Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
asphalt pavementTON9$315.00$48.68 to $906.00
Bids
  • 2024-10-10 · MDT · 05R24 · $315.00 per TON · qty 73.0 · bid tab
  • 2024-04-04 · MDT · 04424 · $315.00 per TON · qty 1099.0 · bid tab
  • 2023-12-07 · MDT · 10R23 · $711.01 per TON · qty 2397.7 · bid tab
  • 2023-12-07 · MDT · 10R23 · $53.88 per TON · qty 46635.0 · bid tab
  • 2023-12-07 · MDT · 10R23 · $898.26 per TON · qty 513.8 · bid tab
  • 2023-12-07 · MDT · 10R23 · $83.88 per TON · qty 374.0 · bid tab
  • 2023-12-07 · MDT · 18R23 · $682.40 per TON · qty 2008.6 · bid tab
  • 2023-12-07 · MDT · 18R23 · $48.68 per TON · qty 42618.0 · bid tab
  • 2023-12-07 · MDT · 18R23 · $906.00 per TON · qty 505.4 · bid tab
curb gutterLNFT3$92.00$76.00 to $132.00
Bids
  • 2024-10-10 · MDT · 05R24 · $92.00 per LNFT · qty 134.0 · bid tab
  • 2024-04-04 · MDT · 04424 · $76.00 per LNFT · qty 57.9 · bid tab
  • 2023-12-07 · MDT · 18R23 · $132.00 per LNFT · qty 80.2 · bid tab
excavation embankmentCUYD2$54.62$49.25 to $60.00
Bids
  • 2024-10-10 · MDT · 05R24 · $49.25 per CUYD · qty 10586.0 · bid tab
  • 2024-04-04 · MDT · 04424 · $60.00 per CUYD · qty 9909.0 · bid tab
lime cement stabilizationTON2$254.05$250.50 to $257.60
Bids
  • 2023-12-07 · MDT · 10R23 · $250.50 per TON · qty 658.0 · bid tab
  • 2023-12-07 · MDT · 18R23 · $257.60 per TON · qty 597.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.