| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | CY | 3 | $360.00 | $360.00 to $395.00 | Bids- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $395.00 per CY · qty 20.0 · bid tab
- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $360.00 per CY · qty 32.0 · bid tab
- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $360.00 per CY · qty 33.0 · bid tab
|
| curb gutter | FT | 1 | $55.00 | $55.00 to $55.00 | Bids- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $55.00 per FT · qty 41.0 · bid tab
|
| fire hydrant | EA | 1 | $11,400.00 | $11,400.00 to $11,400.00 | Bids- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $11,400.00 per EA · qty 3.0 · bid tab
|
| flexible base | CY | 1 | $40.00 | $40.00 to $40.00 | Bids- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $40.00 per CY · qty 118.0 · bid tab
|
| sewer service | FT | 2 | $30.50 | $22.00 to $39.00 | Bids- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $39.00 per FT · qty 20.0 · bid tab
- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $22.00 per FT · qty 20.0 · bid tab
|
| sidewalk | SF | 1 | $9.00 | $9.00 to $9.00 | Bids- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $9.00 per SF · qty 1204.0 · bid tab
|
| storm pipe 12-inch | FT | 1 | $80.00 | $80.00 to $80.00 | Bids- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $80.00 per FT · qty 20.0 · bid tab
|
| water main 12-inch | FT | 1 | $121.00 | $121.00 to $121.00 | Bids- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $121.00 per FT · qty 1134.0 · bid tab
|
| water main 4-inch | FT | 1 | $124.00 | $124.00 to $124.00 | Bids- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $124.00 per FT · qty 27.0 · bid tab
|
| water main 6-inch | FT | 1 | $220.00 | $220.00 to $220.00 | Bids- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $220.00 per FT · qty 24.0 · bid tab
|
| water main 8-inch | FT | 1 | $140.00 | $140.00 to $140.00 | Bids- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $140.00 per FT · qty 233.0 · bid tab
|
| water service | FT | 1 | $55.00 | $55.00 to $55.00 | Bids- 2025-11-24 · Preble County Board of Commissioners (owner per Choice One Engineering posting) · Water Transmission Main Phase 1 · $55.00 per FT · qty 616.0 · bid tab
|