Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| asphalt pavement | TON | 1 | $735.00 | $735.00 to $735.00 | Bids
|
| excavation embankment | CY | 2 | $24.50 | $21.00 to $28.00 | |
| inlet headwall | EA | 1 | $1,425.00 | $1,425.00 to $1,425.00 | Bids
|
| lime cement stabilization | SY | 2 | $5.50 | $5.00 to $6.00 | |
| lime cement stabilization | TON | 1 | $50.00 | $50.00 to $50.00 | Bids
|
| manhole | EA | 1 | $2,400.00 | $2,400.00 to $2,400.00 | Bids
|
| storm pipe 15-inch | LF | 1 | $80.00 | $80.00 to $80.00 | Bids
|
| storm pipe 18-inch | LF | 1 | $87.00 | $87.00 to $87.00 | Bids
|
| storm pipe 48-inch | LF | 1 | $300.00 | $300.00 to $300.00 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.