| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 6 | $635.00 | $610.00 to $735.00 | Bids- 2026-02-17 · NCDOT · C205172 · $620.00 per TON · qty 2697.0 · bid tab
- 2025-02-18 · NCDOT · C204989 · $610.00 per TON · qty 140.0 · bid tab
- 2025-02-18 · NCDOT · C205053 · $700.00 per TON · qty 2248.0 · bid tab
- 2024-07-16 · NCDOT · C204948 · $650.00 per TON · qty 26.0 · bid tab
- 2024-02-20 · NCDOT · C204920 · $617.00 per TON · qty 2196.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $735.00 per TON · qty 2415.0 · bid tab
|
| curb gutter | EA | 1 | $121.00 | $121.00 to $121.00 | Bids- 2023-11-21 · NCDOT · C204852 · $121.00 per EA · qty 40.0 · bid tab
|
| curb gutter | LF | 4 | $35.35 | $34.20 to $37.30 | Bids- 2023-11-21 · NCDOT · C204852 · $34.20 per LF · qty 450.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $37.30 per LF · qty 6400.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $34.20 per LF · qty 300.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $36.50 per LF · qty 18250.0 · bid tab
|
| excavation embankment | CY | 2 | $22.50 | $21.00 to $24.00 | Bids- 2023-11-21 · NCDOT · C204852 · $24.00 per CY · qty 36200.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $21.00 per CY · qty 161900.0 · bid tab
|
| fire hydrant | LF | 1 | $154.00 | $154.00 to $154.00 | Bids- 2023-11-21 · NCDOT · C204852 · $154.00 per LF · qty 491.0 · bid tab
|
| inlet headwall | EA | 1 | $1,240.00 | $1,240.00 to $1,240.00 | Bids- 2023-11-21 · NCDOT · C204852 · $1,240.00 per EA · qty 36.0 · bid tab
|
| lime cement stabilization | SY | 4 | $5.45 | $3.30 to $9.25 | Bids- 2025-02-18 · NCDOT · C204989 · $9.25 per SY · qty 668.0 · bid tab
- 2024-07-16 · NCDOT · C204948 · $5.50 per SY · qty 2000.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $3.30 per SY · qty 9500.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $5.40 per SY · qty 6400.0 · bid tab
|
| lime cement stabilization | TON | 3 | $69.50 | $49.20 to $73.00 | Bids- 2025-02-18 · NCDOT · C204989 · $73.00 per TON · qty 500.0 · bid tab
- 2024-07-16 · NCDOT · C204948 · $69.50 per TON · qty 1500.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $49.20 per TON · qty 4250.0 · bid tab
|
| manhole | EA | 13 | $1,120.00 | $400.00 to $4,910.00 | Bids- 2026-02-17 · NCDOT · C205172 · $450.00 per EA · qty 4.0 · bid tab
- 2026-02-17 · NCDOT · C205172 · $1,450.00 per EA · qty 6.0 · bid tab
- 2025-02-18 · NCDOT · C205053 · $1,050.00 per EA · qty 137.0 · bid tab
- 2025-02-18 · NCDOT · C205053 · $400.00 per EA · qty 4.0 · bid tab
- 2024-07-16 · NCDOT · C204948 · $550.00 per EA · qty 2.0 · bid tab
- 2024-02-20 · NCDOT · C204920 · $600.00 per EA · qty 5.0 · bid tab
- 2024-02-20 · NCDOT · C204920 · $1,200.00 per EA · qty 32.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $1,120.00 per EA · qty 26.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $750.00 per EA · qty 41.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $4,910.00 per EA · qty 24.0 · bid tab
(10 most recent of 13 shown; all in the Hubstake feed) |
| sewer main 8-inch | LF | 1 | $209.00 | $209.00 to $209.00 | Bids- 2023-11-21 · NCDOT · C204852 · $209.00 per LF · qty 2597.0 · bid tab
|
| sewer service | LF | 1 | $68.00 | $68.00 to $68.00 | Bids- 2023-11-21 · NCDOT · C204852 · $68.00 per LF · qty 45.0 · bid tab
|
| sidewalk | EA | 5 | $4,200.00 | $1,250.00 to $5,000.00 | Bids- 2025-02-18 · NCDOT · C205053 · $4,200.00 per EA · qty 45.0 · bid tab
- 2025-02-18 · NCDOT · C205053 · $1,250.00 per EA · qty 12.0 · bid tab
- 2024-02-20 · NCDOT · C204920 · $1,500.00 per EA · qty 1.0 · bid tab
- 2024-02-20 · NCDOT · C204920 · $5,000.00 per EA · qty 1.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $4,500.00 per EA · qty 35.0 · bid tab
|
| sidewalk | SY | 2 | $87.50 | $85.00 to $90.00 | Bids- 2023-11-21 · NCDOT · C204852 · $85.00 per SY · qty 7170.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $90.00 per SY · qty 160.0 · bid tab
|
| storm pipe 15-inch | LF | 2 | $85.00 | $81.00 to $89.00 | Bids- 2023-11-21 · NCDOT · C204852 · $89.00 per LF · qty 16.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $81.00 per LF · qty 116.0 · bid tab
|
| storm pipe 18-inch | LF | 2 | $103.50 | $92.00 to $115.00 | Bids- 2023-11-21 · NCDOT · C204852 · $115.00 per LF · qty 9272.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $92.00 per LF · qty 1160.0 · bid tab
|
| storm pipe 24-inch | LF | 3 | $132.00 | $114.00 to $481.00 | Bids- 2023-11-21 · NCDOT · C204852 · $132.00 per LF · qty 3100.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $481.00 per LF · qty 40.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $114.00 per LF · qty 220.0 · bid tab
|
| storm pipe 30-inch | LF | 2 | $158.00 | $152.00 to $164.00 | Bids- 2023-11-21 · NCDOT · C204852 · $152.00 per LF · qty 228.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $164.00 per LF · qty 376.0 · bid tab
|
| storm pipe 36-inch | LF | 2 | $212.00 | $192.00 to $232.00 | Bids- 2023-11-21 · NCDOT · C204852 · $232.00 per LF · qty 708.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $192.00 per LF · qty 132.0 · bid tab
|
| storm pipe 42-inch | LF | 2 | $303.50 | $299.00 to $308.00 | Bids- 2023-11-21 · NCDOT · C204852 · $299.00 per LF · qty 1124.0 · bid tab
- 2023-11-21 · NCDOT · C204852 · $308.00 per LF · qty 52.0 · bid tab
|
| storm pipe 48-inch | LF | 1 | $354.00 | $354.00 to $354.00 | Bids- 2023-11-21 · NCDOT · C204852 · $354.00 per LF · qty 60.0 · bid tab
|
| storm pipe 60-inch | LF | 1 | $486.00 | $486.00 to $486.00 | Bids- 2023-11-21 · NCDOT · C204852 · $486.00 per LF · qty 304.0 · bid tab
|
| water main 12-inch | LF | 1 | $215.00 | $215.00 to $215.00 | Bids- 2023-11-21 · NCDOT · C204852 · $215.00 per LF · qty 1270.0 · bid tab
|
| water main 16-inch | LF | 1 | $264.00 | $264.00 to $264.00 | Bids- 2023-11-21 · NCDOT · C204852 · $264.00 per LF · qty 1335.0 · bid tab
|
| water main 6-inch | LF | 1 | $101.00 | $101.00 to $101.00 | Bids- 2023-11-21 · NCDOT · C204852 · $101.00 per LF · qty 105.0 · bid tab
|
| water main 8-inch | LF | 1 | $106.00 | $106.00 to $106.00 | Bids- 2023-11-21 · NCDOT · C204852 · $106.00 per LF · qty 850.0 · bid tab
|
| water service | LF | 1 | $24.60 | $24.60 to $24.60 | Bids- 2023-11-21 · NCDOT · C204852 · $24.60 per LF · qty 415.0 · bid tab
|