Site-work prices, Garfield County, MT
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| asphalt pavement | TON | 4 | $390.52 | $63.34 to $914.35 | |
| excavation embankment | CUYD | 3 | $14.78 | $9.01 to $19.00 | |
| lime cement stabilization | SQYD | 1 | $2.70 | $2.70 to $2.70 | Bids
|
| lime cement stabilization | TON | 1 | $285.80 | $285.80 to $285.80 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.