Site-work prices, Miller County, MO
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|---|---|---|---|---|
| concrete pavement | SQYD | 2 | $87.43 | $84.38 to $90.48 | |
| curb gutter | EA | 1 | $3,093.47 | $3,093.47 to $3,093.47 | Bids
|
| curb gutter | LF | 6 | $47.62 | $43.11 to $70.01 | Bids
|
| excavation embankment | CUYD | 1 | $272.08 | $272.08 to $272.08 | Bids
|
| inlet headwall | EA | 1 | $210.58 | $210.58 to $210.58 | Bids
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.