| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 4 | $487.50 | $136.00 to $700.00 | Bids- 2026-06-16 · NCDOT · C205182 · $700.00 per TON · qty 750.0 · bid tab
- 2025-07-15 · NCDOT · C205075 · $575.00 per TON · qty 230.0 · bid tab
- 2024-10-15 · NCDOT · C204983 · $136.00 per TON · qty 1060.0 · bid tab
- 2024-10-15 · NCDOT · C204983 · $400.00 per TON · qty 3827.0 · bid tab
|
| curb gutter | LF | 4 | $32.91 | $22.94 to $39.00 | Bids- 2026-06-16 · NCDOT · C205182 · $39.00 per LF · qty 1800.0 · bid tab
- 2025-07-15 · NCDOT · C205075 · $22.94 per LF · qty 1100.0 · bid tab
- 2025-07-15 · NCDOT · C205075 · $29.43 per LF · qty 400.0 · bid tab
- 2025-07-15 · NCDOT · C205075 · $36.39 per LF · qty 2700.0 · bid tab
|
| fire hydrant | EA | 1 | $11,200.00 | $11,200.00 to $11,200.00 | Bids- 2025-07-15 · NCDOT · C205075 · $11,200.00 per EA · qty 3.0 · bid tab
|
| fire hydrant | LF | 1 | $240.00 | $240.00 to $240.00 | Bids- 2025-07-15 · NCDOT · C205075 · $240.00 per LF · qty 84.0 · bid tab
|
| flexible base | TON | 2 | $76.50 | $75.00 to $78.00 | Bids- 2026-06-16 · NCDOT · C205182 · $78.00 per TON · qty 2300.0 · bid tab
- 2025-07-15 · NCDOT · C205075 · $75.00 per TON · qty 1735.0 · bid tab
|
| inlet headwall | LS | 1 | $215,000.00 | $215,000.00 to $215,000.00 | Bids- 2025-07-15 · NCDOT · C205075 · $215,000.00 per LS · qty 1.0 · bid tab
|
| lime cement stabilization | SY | 4 | $4.00 | $2.80 to $5.00 | Bids- 2026-06-16 · NCDOT · C205182 · $4.00 per SY · qty 1100.0 · bid tab
- 2026-06-16 · NCDOT · C205182 · $5.00 per SY · qty 1500.0 · bid tab
- 2025-07-15 · NCDOT · C205075 · $2.80 per SY · qty 4440.0 · bid tab
- 2025-07-15 · NCDOT · C205075 · $4.00 per SY · qty 400.0 · bid tab
|
| lime cement stabilization | TON | 2 | $71.50 | $70.00 to $73.00 | Bids- 2026-06-16 · NCDOT · C205182 · $73.00 per TON · qty 950.0 · bid tab
- 2025-07-15 · NCDOT · C205075 · $70.00 per TON · qty 2830.0 · bid tab
|
| manhole | EA | 3 | $850.00 | $520.00 to $12,000.00 | Bids- 2026-06-16 · NCDOT · C205182 · $520.00 per EA · qty 9.0 · bid tab
- 2025-07-15 · NCDOT · C205075 · $12,000.00 per EA · qty 9.0 · bid tab
- 2024-10-15 · NCDOT · C204983 · $850.00 per EA · qty 13.0 · bid tab
|
| sewer main 10-inch | LF | 1 | $825.00 | $825.00 to $825.00 | Bids- 2025-07-15 · NCDOT · C205075 · $825.00 per LF · qty 1226.0 · bid tab
|
| sewer main 8-inch | LF | 1 | $820.00 | $820.00 to $820.00 | Bids- 2025-07-15 · NCDOT · C205075 · $820.00 per LF · qty 524.0 · bid tab
|
| sewer service | LF | 1 | $190.00 | $190.00 to $190.00 | Bids- 2025-07-15 · NCDOT · C205075 · $190.00 per LF · qty 318.0 · bid tab
|
| sidewalk | EA | 2 | $2,575.00 | $2,250.00 to $2,900.00 | Bids- 2026-06-16 · NCDOT · C205182 · $2,900.00 per EA · qty 8.0 · bid tab
- 2025-07-15 · NCDOT · C205075 · $2,250.00 per EA · qty 22.0 · bid tab
|
| sidewalk | SY | 3 | $80.00 | $59.36 to $94.85 | Bids- 2026-06-16 · NCDOT · C205182 · $80.00 per SY · qty 160.0 · bid tab
- 2025-07-15 · NCDOT · C205075 · $94.85 per SY · qty 150.0 · bid tab
- 2025-07-15 · NCDOT · C205075 · $59.36 per SY · qty 1200.0 · bid tab
|
| storm pipe 15-inch | LF | 2 | $124.00 | $98.00 to $150.00 | Bids- 2026-06-16 · NCDOT · C205182 · $150.00 per LF · qty 668.0 · bid tab
- 2025-07-15 · NCDOT · C205075 · $98.00 per LF · qty 1040.0 · bid tab
|
| storm pipe 18-inch | LF | 2 | $156.25 | $117.50 to $195.00 | Bids- 2026-06-16 · NCDOT · C205182 · $195.00 per LF · qty 228.0 · bid tab
- 2025-07-15 · NCDOT · C205075 · $117.50 per LF · qty 188.0 · bid tab
|
| storm pipe 24-inch | LF | 1 | $148.50 | $148.50 to $148.50 | Bids- 2025-07-15 · NCDOT · C205075 · $148.50 per LF · qty 612.0 · bid tab
|
| storm pipe 30-inch | LF | 1 | $195.30 | $195.30 to $195.30 | Bids- 2025-07-15 · NCDOT · C205075 · $195.30 per LF · qty 432.0 · bid tab
|
| storm pipe 36-inch | LF | 1 | $275.30 | $275.30 to $275.30 | Bids- 2025-07-15 · NCDOT · C205075 · $275.30 per LF · qty 60.0 · bid tab
|
| storm pipe 42-inch | LF | 1 | $375.00 | $375.00 to $375.00 | Bids- 2026-06-16 · NCDOT · C205182 · $375.00 per LF · qty 300.0 · bid tab
|
| water main 2-inch | LF | 1 | $95.00 | $95.00 to $95.00 | Bids- 2025-07-15 · NCDOT · C205075 · $95.00 per LF · qty 684.0 · bid tab
|
| water main 6-inch | LF | 1 | $190.00 | $190.00 to $190.00 | Bids- 2025-07-15 · NCDOT · C205075 · $190.00 per LF · qty 351.0 · bid tab
|
| water main 8-inch | LF | 1 | $195.00 | $195.00 to $195.00 | Bids- 2025-07-15 · NCDOT · C205075 · $195.00 per LF · qty 1573.0 · bid tab
|
| water service | LF | 1 | $45.00 | $45.00 to $45.00 | Bids- 2025-07-15 · NCDOT · C205075 · $45.00 per LF · qty 1154.0 · bid tab
|