| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 2 | $725.50 | $691.00 to $760.00 | Bids- 2025-10-21 · NCDOT · C205093 · $760.00 per TON · qty 1585.0 · bid tab
- 2025-02-18 · NCDOT · C204979 · $691.00 per TON · qty 95.0 · bid tab
|
| curb gutter | LF | 1 | $42.00 | $42.00 to $42.00 | Bids- 2025-10-21 · NCDOT · C205093 · $42.00 per LF · qty 930.0 · bid tab
|
| excavation embankment | CY | 2 | $5.50 | $0.01 to $11.00 | Bids- 2025-10-21 · NCDOT · C205093 · $11.00 per CY · qty 228500.0 · bid tab
- 2025-10-21 · NCDOT · C205093 · $0.01 per CY · qty 214000.0 · bid tab
|
| fire hydrant | EA | 1 | $9,600.00 | $9,600.00 to $9,600.00 | Bids- 2025-10-21 · NCDOT · C205093 · $9,600.00 per EA · qty 4.0 · bid tab
|
| fire hydrant | LF | 1 | $234.00 | $234.00 to $234.00 | Bids- 2025-10-21 · NCDOT · C205093 · $234.00 per LF · qty 29.0 · bid tab
|
| flexible base | TON | 1 | $38.00 | $38.00 to $38.00 | Bids- 2025-10-21 · NCDOT · C205093 · $38.00 per TON · qty 24000.0 · bid tab
|
| inlet headwall | EA | 1 | $1,390.00 | $1,390.00 to $1,390.00 | Bids- 2025-10-21 · NCDOT · C205093 · $1,390.00 per EA · qty 13.0 · bid tab
|
| lime cement stabilization | LF | 1 | $283.00 | $283.00 to $283.00 | Bids- 2025-10-21 · NCDOT · C205093 · $283.00 per LF · qty 604.0 · bid tab
|
| lime cement stabilization | SY | 6 | $4.38 | $3.50 to $6.25 | Bids- 2025-10-21 · NCDOT · C205093 · $4.50 per SY · qty 22540.0 · bid tab
- 2025-10-21 · NCDOT · C205093 · $3.50 per SY · qty 23950.0 · bid tab
- 2025-10-21 · NCDOT · C205093 · $4.25 per SY · qty 29690.0 · bid tab
- 2025-10-21 · NCDOT · C205093 · $3.75 per SY · qty 11220.0 · bid tab
- 2025-02-18 · NCDOT · C204979 · $4.98 per SY · qty 400.0 · bid tab
- 2025-02-18 · NCDOT · C204979 · $6.25 per SY · qty 600.0 · bid tab
|
| lime cement stabilization | TON | 4 | $54.00 | $46.75 to $357.00 | Bids- 2025-10-21 · NCDOT · C205093 · $54.00 per TON · qty 1000.0 · bid tab
- 2025-10-21 · NCDOT · C205093 · $357.00 per TON · qty 290.0 · bid tab
- 2025-10-21 · NCDOT · C205093 · $54.00 per TON · qty 500.0 · bid tab
- 2025-02-18 · NCDOT · C204979 · $46.75 per TON · qty 400.0 · bid tab
|
| manhole | EA | 2 | $3,700.00 | $1,100.00 to $6,300.00 | Bids- 2025-10-21 · NCDOT · C205093 · $6,300.00 per EA · qty 1.0 · bid tab
- 2025-10-21 · NCDOT · C205093 · $1,100.00 per EA · qty 11.0 · bid tab
|
| storm pipe 15-inch | LF | 2 | $98.16 | $90.33 to $106.00 | Bids- 2025-10-21 · NCDOT · C205093 · $106.00 per LF · qty 3940.0 · bid tab
- 2025-02-18 · NCDOT · C204979 · $90.33 per LF · qty 308.0 · bid tab
|
| storm pipe 18-inch | LF | 3 | $109.00 | $106.66 to $120.43 | Bids- 2025-10-21 · NCDOT · C205093 · $109.00 per LF · qty 1296.0 · bid tab
- 2025-02-18 · NCDOT · C204979 · $120.43 per LF · qty 300.0 · bid tab
- 2025-02-18 · NCDOT · C204979 · $106.66 per LF · qty 100.0 · bid tab
|
| storm pipe 24-inch | LF | 1 | $150.00 | $150.00 to $150.00 | Bids- 2025-10-21 · NCDOT · C205093 · $150.00 per LF · qty 368.0 · bid tab
|
| storm pipe 30-inch | LF | 2 | $141.50 | $103.00 to $180.00 | Bids- 2025-10-21 · NCDOT · C205093 · $180.00 per LF · qty 1216.0 · bid tab
- 2025-10-21 · NCDOT · C205093 · $103.00 per LF · qty 568.0 · bid tab
|
| storm pipe 36-inch | LF | 2 | $246.50 | $167.00 to $326.00 | Bids- 2025-10-21 · NCDOT · C205093 · $167.00 per LF · qty 764.0 · bid tab
- 2025-10-21 · NCDOT · C205093 · $326.00 per LF · qty 332.0 · bid tab
|
| storm pipe 42-inch | LF | 1 | $309.00 | $309.00 to $309.00 | Bids- 2025-10-21 · NCDOT · C205093 · $309.00 per LF · qty 200.0 · bid tab
|
| storm pipe 48-inch | LF | 1 | $400.00 | $400.00 to $400.00 | Bids- 2025-10-21 · NCDOT · C205093 · $400.00 per LF · qty 140.0 · bid tab
|
| storm pipe 54-inch | LF | 1 | $917.00 | $917.00 to $917.00 | Bids- 2025-10-21 · NCDOT · C205093 · $917.00 per LF · qty 28.0 · bid tab
|
| water main 8-inch | LF | 1 | $130.00 | $130.00 to $130.00 | Bids- 2025-10-21 · NCDOT · C205093 · $130.00 per LF · qty 3532.0 · bid tab
|
| water service | LF | 1 | $73.00 | $73.00 to $73.00 | Bids- 2025-10-21 · NCDOT · C205093 · $73.00 per LF · qty 640.0 · bid tab
|