| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 4 | $567.50 | $145.00 to $1,114.29 | Bids- 2026-09-24 · NCDOT · C205140 · $1,114.29 per TON · qty 180.0 · bid tab
- 2026-06-16 · NCDOT · C205213 · $685.00 per TON · qty 1798.0 · bid tab
- 2026-06-16 · NCDOT · C205213 · $145.00 per TON · qty 60.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $450.00 per TON · qty 3200.0 · bid tab
|
| curb gutter | LF | 3 | $35.00 | $25.00 to $100.29 | Bids- 2026-09-24 · NCDOT · C205140 · $100.29 per LF · qty 701.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $35.00 per LF · qty 28500.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $25.00 per LF · qty 5500.0 · bid tab
|
| excavation embankment | CY | 2 | $90.00 | $50.00 to $130.00 | Bids- 2026-06-16 · NCDOT · C205213 · $50.00 per CY · qty 1236.0 · bid tab
- 2026-06-16 · NCDOT · C205213 · $130.00 per CY · qty 18.0 · bid tab
|
| fire hydrant | EA | 1 | $7,000.00 | $7,000.00 to $7,000.00 | Bids- 2024-11-19 · NCDOT · C204942 · $7,000.00 per EA · qty 1.0 · bid tab
|
| fire hydrant | LF | 1 | $225.00 | $225.00 to $225.00 | Bids- 2024-11-19 · NCDOT · C204942 · $225.00 per LF · qty 130.0 · bid tab
|
| flexible base | TON | 2 | $62.95 | $50.00 to $75.91 | Bids- 2026-09-24 · NCDOT · C205140 · $75.91 per TON · qty 120.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $50.00 per TON · qty 4500.0 · bid tab
|
| inlet headwall | EA | 2 | $984.74 | $244.48 to $1,725.00 | Bids- 2026-09-24 · NCDOT · C205140 · $244.48 per EA · qty 18.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $1,725.00 per EA · qty 60.0 · bid tab
|
| lime cement stabilization | SY | 4 | $5.75 | $4.14 to $6.08 | Bids- 2026-09-24 · NCDOT · C205140 · $4.14 per SY · qty 200.0 · bid tab
- 2026-09-24 · NCDOT · C205140 · $6.08 per SY · qty 300.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $5.50 per SY · qty 4300.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $6.00 per SY · qty 300.0 · bid tab
|
| lime cement stabilization | TON | 3 | $50.00 | $50.00 to $74.34 | Bids- 2026-09-24 · NCDOT · C205140 · $74.34 per TON · qty 200.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $50.00 per TON · qty 500.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $50.00 per TON · qty 190.0 · bid tab
|
| manhole | EA | 9 | $1,800.00 | $650.00 to $23,750.00 | Bids- 2026-06-16 · NCDOT · C205213 · $1,050.00 per EA · qty 44.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $23,750.00 per EA · qty 2.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $1,800.00 per EA · qty 3.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $650.00 per EA · qty 38.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $1,300.00 per EA · qty 29.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $3,500.00 per EA · qty 6.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $16,500.00 per EA · qty 11.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $1,475.00 per EA · qty 3.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $11,000.00 per EA · qty 1.0 · bid tab
|
| sewer main 10-inch | LF | 1 | $145.00 | $145.00 to $145.00 | Bids- 2024-11-19 · NCDOT · C204942 · $145.00 per LF · qty 160.0 · bid tab
|
| sewer main 8-inch | LF | 1 | $115.00 | $115.00 to $115.00 | Bids- 2024-11-19 · NCDOT · C204942 · $115.00 per LF · qty 1705.0 · bid tab
|
| sewer service | LF | 1 | $200.00 | $200.00 to $200.00 | Bids- 2024-11-19 · NCDOT · C204942 · $200.00 per LF · qty 491.0 · bid tab
|
| sidewalk | EA | 2 | $6,983.58 | $6,000.00 to $7,967.16 | Bids- 2026-09-24 · NCDOT · C205140 · $7,967.16 per EA · qty 4.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $6,000.00 per EA · qty 106.0 · bid tab
|
| sidewalk | SY | 4 | $123.50 | $55.00 to $501.43 | Bids- 2026-09-24 · NCDOT · C205140 · $117.00 per SY · qty 550.0 · bid tab
- 2026-09-24 · NCDOT · C205140 · $501.43 per SY · qty 60.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $55.00 per SY · qty 6440.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $130.00 per SY · qty 3090.0 · bid tab
|
| storm pipe 15-inch | LF | 2 | $157.10 | $92.00 to $222.20 | Bids- 2026-09-24 · NCDOT · C205140 · $222.20 per LF · qty 162.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $92.00 per LF · qty 11084.0 · bid tab
|
| storm pipe 18-inch | LF | 3 | $205.76 | $107.00 to $206.00 | Bids- 2026-09-24 · NCDOT · C205140 · $205.76 per LF · qty 149.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $206.00 per LF · qty 52.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $107.00 per LF · qty 4092.0 · bid tab
|
| storm pipe 24-inch | LF | 1 | $143.00 | $143.00 to $143.00 | Bids- 2024-11-19 · NCDOT · C204942 · $143.00 per LF · qty 5456.0 · bid tab
|
| storm pipe 28-inch | LF | 1 | $350.00 | $350.00 to $350.00 | Bids- 2024-11-19 · NCDOT · C204942 · $350.00 per LF · qty 174.0 · bid tab
|
| storm pipe 30-inch | LF | 1 | $188.00 | $188.00 to $188.00 | Bids- 2024-11-19 · NCDOT · C204942 · $188.00 per LF · qty 1608.0 · bid tab
|
| storm pipe 36-inch | LF | 1 | $245.00 | $245.00 to $245.00 | Bids- 2024-11-19 · NCDOT · C204942 · $245.00 per LF · qty 1576.0 · bid tab
|
| storm pipe 42-inch | LF | 1 | $308.00 | $308.00 to $308.00 | Bids- 2024-11-19 · NCDOT · C204942 · $308.00 per LF · qty 2764.0 · bid tab
|
| storm pipe 48-inch | LF | 1 | $448.00 | $448.00 to $448.00 | Bids- 2024-11-19 · NCDOT · C204942 · $448.00 per LF · qty 392.0 · bid tab
|
| storm pipe 54-inch | LF | 1 | $620.00 | $620.00 to $620.00 | Bids- 2024-11-19 · NCDOT · C204942 · $620.00 per LF · qty 208.0 · bid tab
|
| storm pipe 66-inch | LF | 1 | $1,000.00 | $1,000.00 to $1,000.00 | Bids- 2024-11-19 · NCDOT · C204942 · $1,000.00 per LF · qty 156.0 · bid tab
|
| water main 10-inch | LF | 1 | $163.00 | $163.00 to $163.00 | Bids- 2024-11-19 · NCDOT · C204942 · $163.00 per LF · qty 124.0 · bid tab
|
| water main 12-inch | LF | 1 | $131.00 | $131.00 to $131.00 | Bids- 2024-11-19 · NCDOT · C204942 · $131.00 per LF · qty 1132.0 · bid tab
|
| water main 16-inch | LF | 2 | $369.57 | $143.00 to $596.14 | Bids- 2026-09-24 · NCDOT · C205140 · $596.14 per LF · qty 112.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $143.00 per LF · qty 9111.0 · bid tab
|
| water main 20-inch | LF | 1 | $529.29 | $529.29 to $529.29 | Bids- 2026-09-24 · NCDOT · C205140 · $529.29 per LF · qty 255.0 · bid tab
|
| water main 6-inch | LF | 1 | $84.00 | $84.00 to $84.00 | Bids- 2024-11-19 · NCDOT · C204942 · $84.00 per LF · qty 987.5 · bid tab
|
| water main 8-inch | LF | 2 | $538.36 | $85.00 to $991.72 | Bids- 2026-09-24 · NCDOT · C205140 · $991.72 per LF · qty 52.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $85.00 per LF · qty 7042.5 · bid tab
|
| water service | LF | 2 | $336.43 | $60.00 to $612.86 | Bids- 2026-09-24 · NCDOT · C205140 · $612.86 per LF · qty 18.0 · bid tab
- 2024-11-19 · NCDOT · C204942 · $60.00 per LF · qty 1432.0 · bid tab
|