Site-work prices, Livingston County, MO
Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| curb gutter | EA | 3 | $3,659.00 | $3,540.00 to $3,800.00 | Bids- 2024-06-21 · MoDOT · 240621-A01 · $3,540.00 per EA · qty 32.0 · bid tab
- 2024-06-21 · MoDOT · 240621-A01 · $3,659.00 per EA · qty 2.0 · bid tab
- 2024-06-21 · MoDOT · 240621-A06 · $3,800.00 per EA · qty 2.0 · bid tab
|
| curb gutter | LF | 6 | $64.53 | $35.00 to $135.10 | Bids- 2026-03-20 · MoDOT · 260320-A01 · $83.28 per LF · qty 401.0 · bid tab
- 2026-03-20 · MoDOT · 260320-A01 · $135.10 per LF · qty 16.0 · bid tab
- 2026-03-20 · MoDOT · 260320-A01 · $81.06 per LF · qty 391.0 · bid tab
- 2024-06-21 · MoDOT · 240621-A06 · $35.00 per LF · qty 1015.0 · bid tab
- 2024-06-21 · MoDOT · 240621-A06 · $48.00 per LF · qty 230.0 · bid tab
- 2024-06-21 · MoDOT · 240621-A06 · $45.00 per LF · qty 40.0 · bid tab
|
| inlet headwall | EA | 2 | $1,357.50 | $715.00 to $2,000.00 | Bids- 2026-03-20 · MoDOT · 260320-A01 · $715.00 per EA · qty 3.0 · bid tab
- 2024-06-21 · MoDOT · 240621-A06 · $2,000.00 per EA · qty 12.0 · bid tab
|
Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.