| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 2 | $718.90 | $690.00 to $747.80 | Bids- 2025-11-18 · NCDOT · C205086 · $747.80 per TON · qty 3865.0 · bid tab
- 2024-01-16 · NCDOT · C204828 · $690.00 per TON · qty 190.0 · bid tab
|
| curb gutter | LF | 4 | $40.65 | $31.60 to $44.00 | Bids- 2025-11-18 · NCDOT · C205086 · $31.60 per LF · qty 7700.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $43.50 per LF · qty 4700.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $44.00 per LF · qty 28200.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $37.80 per LF · qty 3300.0 · bid tab
|
| excavation embankment | CY | 2 | $39.60 | $26.75 to $52.45 | Bids- 2025-11-18 · NCDOT · C205086 · $52.45 per CY · qty 160.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $26.75 per CY · qty 87500.0 · bid tab
|
| fire hydrant | EA | 2 | $5,795.50 | $3,116.00 to $8,475.00 | Bids- 2025-11-18 · NCDOT · C205086 · $8,475.00 per EA · qty 12.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $3,116.00 per EA · qty 3.0 · bid tab
|
| fire hydrant | LF | 1 | $155.80 | $155.80 to $155.80 | Bids- 2025-11-18 · NCDOT · C205086 · $155.80 per LF · qty 481.0 · bid tab
|
| flexible base | TON | 2 | $57.00 | $39.00 to $75.00 | Bids- 2025-11-18 · NCDOT · C205086 · $75.00 per TON · qty 400.0 · bid tab
- 2024-01-16 · NCDOT · C204828 · $39.00 per TON · qty 650.0 · bid tab
|
| inlet headwall | EA | 1 | $2,354.00 | $2,354.00 to $2,354.00 | Bids- 2025-11-18 · NCDOT · C205086 · $2,354.00 per EA · qty 34.0 · bid tab
|
| lime cement stabilization | EA | 2 | $1,558.00 | $1,246.00 to $1,870.00 | Bids- 2025-11-18 · NCDOT · C205086 · $1,870.00 per EA · qty 10.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $1,246.00 per EA · qty 5.0 · bid tab
|
| lime cement stabilization | SY | 5 | $6.00 | $5.15 to $553.40 | Bids- 2025-11-18 · NCDOT · C205086 · $553.40 per SY · qty 300.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $6.35 per SY · qty 15900.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $5.15 per SY · qty 3900.0 · bid tab
- 2024-01-16 · NCDOT · C204828 · $6.00 per SY · qty 400.0 · bid tab
- 2024-01-16 · NCDOT · C204828 · $6.00 per SY · qty 300.0 · bid tab
|
| lime cement stabilization | TON | 2 | $53.30 | $40.00 to $66.60 | Bids- 2025-11-18 · NCDOT · C205086 · $66.60 per TON · qty 15050.0 · bid tab
- 2024-01-16 · NCDOT · C204828 · $40.00 per TON · qty 200.0 · bid tab
|
| manhole | EA | 5 | $1,870.00 | $1,371.00 to $9,348.00 | Bids- 2025-11-18 · NCDOT · C205086 · $1,371.00 per EA · qty 32.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $1,870.00 per EA · qty 6.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $1,558.00 per EA · qty 42.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $3,178.00 per EA · qty 4.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $9,348.00 per EA · qty 124.0 · bid tab
|
| sewer main 10-inch | LF | 1 | $236.80 | $236.80 to $236.80 | Bids- 2025-11-18 · NCDOT · C205086 · $236.80 per LF · qty 599.0 · bid tab
|
| sewer main 12-inch | LF | 1 | $249.30 | $249.30 to $249.30 | Bids- 2025-11-18 · NCDOT · C205086 · $249.30 per LF · qty 2806.0 · bid tab
|
| sewer main 6-inch | LF | 1 | $93.50 | $93.50 to $93.50 | Bids- 2025-11-18 · NCDOT · C205086 · $93.50 per LF · qty 69.0 · bid tab
|
| sewer main 8-inch | LF | 1 | $224.30 | $224.30 to $224.30 | Bids- 2025-11-18 · NCDOT · C205086 · $224.30 per LF · qty 10461.0 · bid tab
|
| sewer service | LF | 1 | $87.25 | $87.25 to $87.25 | Bids- 2025-11-18 · NCDOT · C205086 · $87.25 per LF · qty 1711.0 · bid tab
|
| sidewalk | EA | 1 | $3,851.00 | $3,851.00 to $3,851.00 | Bids- 2025-11-18 · NCDOT · C205086 · $3,851.00 per EA · qty 205.0 · bid tab
|
| sidewalk | SF | 1 | $68.55 | $68.55 to $68.55 | Bids- 2025-11-18 · NCDOT · C205086 · $68.55 per SF · qty 753.5 · bid tab
|
| sidewalk | SY | 2 | $112.58 | $77.65 to $147.50 | Bids- 2025-11-18 · NCDOT · C205086 · $147.50 per SY · qty 1600.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $77.65 per SY · qty 17262.0 · bid tab
|
| storm pipe 12-inch | LF | 1 | $98.80 | $98.80 to $98.80 | Bids- 2025-11-18 · NCDOT · C205086 · $98.80 per LF · qty 180.0 · bid tab
|
| storm pipe 15-inch | LF | 3 | $125.00 | $100.90 to $139.60 | Bids- 2025-11-18 · NCDOT · C205086 · $100.90 per LF · qty 208.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $139.60 per LF · qty 9888.0 · bid tab
- 2024-01-16 · NCDOT · C204828 · $125.00 per LF · qty 112.0 · bid tab
|
| storm pipe 18-inch | LF | 2 | $128.05 | $114.90 to $141.20 | Bids- 2025-11-18 · NCDOT · C205086 · $114.90 per LF · qty 88.0 · bid tab
- 2025-11-18 · NCDOT · C205086 · $141.20 per LF · qty 5942.0 · bid tab
|
| storm pipe 24-inch | LF | 1 | $177.40 | $177.40 to $177.40 | Bids- 2025-11-18 · NCDOT · C205086 · $177.40 per LF · qty 5644.0 · bid tab
|
| storm pipe 30-inch | LF | 1 | $247.80 | $247.80 to $247.80 | Bids- 2025-11-18 · NCDOT · C205086 · $247.80 per LF · qty 3740.0 · bid tab
|
| storm pipe 36-inch | LF | 1 | $300.30 | $300.30 to $300.30 | Bids- 2025-11-18 · NCDOT · C205086 · $300.30 per LF · qty 1332.0 · bid tab
|
| storm pipe 42-inch | LF | 1 | $469.60 | $469.60 to $469.60 | Bids- 2025-11-18 · NCDOT · C205086 · $469.60 per LF · qty 212.0 · bid tab
|
| storm pipe 48-inch | LF | 1 | $537.80 | $537.80 to $537.80 | Bids- 2025-11-18 · NCDOT · C205086 · $537.80 per LF · qty 560.0 · bid tab
|
| storm pipe 54-inch | LF | 1 | $590.80 | $590.80 to $590.80 | Bids- 2025-11-18 · NCDOT · C205086 · $590.80 per LF · qty 648.0 · bid tab
|
| storm pipe 60-inch | LF | 1 | $694.10 | $694.10 to $694.10 | Bids- 2025-11-18 · NCDOT · C205086 · $694.10 per LF · qty 808.0 · bid tab
|
| storm pipe 72-inch | LF | 1 | $1,587.00 | $1,587.00 to $1,587.00 | Bids- 2025-11-18 · NCDOT · C205086 · $1,587.00 per LF · qty 148.0 · bid tab
|
| water main 10-inch | LF | 1 | $199.40 | $199.40 to $199.40 | Bids- 2025-11-18 · NCDOT · C205086 · $199.40 per LF · qty 503.0 · bid tab
|
| water main 12-inch | LF | 1 | $189.40 | $189.40 to $189.40 | Bids- 2025-11-18 · NCDOT · C205086 · $189.40 per LF · qty 11535.0 · bid tab
|
| water main 2-inch | LF | 1 | $68.55 | $68.55 to $68.55 | Bids- 2025-11-18 · NCDOT · C205086 · $68.55 per LF · qty 1962.0 · bid tab
|
| water main 6-inch | LF | 1 | $112.20 | $112.20 to $112.20 | Bids- 2025-11-18 · NCDOT · C205086 · $112.20 per LF · qty 1513.0 · bid tab
|
| water main 8-inch | LF | 1 | $115.90 | $115.90 to $115.90 | Bids- 2025-11-18 · NCDOT · C205086 · $115.90 per LF · qty 17604.0 · bid tab
|
| water service | LF | 1 | $81.00 | $81.00 to $81.00 | Bids- 2025-11-18 · NCDOT · C205086 · $81.00 per LF · qty 2800.0 · bid tab
|