| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 4 | $550.00 | $500.00 to $758.94 | Bids- 2026-04-21 · NCDOT · C204857 · $500.00 per TON · qty 1490.0 · bid tab
- 2025-01-21 · NCDOT · C204972 · $575.00 per TON · qty 145.0 · bid tab
- 2024-02-20 · NCDOT · C204792 · $525.00 per TON · qty 85.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $758.94 per TON · qty 2740.0 · bid tab
|
| curb gutter | LF | 3 | $36.00 | $30.00 to $38.22 | Bids- 2026-04-21 · NCDOT · C204857 · $30.00 per LF · qty 1950.0 · bid tab
- 2025-01-21 · NCDOT · C204972 · $36.00 per LF · qty 835.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $38.22 per LF · qty 2760.0 · bid tab
|
| excavation embankment | CY | 6 | $15.75 | $5.00 to $51.00 | Bids- 2026-04-21 · NCDOT · C204857 · $19.50 per CY · qty 14500.0 · bid tab
- 2025-01-21 · NCDOT · C204972 · $12.00 per CY · qty 7665.0 · bid tab
- 2025-01-21 · NCDOT · C204972 · $51.00 per CY · qty 505.0 · bid tab
- 2024-02-20 · NCDOT · C204792 · $5.00 per CY · qty 6400.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $22.00 per CY · qty 174010.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $8.00 per CY · qty 32350.0 · bid tab
|
| fire hydrant | EA | 3 | $9,330.00 | $9,000.00 to $9,743.84 | Bids- 2026-04-21 · NCDOT · C204857 · $9,000.00 per EA · qty 5.0 · bid tab
- 2025-01-21 · NCDOT · C204972 · $9,330.00 per EA · qty 1.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $9,743.84 per EA · qty 4.0 · bid tab
|
| fire hydrant | LF | 3 | $150.00 | $143.00 to $337.28 | Bids- 2026-04-21 · NCDOT · C204857 · $150.00 per LF · qty 51.0 · bid tab
- 2025-01-21 · NCDOT · C204972 · $143.00 per LF · qty 9.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $337.28 per LF · qty 46.0 · bid tab
|
| flexible base | TON | 1 | $51.50 | $51.50 to $51.50 | Bids- 2026-04-21 · NCDOT · C204857 · $51.50 per TON · qty 1090.0 · bid tab
|
| inlet headwall | EA | 1 | $1,186.74 | $1,186.74 to $1,186.74 | Bids- 2023-11-21 · NCDOT · C204873 · $1,186.74 per EA · qty 2.0 · bid tab
|
| lime cement stabilization | SY | 7 | $3.00 | $1.00 to $5.10 | Bids- 2026-04-21 · NCDOT · C204857 · $4.50 per SY · qty 300.0 · bid tab
- 2026-04-21 · NCDOT · C204857 · $5.10 per SY · qty 700.0 · bid tab
- 2025-01-21 · NCDOT · C204972 · $3.00 per SY · qty 900.0 · bid tab
- 2025-01-21 · NCDOT · C204972 · $3.00 per SY · qty 300.0 · bid tab
- 2024-02-20 · NCDOT · C204792 · $1.00 per SY · qty 300.0 · bid tab
- 2024-02-20 · NCDOT · C204792 · $1.00 per SY · qty 300.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $1.45 per SY · qty 50300.0 · bid tab
|
| lime cement stabilization | TON | 4 | $32.90 | $15.00 to $47.00 | Bids- 2026-04-21 · NCDOT · C204857 · $47.00 per TON · qty 200.0 · bid tab
- 2025-01-21 · NCDOT · C204972 · $31.00 per TON · qty 600.0 · bid tab
- 2024-02-20 · NCDOT · C204792 · $15.00 per TON · qty 200.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $34.80 per TON · qty 22600.0 · bid tab
|
| manhole | EA | 10 | $1,901.83 | $650.00 to $23,500.00 | Bids- 2026-04-21 · NCDOT · C204857 · $950.00 per EA · qty 1.0 · bid tab
- 2026-04-21 · NCDOT · C204857 · $1,300.00 per EA · qty 6.0 · bid tab
- 2026-04-21 · NCDOT · C204857 · $650.00 per EA · qty 5.0 · bid tab
- 2024-02-20 · NCDOT · C204792 · $23,500.00 per EA · qty 2.0 · bid tab
- 2024-02-20 · NCDOT · C204792 · $4,100.00 per EA · qty 3.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $3,277.71 per EA · qty 2.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $2,319.31 per EA · qty 2.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $927.72 per EA · qty 8.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $7,495.26 per EA · qty 1.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $1,484.35 per EA · qty 7.0 · bid tab
|
| sewer main 8-inch | LF | 1 | $78.00 | $78.00 to $78.00 | Bids- 2024-02-20 · NCDOT · C204792 · $78.00 per LF · qty 285.0 · bid tab
|
| sewer service | LF | 1 | $262.34 | $262.34 to $262.34 | Bids- 2023-11-21 · NCDOT · C204873 · $262.34 per LF · qty 54.0 · bid tab
|
| sidewalk | EA | 2 | $3,357.52 | $2,650.00 to $4,065.04 | Bids- 2026-04-21 · NCDOT · C204857 · $2,650.00 per EA · qty 2.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $4,065.04 per EA · qty 11.0 · bid tab
|
| sidewalk | SY | 4 | $73.50 | $54.00 to $145.04 | Bids- 2026-04-21 · NCDOT · C204857 · $54.00 per SY · qty 570.0 · bid tab
- 2026-04-21 · NCDOT · C204857 · $87.00 per SY · qty 1160.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $60.00 per SY · qty 1020.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $145.04 per SY · qty 100.0 · bid tab
|
| storm pipe 15-inch | LF | 4 | $125.00 | $90.24 to $130.00 | Bids- 2026-04-21 · NCDOT · C204857 · $125.00 per LF · qty 308.0 · bid tab
- 2026-04-21 · NCDOT · C204857 · $130.00 per LF · qty 824.0 · bid tab
- 2025-01-21 · NCDOT · C204972 · $125.00 per LF · qty 248.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $90.24 per LF · qty 812.0 · bid tab
|
| storm pipe 18-inch | LF | 5 | $138.00 | $100.47 to $151.00 | Bids- 2026-04-21 · NCDOT · C204857 · $142.00 per LF · qty 956.0 · bid tab
- 2026-04-21 · NCDOT · C204857 · $151.00 per LF · qty 40.0 · bid tab
- 2025-01-21 · NCDOT · C204972 · $138.00 per LF · qty 504.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $100.47 per LF · qty 264.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $107.30 per LF · qty 904.0 · bid tab
|
| storm pipe 24-inch | LF | 4 | $147.60 | $136.84 to $172.00 | Bids- 2026-04-21 · NCDOT · C204857 · $172.00 per LF · qty 176.0 · bid tab
- 2024-02-20 · NCDOT · C204792 · $150.00 per LF · qty 84.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $145.20 per LF · qty 88.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $136.84 per LF · qty 312.0 · bid tab
|
| storm pipe 30-inch | LF | 5 | $233.00 | $176.11 to $315.00 | Bids- 2026-04-21 · NCDOT · C204857 · $291.00 per LF · qty 96.0 · bid tab
- 2026-04-21 · NCDOT · C204857 · $315.00 per LF · qty 156.0 · bid tab
- 2026-04-21 · NCDOT · C204857 · $233.00 per LF · qty 32.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $192.84 per LF · qty 168.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $176.11 per LF · qty 296.0 · bid tab
|
| storm pipe 42-inch | LF | 1 | $308.02 | $308.02 to $308.02 | Bids- 2023-11-21 · NCDOT · C204873 · $308.02 per LF · qty 100.0 · bid tab
|
| storm pipe 8-inch | LF | 1 | $150.00 | $150.00 to $150.00 | Bids- 2026-04-21 · NCDOT · C204857 · $150.00 per LF · qty 162.0 · bid tab
|
| water main 12-inch | LF | 2 | $151.82 | $135.00 to $168.65 | Bids- 2026-04-21 · NCDOT · C204857 · $135.00 per LF · qty 4513.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $168.65 per LF · qty 2123.0 · bid tab
|
| water main 16-inch | LF | 4 | $348.50 | $143.66 to $790.00 | Bids- 2026-04-21 · NCDOT · C204857 · $180.00 per LF · qty 2859.0 · bid tab
- 2025-01-21 · NCDOT · C204972 · $790.00 per LF · qty 475.0 · bid tab
- 2024-02-20 · NCDOT · C204792 · $517.00 per LF · qty 50.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $143.66 per LF · qty 349.0 · bid tab
|
| water main 20-inch | LF | 1 | $118.00 | $118.00 to $118.00 | Bids- 2024-02-20 · NCDOT · C204792 · $118.00 per LF · qty 538.0 · bid tab
|
| water main 4-inch | LF | 1 | $85.00 | $85.00 to $85.00 | Bids- 2026-04-21 · NCDOT · C204857 · $85.00 per LF · qty 21.0 · bid tab
|
| water main 6-inch | LF | 2 | $316.07 | $70.00 to $562.14 | Bids- 2026-04-21 · NCDOT · C204857 · $70.00 per LF · qty 2570.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $562.14 per LF · qty 61.0 · bid tab
|
| water main 8-inch | LF | 1 | $156.15 | $156.15 to $156.15 | Bids- 2023-11-21 · NCDOT · C204873 · $156.15 per LF · qty 2169.0 · bid tab
|
| water service | LF | 4 | $55.50 | $22.00 to $87.45 | Bids- 2026-04-21 · NCDOT · C204857 · $35.00 per LF · qty 1539.0 · bid tab
- 2025-01-21 · NCDOT · C204972 · $76.00 per LF · qty 18.0 · bid tab
- 2024-02-20 · NCDOT · C204792 · $22.00 per LF · qty 31.0 · bid tab
- 2023-11-21 · NCDOT · C204873 · $87.45 per LF · qty 176.0 · bid tab
|