| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 4 | $527.50 | $415.00 to $650.00 | Bids- 2025-11-18 · NCDOT · C205155 · $580.00 per TON · qty 1943.0 · bid tab
- 2025-09-16 · NCDOT · C205042 · $650.00 per TON · qty 285.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $475.00 per TON · qty 7045.0 · bid tab
- 2024-11-19 · NCDOT · C204997 · $415.00 per TON · qty 2579.0 · bid tab
|
| curb gutter | LF | 6 | $35.50 | $31.00 to $65.00 | Bids- 2025-09-16 · NCDOT · C205042 · $65.00 per LF · qty 5210.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $39.00 per LF · qty 1730.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $31.00 per LF · qty 2180.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $53.00 per LF · qty 120.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $32.00 per LF · qty 15800.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $31.20 per LF · qty 15650.0 · bid tab
|
| excavation embankment | CY | 2 | $4.38 | $1.00 to $7.75 | Bids- 2024-11-19 · NCDOT · C204949 · $7.75 per CY · qty 91000.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $1.00 per CY · qty 174000.0 · bid tab
|
| fire hydrant | EA | 1 | $8,000.00 | $8,000.00 to $8,000.00 | Bids- 2025-09-16 · NCDOT · C205042 · $8,000.00 per EA · qty 1.0 · bid tab
|
| fire hydrant | LF | 2 | $70.00 | $65.00 to $75.00 | Bids- 2025-09-16 · NCDOT · C205042 · $75.00 per LF · qty 10.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $65.00 per LF · qty 587.0 · bid tab
|
| flexible base | TON | 1 | $40.00 | $40.00 to $40.00 | Bids- 2024-11-19 · NCDOT · C204949 · $40.00 per TON · qty 4900.0 · bid tab
|
| lime cement stabilization | SY | 3 | $4.75 | $3.25 to $6.00 | Bids- 2025-09-16 · NCDOT · C205042 · $6.00 per SY · qty 200.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $3.25 per SY · qty 3750.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $4.75 per SY · qty 900.0 · bid tab
|
| lime cement stabilization | TON | 1 | $35.00 | $35.00 to $35.00 | Bids- 2024-11-19 · NCDOT · C204949 · $35.00 per TON · qty 590.0 · bid tab
|
| manhole | EA | 5 | $900.00 | $650.00 to $10,600.00 | Bids- 2025-11-18 · NCDOT · C205155 · $700.00 per EA · qty 37.0 · bid tab
- 2025-09-16 · NCDOT · C205042 · $900.00 per EA · qty 5.0 · bid tab
- 2025-09-16 · NCDOT · C205042 · $930.00 per EA · qty 12.0 · bid tab
- 2025-09-16 · NCDOT · C205042 · $10,600.00 per EA · qty 10.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $650.00 per EA · qty 52.0 · bid tab
|
| sewer main 12-inch | LF | 2 | $166.00 | $117.00 to $215.00 | Bids- 2025-09-16 · NCDOT · C205042 · $215.00 per LF · qty 100.0 · bid tab
- 2025-09-16 · NCDOT · C205042 · $117.00 per LF · qty 1843.0 · bid tab
|
| sewer service | LF | 1 | $240.00 | $240.00 to $240.00 | Bids- 2025-09-16 · NCDOT · C205042 · $240.00 per LF · qty 340.0 · bid tab
|
| sidewalk | EA | 1 | $4,500.00 | $4,500.00 to $4,500.00 | Bids- 2025-09-16 · NCDOT · C205042 · $4,500.00 per EA · qty 32.0 · bid tab
|
| sidewalk | SY | 3 | $126.50 | $84.00 to $130.00 | Bids- 2025-09-16 · NCDOT · C205042 · $84.00 per SY · qty 1660.0 · bid tab
- 2025-09-16 · NCDOT · C205042 · $130.00 per SY · qty 400.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $126.50 per SY · qty 720.0 · bid tab
|
| storm pipe 15-inch | LF | 3 | $80.00 | $70.00 to $93.00 | Bids- 2025-09-16 · NCDOT · C205042 · $93.00 per LF · qty 1360.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $80.00 per LF · qty 5096.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $70.00 per LF · qty 684.0 · bid tab
|
| storm pipe 18-inch | LF | 3 | $95.00 | $75.00 to $130.00 | Bids- 2025-09-16 · NCDOT · C205042 · $130.00 per LF · qty 516.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $95.00 per LF · qty 8044.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $75.00 per LF · qty 3764.0 · bid tab
|
| storm pipe 24-inch | LF | 2 | $119.00 | $110.00 to $128.00 | Bids- 2024-11-19 · NCDOT · C204949 · $128.00 per LF · qty 944.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $110.00 per LF · qty 2496.0 · bid tab
|
| storm pipe 30-inch | LF | 3 | $165.00 | $144.00 to $179.00 | Bids- 2024-11-19 · NCDOT · C204949 · $165.00 per LF · qty 336.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $144.00 per LF · qty 1228.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $179.00 per LF · qty 176.0 · bid tab
|
| storm pipe 36-inch | LF | 2 | $191.50 | $173.00 to $210.00 | Bids- 2024-11-19 · NCDOT · C204949 · $210.00 per LF · qty 120.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $173.00 per LF · qty 284.0 · bid tab
|
| storm pipe 54-inch | LF | 1 | $536.00 | $536.00 to $536.00 | Bids- 2024-11-19 · NCDOT · C204949 · $536.00 per LF · qty 192.0 · bid tab
|
| water main 10-inch | LF | 1 | $25.00 | $25.00 to $25.00 | Bids- 2024-11-19 · NCDOT · C204949 · $25.00 per LF · qty 534.0 · bid tab
|
| water main 12-inch | LF | 1 | $142.00 | $142.00 to $142.00 | Bids- 2024-11-19 · NCDOT · C204949 · $142.00 per LF · qty 543.0 · bid tab
|
| water main 2-inch | LF | 2 | $54.00 | $43.00 to $65.00 | Bids- 2025-09-16 · NCDOT · C205042 · $65.00 per LF · qty 172.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $43.00 per LF · qty 444.0 · bid tab
|
| water main 3-inch | LF | 1 | $85.00 | $85.00 to $85.00 | Bids- 2025-09-16 · NCDOT · C205042 · $85.00 per LF · qty 128.0 · bid tab
|
| water main 6-inch | LF | 2 | $75.50 | $66.00 to $85.00 | Bids- 2025-09-16 · NCDOT · C205042 · $85.00 per LF · qty 2313.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $66.00 per LF · qty 585.0 · bid tab
|
| water main 8-inch | LF | 1 | $50.00 | $50.00 to $50.00 | Bids- 2024-11-19 · NCDOT · C204949 · $50.00 per LF · qty 11931.0 · bid tab
|
| water service | LF | 3 | $85.00 | $41.00 to $300.00 | Bids- 2025-09-16 · NCDOT · C205042 · $300.00 per LF · qty 12.0 · bid tab
- 2025-09-16 · NCDOT · C205042 · $85.00 per LF · qty 259.0 · bid tab
- 2024-11-19 · NCDOT · C204949 · $41.00 per LF · qty 1712.0 · bid tab
|