Site-work prices, Jackson County, NC

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON2$718.90$690.00 to $747.80
Bids
  • 2025-11-18 · NCDOT · C205086 · $747.80 per TON · qty 3865.0 · bid tab
  • 2024-01-16 · NCDOT · C204828 · $690.00 per TON · qty 190.0 · bid tab
curb gutterLF4$40.65$31.60 to $44.00
Bids
  • 2025-11-18 · NCDOT · C205086 · $31.60 per LF · qty 7700.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $43.50 per LF · qty 4700.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $44.00 per LF · qty 28200.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $37.80 per LF · qty 3300.0 · bid tab
excavation embankmentCY2$39.60$26.75 to $52.45
Bids
  • 2025-11-18 · NCDOT · C205086 · $52.45 per CY · qty 160.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $26.75 per CY · qty 87500.0 · bid tab
fire hydrantEA2$5,795.50$3,116.00 to $8,475.00
Bids
  • 2025-11-18 · NCDOT · C205086 · $8,475.00 per EA · qty 12.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $3,116.00 per EA · qty 3.0 · bid tab
fire hydrantLF1$155.80$155.80 to $155.80
Bids
  • 2025-11-18 · NCDOT · C205086 · $155.80 per LF · qty 481.0 · bid tab
flexible baseTON2$57.00$39.00 to $75.00
Bids
  • 2025-11-18 · NCDOT · C205086 · $75.00 per TON · qty 400.0 · bid tab
  • 2024-01-16 · NCDOT · C204828 · $39.00 per TON · qty 650.0 · bid tab
inlet headwallEA1$2,354.00$2,354.00 to $2,354.00
Bids
  • 2025-11-18 · NCDOT · C205086 · $2,354.00 per EA · qty 34.0 · bid tab
lime cement stabilizationEA2$1,558.00$1,246.00 to $1,870.00
Bids
  • 2025-11-18 · NCDOT · C205086 · $1,870.00 per EA · qty 10.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $1,246.00 per EA · qty 5.0 · bid tab
lime cement stabilizationSY5$6.00$5.15 to $553.40
Bids
  • 2025-11-18 · NCDOT · C205086 · $553.40 per SY · qty 300.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $6.35 per SY · qty 15900.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $5.15 per SY · qty 3900.0 · bid tab
  • 2024-01-16 · NCDOT · C204828 · $6.00 per SY · qty 400.0 · bid tab
  • 2024-01-16 · NCDOT · C204828 · $6.00 per SY · qty 300.0 · bid tab
lime cement stabilizationTON2$53.30$40.00 to $66.60
Bids
  • 2025-11-18 · NCDOT · C205086 · $66.60 per TON · qty 15050.0 · bid tab
  • 2024-01-16 · NCDOT · C204828 · $40.00 per TON · qty 200.0 · bid tab
manholeEA5$1,870.00$1,371.00 to $9,348.00
Bids
  • 2025-11-18 · NCDOT · C205086 · $1,371.00 per EA · qty 32.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $1,870.00 per EA · qty 6.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $1,558.00 per EA · qty 42.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $3,178.00 per EA · qty 4.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $9,348.00 per EA · qty 124.0 · bid tab
sewer main 10-inchLF1$236.80$236.80 to $236.80
Bids
  • 2025-11-18 · NCDOT · C205086 · $236.80 per LF · qty 599.0 · bid tab
sewer main 12-inchLF1$249.30$249.30 to $249.30
Bids
  • 2025-11-18 · NCDOT · C205086 · $249.30 per LF · qty 2806.0 · bid tab
sewer main 6-inchLF1$93.50$93.50 to $93.50
Bids
  • 2025-11-18 · NCDOT · C205086 · $93.50 per LF · qty 69.0 · bid tab
sewer main 8-inchLF1$224.30$224.30 to $224.30
Bids
  • 2025-11-18 · NCDOT · C205086 · $224.30 per LF · qty 10461.0 · bid tab
sewer serviceLF1$87.25$87.25 to $87.25
Bids
  • 2025-11-18 · NCDOT · C205086 · $87.25 per LF · qty 1711.0 · bid tab
sidewalkEA1$3,851.00$3,851.00 to $3,851.00
Bids
  • 2025-11-18 · NCDOT · C205086 · $3,851.00 per EA · qty 205.0 · bid tab
sidewalkSF1$68.55$68.55 to $68.55
Bids
  • 2025-11-18 · NCDOT · C205086 · $68.55 per SF · qty 753.5 · bid tab
sidewalkSY2$112.58$77.65 to $147.50
Bids
  • 2025-11-18 · NCDOT · C205086 · $147.50 per SY · qty 1600.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $77.65 per SY · qty 17262.0 · bid tab
storm pipe 12-inchLF1$98.80$98.80 to $98.80
Bids
  • 2025-11-18 · NCDOT · C205086 · $98.80 per LF · qty 180.0 · bid tab
storm pipe 15-inchLF3$125.00$100.90 to $139.60
Bids
  • 2025-11-18 · NCDOT · C205086 · $100.90 per LF · qty 208.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $139.60 per LF · qty 9888.0 · bid tab
  • 2024-01-16 · NCDOT · C204828 · $125.00 per LF · qty 112.0 · bid tab
storm pipe 18-inchLF2$128.05$114.90 to $141.20
Bids
  • 2025-11-18 · NCDOT · C205086 · $114.90 per LF · qty 88.0 · bid tab
  • 2025-11-18 · NCDOT · C205086 · $141.20 per LF · qty 5942.0 · bid tab
storm pipe 24-inchLF1$177.40$177.40 to $177.40
Bids
  • 2025-11-18 · NCDOT · C205086 · $177.40 per LF · qty 5644.0 · bid tab
storm pipe 30-inchLF1$247.80$247.80 to $247.80
Bids
  • 2025-11-18 · NCDOT · C205086 · $247.80 per LF · qty 3740.0 · bid tab
storm pipe 36-inchLF1$300.30$300.30 to $300.30
Bids
  • 2025-11-18 · NCDOT · C205086 · $300.30 per LF · qty 1332.0 · bid tab
storm pipe 42-inchLF1$469.60$469.60 to $469.60
Bids
  • 2025-11-18 · NCDOT · C205086 · $469.60 per LF · qty 212.0 · bid tab
storm pipe 48-inchLF1$537.80$537.80 to $537.80
Bids
  • 2025-11-18 · NCDOT · C205086 · $537.80 per LF · qty 560.0 · bid tab
storm pipe 54-inchLF1$590.80$590.80 to $590.80
Bids
  • 2025-11-18 · NCDOT · C205086 · $590.80 per LF · qty 648.0 · bid tab
storm pipe 60-inchLF1$694.10$694.10 to $694.10
Bids
  • 2025-11-18 · NCDOT · C205086 · $694.10 per LF · qty 808.0 · bid tab
storm pipe 72-inchLF1$1,587.00$1,587.00 to $1,587.00
Bids
  • 2025-11-18 · NCDOT · C205086 · $1,587.00 per LF · qty 148.0 · bid tab
water main 10-inchLF1$199.40$199.40 to $199.40
Bids
  • 2025-11-18 · NCDOT · C205086 · $199.40 per LF · qty 503.0 · bid tab
water main 12-inchLF1$189.40$189.40 to $189.40
Bids
  • 2025-11-18 · NCDOT · C205086 · $189.40 per LF · qty 11535.0 · bid tab
water main 2-inchLF1$68.55$68.55 to $68.55
Bids
  • 2025-11-18 · NCDOT · C205086 · $68.55 per LF · qty 1962.0 · bid tab
water main 6-inchLF1$112.20$112.20 to $112.20
Bids
  • 2025-11-18 · NCDOT · C205086 · $112.20 per LF · qty 1513.0 · bid tab
water main 8-inchLF1$115.90$115.90 to $115.90
Bids
  • 2025-11-18 · NCDOT · C205086 · $115.90 per LF · qty 17604.0 · bid tab
water serviceLF1$81.00$81.00 to $81.00
Bids
  • 2025-11-18 · NCDOT · C205086 · $81.00 per LF · qty 2800.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.