · qty 96.0 · bid tab
  • 2023-12-12 · SCDOT · 0451530 · $900.00 per LF · qty 168.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.