| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| asphalt pavement | TON | 3 | $960.00 | $740.00 to $1,065.00 | Bids- 2026-09-15 · NCDOT · C204947 · $1,065.00 per TON · qty 2285.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $960.00 per TON · qty 1410.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $740.00 per TON · qty 430.0 · bid tab
|
| curb gutter | LF | 9 | $56.00 | $30.00 to $105.00 | Bids- 2026-09-15 · NCDOT · C204947 · $51.50 per LF · qty 6100.0 · bid tab
- 2026-09-15 · NCDOT · C204947 · $60.75 per LF · qty 2600.0 · bid tab
- 2026-09-15 · NCDOT · C204947 · $58.00 per LF · qty 330.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $105.00 per LF · qty 72.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $30.00 per LF · qty 2830.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $56.00 per LF · qty 370.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $44.00 per LF · qty 8220.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $46.00 per LF · qty 370.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $58.00 per LF · qty 185.0 · bid tab
|
| fire hydrant | EA | 2 | $8,184.50 | $6,500.00 to $9,869.00 | Bids- 2026-09-15 · NCDOT · C204947 · $9,869.00 per EA · qty 8.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $6,500.00 per EA · qty 2.0 · bid tab
|
| fire hydrant | LF | 3 | $120.00 | $76.00 to $153.00 | Bids- 2026-09-15 · NCDOT · C204947 · $153.00 per LF · qty 159.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $76.00 per LF · qty 32.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $120.00 per LF · qty 40.0 · bid tab
|
| flexible base | TON | 2 | $67.75 | $59.00 to $76.50 | Bids- 2025-10-21 · NCDOT · C204840 · $76.50 per TON · qty 145.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $59.00 per TON · qty 1000.0 · bid tab
|
| inlet headwall | EA | 3 | $2,105.00 | $2,100.00 to $2,108.00 | Bids- 2026-09-15 · NCDOT · C204947 · $2,105.00 per EA · qty 10.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $2,108.00 per EA · qty 11.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $2,100.00 per EA · qty 1.0 · bid tab
|
| lime cement stabilization | SY | 6 | $4.00 | $3.30 to $6.80 | Bids- 2026-09-15 · NCDOT · C204947 · $3.80 per SY · qty 3000.0 · bid tab
- 2026-09-15 · NCDOT · C204947 · $5.70 per SY · qty 900.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $3.30 per SY · qty 5005.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $4.00 per SY · qty 1680.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $6.80 per SY · qty 2100.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $4.00 per SY · qty 600.0 · bid tab
|
| lime cement stabilization | TON | 3 | $62.50 | $58.00 to $70.00 | Bids- 2026-09-15 · NCDOT · C204947 · $62.50 per TON · qty 600.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $70.00 per TON · qty 1120.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $58.00 per TON · qty 1400.0 · bid tab
|
| manhole | EA | 12 | $1,927.50 | $187.00 to $20,800.00 | Bids- 2026-09-15 · NCDOT · C204947 · $7,357.00 per EA · qty 21.0 · bid tab
- 2026-09-15 · NCDOT · C204947 · $1,910.00 per EA · qty 8.0 · bid tab
- 2026-09-15 · NCDOT · C204947 · $187.00 per EA · qty 1.0 · bid tab
- 2026-09-15 · NCDOT · C204947 · $1,011.00 per EA · qty 52.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $1,035.00 per EA · qty 27.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $1,945.00 per EA · qty 4.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $3,365.00 per EA · qty 5.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $1,880.00 per EA · qty 5.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $7,800.00 per EA · qty 21.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $980.00 per EA · qty 8.0 · bid tab
(10 most recent of 12 shown; all in the Hubstake feed) |
| sewer main 8-inch | LF | 3 | $163.00 | $73.00 to $300.00 | Bids- 2026-09-15 · NCDOT · C204947 · $163.00 per LF · qty 3880.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $73.00 per LF · qty 753.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $300.00 per LF · qty 3282.0 · bid tab
|
| sewer service | LF | 1 | $110.00 | $110.00 to $110.00 | Bids- 2024-05-28 · NCDOT · C204844 · $110.00 per LF · qty 453.0 · bid tab
|
| sidewalk | EA | 2 | $4,216.50 | $3,500.00 to $4,933.00 | Bids- 2026-09-15 · NCDOT · C204947 · $4,933.00 per EA · qty 26.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $3,500.00 per EA · qty 26.0 · bid tab
|
| sidewalk | SY | 3 | $95.00 | $70.00 to $98.00 | Bids- 2026-09-15 · NCDOT · C204947 · $98.00 per SY · qty 1310.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $95.00 per SY · qty 1000.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $70.00 per SY · qty 2940.0 · bid tab
|
| storm pipe 15-inch | LF | 3 | $100.00 | $83.00 to $179.00 | Bids- 2026-09-15 · NCDOT · C204947 · $179.00 per LF · qty 2816.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $83.00 per LF · qty 1508.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $100.00 per LF · qty 3432.0 · bid tab
|
| storm pipe 18-inch | LF | 4 | $125.00 | $95.00 to $189.00 | Bids- 2026-09-15 · NCDOT · C204947 · $189.00 per LF · qty 1596.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $95.00 per LF · qty 348.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $140.00 per LF · qty 32.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $110.00 per LF · qty 1268.0 · bid tab
|
| storm pipe 24-inch | LF | 3 | $180.00 | $124.00 to $249.00 | Bids- 2026-09-15 · NCDOT · C204947 · $249.00 per LF · qty 1144.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $124.00 per LF · qty 852.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $180.00 per LF · qty 268.0 · bid tab
|
| storm pipe 30-inch | LF | 2 | $204.50 | $202.00 to $207.00 | Bids- 2026-09-15 · NCDOT · C204947 · $202.00 per LF · qty 116.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $207.00 per LF · qty 344.0 · bid tab
|
| storm pipe 42-inch | LF | 1 | $330.00 | $330.00 to $330.00 | Bids- 2026-09-15 · NCDOT · C204947 · $330.00 per LF · qty 40.0 · bid tab
|
| storm pipe 66-inch | LF | 1 | $958.00 | $958.00 to $958.00 | Bids- 2026-09-15 · NCDOT · C204947 · $958.00 per LF · qty 52.0 · bid tab
|
| water main 10-inch | LF | 2 | $101.75 | $43.50 to $160.00 | Bids- 2026-09-15 · NCDOT · C204947 · $43.50 per LF · qty 425.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $160.00 per LF · qty 910.0 · bid tab
|
| water main 12-inch | LF | 3 | $161.00 | $130.50 to $170.00 | Bids- 2026-09-15 · NCDOT · C204947 · $161.00 per LF · qty 3042.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $130.50 per LF · qty 2970.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $170.00 per LF · qty 2674.0 · bid tab
|
| water main 16-inch | LF | 2 | $115.25 | $88.50 to $142.00 | Bids- 2026-09-15 · NCDOT · C204947 · $88.50 per LF · qty 574.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $142.00 per LF · qty 140.0 · bid tab
|
| water main 4-inch | LF | 1 | $45.00 | $45.00 to $45.00 | Bids- 2025-10-21 · NCDOT · C204840 · $45.00 per LF · qty 219.0 · bid tab
|
| water main 6-inch | LF | 3 | $73.50 | $58.00 to $120.00 | Bids- 2026-09-15 · NCDOT · C204947 · $73.50 per LF · qty 640.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $58.00 per LF · qty 24.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $120.00 per LF · qty 177.0 · bid tab
|
| water main 8-inch | LF | 3 | $96.00 | $73.75 to $140.00 | Bids- 2026-09-15 · NCDOT · C204947 · $96.00 per LF · qty 3346.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $73.75 per LF · qty 1465.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $140.00 per LF · qty 1101.0 · bid tab
|
| water service | LF | 4 | $104.75 | $82.00 to $166.00 | Bids- 2026-09-15 · NCDOT · C204947 · $88.50 per LF · qty 620.0 · bid tab
- 2026-09-15 · NCDOT · C204947 · $166.00 per LF · qty 11.0 · bid tab
- 2025-10-21 · NCDOT · C204840 · $121.00 per LF · qty 33.0 · bid tab
- 2024-05-28 · NCDOT · C204844 · $82.00 per LF · qty 1050.0 · bid tab
|