Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| asphalt pavement | TON | 1 | $450.00 | $450.00 to $450.00 | Bids
|
| curb gutter | LF | 1 | $30.00 | $30.00 to $30.00 | Bids
|
| excavation embankment | CY | 2 | $10.01 | $0.01 to $20.00 | |
| fire hydrant | EA | 1 | $5,500.00 | $5,500.00 to $5,500.00 | Bids
|
| fire hydrant | LF | 1 | $223.00 | $223.00 to $223.00 | Bids
|
| flexible base | TON | 1 | $70.00 | $70.00 to $70.00 | Bids
|
| lime cement stabilization | SY | 2 | $4.00 | $3.00 to $5.00 | |
| lime cement stabilization | TON | 2 | $67.50 | $65.00 to $70.00 | |
| storm pipe 15-inch | LF | 1 | $73.15 | $73.15 to $73.15 | Bids
|
| storm pipe 18-inch | LF | 1 | $91.00 | $91.00 to $91.00 | Bids
|
| storm pipe 24-inch | LF | 2 | $124.50 | $116.00 to $133.00 | |
| storm pipe 30-inch | LF | 1 | $152.00 | $152.00 to $152.00 | Bids
|
| storm pipe 36-inch | LF | 1 | $197.00 | $197.00 to $197.00 | Bids
|
| storm pipe 42-inch | LF | 1 | $253.00 | $253.00 to $253.00 | Bids
|
| storm pipe 48-inch | LF | 1 | $325.00 | $325.00 to $325.00 | Bids
|
| storm pipe 54-inch | LF | 1 | $450.00 | $450.00 to $450.00 | Bids
|
| storm pipe 60-inch | LF | 1 | $520.00 | $520.00 to $520.00 | Bids
|
| storm pipe 72-inch | LF | 1 | $750.00 | $750.00 to $750.00 | Bids
|
| water main 6-inch | LF | 1 | $110.00 | $110.00 to $110.00 | Bids
|
| water main 8-inch | LF | 1 | $25.00 | $25.00 to $25.00 | Bids
|
| water service | LF | 1 | $68.50 | $68.50 to $68.50 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.