Site-work prices, Alamance County, NC

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON5$590.00$550.00 to $735.00
Bids
  • 2026-02-17 · NCDOT · C204936 · $735.00 per TON · qty 275.0 · bid tab
  • 2025-07-15 · NCDOT · C205115 · $550.00 per TON · qty 2511.0 · bid tab
  • 2025-04-15 · NCDOT · C205066 · $680.00 per TON · qty 375.0 · bid tab
  • 2024-12-17 · NCDOT · C205003 · $590.00 per TON · qty 1780.0 · bid tab
  • 2024-11-19 · NCDOT · C204998 · $580.00 per TON · qty 2084.0 · bid tab
curb gutterLF2$50.00$48.00 to $52.00
Bids
  • 2025-04-15 · NCDOT · C205066 · $52.00 per LF · qty 4110.0 · bid tab
  • 2025-04-15 · NCDOT · C205066 · $48.00 per LF · qty 680.0 · bid tab
excavation embankmentCY3$32.00$23.00 to $54.00
Bids
  • 2025-07-15 · NCDOT · C205115 · $32.00 per CY · qty 761.0 · bid tab
  • 2024-12-17 · NCDOT · C205003 · $23.00 per CY · qty 288.0 · bid tab
  • 2024-11-19 · NCDOT · C204998 · $54.00 per CY · qty 178.0 · bid tab
fire hydrantLF1$160.00$160.00 to $160.00
Bids
  • 2025-04-15 · NCDOT · C205066 · $160.00 per LF · qty 89.0 · bid tab
flexible baseTON2$56.50$38.00 to $75.00
Bids
  • 2026-02-17 · NCDOT · C204936 · $38.00 per TON · qty 1727.0 · bid tab
  • 2025-04-15 · NCDOT · C205066 · $75.00 per TON · qty 420.0 · bid tab
lime cement stabilizationSY2$2.50$1.50 to $3.50
Bids
  • 2026-02-17 · NCDOT · C204936 · $3.50 per SY · qty 450.0 · bid tab
  • 2026-02-17 · NCDOT · C204936 · $1.50 per SY · qty 1400.0 · bid tab
lime cement stabilizationTON1$25.00$25.00 to $25.00
Bids
  • 2026-02-17 · NCDOT · C204936 · $25.00 per TON · qty 450.0 · bid tab
manholeEA6$1,425.00$819.00 to $1,530.00
Bids
  • 2025-07-15 · NCDOT · C205115 · $1,500.00 per EA · qty 13.0 · bid tab
  • 2025-04-15 · NCDOT · C205066 · $1,500.00 per EA · qty 8.0 · bid tab
  • 2025-04-15 · NCDOT · C205066 · $1,530.00 per EA · qty 4.0 · bid tab
  • 2025-04-15 · NCDOT · C205066 · $819.00 per EA · qty 18.0 · bid tab
  • 2024-12-17 · NCDOT · C205003 · $1,100.00 per EA · qty 13.0 · bid tab
  • 2024-11-19 · NCDOT · C204998 · $1,350.00 per EA · qty 99.0 · bid tab
sidewalkEA1$5,600.00$5,600.00 to $5,600.00
Bids
  • 2025-04-15 · NCDOT · C205066 · $5,600.00 per EA · qty 25.0 · bid tab
sidewalkSY1$130.00$130.00 to $130.00
Bids
  • 2025-04-15 · NCDOT · C205066 · $130.00 per SY · qty 1330.0 · bid tab
storm pipe 12-inchLF1$160.00$160.00 to $160.00
Bids
  • 2025-04-15 · NCDOT · C205066 · $160.00 per LF · qty 4.0 · bid tab
storm pipe 15-inchLF2$122.50$85.00 to $160.00
Bids
  • 2026-02-17 · NCDOT · C204936 · $85.00 per LF · qty 168.0 · bid tab
  • 2025-04-15 · NCDOT · C205066 · $160.00 per LF · qty 892.0 · bid tab
storm pipe 18-inchLF3$100.00$95.00 to $210.00
Bids
  • 2026-02-17 · NCDOT · C204936 · $95.00 per LF · qty 32.0 · bid tab
  • 2026-02-17 · NCDOT · C204936 · $100.00 per LF · qty 44.0 · bid tab
  • 2025-04-15 · NCDOT · C205066 · $210.00 per LF · qty 248.0 · bid tab
storm pipe 24-inchLF1$125.00$125.00 to $125.00
Bids
  • 2026-02-17 · NCDOT · C204936 · $125.00 per LF · qty 52.0 · bid tab
storm pipe 30-inchLF1$175.00$175.00 to $175.00
Bids
  • 2026-02-17 · NCDOT · C204936 · $175.00 per LF · qty 236.0 · bid tab
water main 8-inchLF1$600.00$600.00 to $600.00
Bids
  • 2025-04-15 · NCDOT · C205066 · $600.00 per LF · qty 45.0 · bid tab
water serviceLF1$110.00$110.00 to $110.00
Bids
  • 2025-04-15 · NCDOT · C205066 · $110.00 per LF · qty 87.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.