Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
concrete pavementSQYD12$75.57$6.15 to $211.00
Bids
  • 2025-11-14 · MoDOT · 251114-G02 · $80.00 per SQYD · qty 1622.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $80.00 per SQYD · qty 8683.7 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $70.00 per SQYD · qty 1581.2 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $70.00 per SQYD · qty 14.4 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $80.00 per SQYD · qty 28442.1 · bid tab
  • 2025-10-17 · MoDOT · 251017-G03 · $6.15 per SQYD · qty 4098.0 · bid tab
  • 2025-10-17 · MoDOT · 251017-G03 · $211.00 per SQYD · qty 1878.9 · bid tab
  • 2025-10-17 · MoDOT · 251017-G03 · $6.15 per SQYD · qty 2475.0 · bid tab
  • 2025-05-16 · MoDOT · 250516-G01 · $67.70 per SQYD · qty 5883.4 · bid tab
  • 2025-05-16 · MoDOT · 250516-G02 · $75.57 per SQYD · qty 183.2 · bid tab
(10 most recent of 12 shown; all in the Hubstake feed)
curb gutterEA8$3,525.00$160.00 to $4,000.00
Bids
  • 2026-01-16 · MoDOT · 260116-G04 · $4,000.00 per EA · qty 4.0 · bid tab
  • 2025-10-17 · MoDOT · 251017-G03 · $3,550.00 per EA · qty 11.0 · bid tab
  • 2025-10-17 · MoDOT · 251017-G03 · $3,565.00 per EA · qty 18.0 · bid tab
  • 2025-08-15 · MoDOT · 250815-G03 · $165.00 per EA · qty 114.0 · bid tab
  • 2025-08-15 · MoDOT · 250815-G03 · $3,500.00 per EA · qty 4.0 · bid tab
  • 2025-08-15 · MoDOT · 250815-G03 · $3,450.00 per EA · qty 8.0 · bid tab
  • 2025-08-15 · MoDOT · 250815-G03 · $160.00 per EA · qty 172.0 · bid tab
  • 2024-03-15 · MoDOT · 240315-G01 · $3,800.00 per EA · qty 4.0 · bid tab
curb gutterLF40$50.00$2.50 to $474.39
Bids
  • 2025-11-14 · MoDOT · 251114-G02 · $141.27 per LF · qty 338.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $50.00 per LF · qty 79.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $45.00 per LF · qty 12.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $60.00 per LF · qty 108.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $50.00 per LF · qty 282.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $45.00 per LF · qty 752.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $2.50 per LF · qty 1643.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $2.50 per LF · qty 82.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $50.00 per LF · qty 383.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $45.00 per LF · qty 5846.0 · bid tab
(10 most recent of 40 shown; all in the Hubstake feed)
excavation embankmentCUYD18$13.43$5.00 to $56.30
Bids
  • 2026-01-16 · MoDOT · 260116-G04 · $21.00 per CUYD · qty 1159.0 · bid tab
  • 2026-01-16 · MoDOT · 260116-G04 · $21.00 per CUYD · qty 429.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $12.00 per CUYD · qty 14588.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $5.00 per CUYD · qty 117.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $12.00 per CUYD · qty 18480.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $5.00 per CUYD · qty 98.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $12.00 per CUYD · qty 13707.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $5.00 per CUYD · qty 245.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $5.00 per CUYD · qty 79.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $12.00 per CUYD · qty 17537.0 · bid tab
(10 most recent of 18 shown; all in the Hubstake feed)
flexible baseSQYD1$16.45$16.45 to $16.45
Bids
  • 2024-05-17 · MoDOT · 240517-G08 · $16.45 per SQYD · qty 2537.2 · bid tab
inlet headwallEA9$100.00$100.00 to $100.00
Bids
  • 2025-11-14 · MoDOT · 251114-G02 · $100.00 per EA · qty 94.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $100.00 per EA · qty 68.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $100.00 per EA · qty 70.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $100.00 per EA · qty 97.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $100.00 per EA · qty 14.0 · bid tab
  • 2025-05-16 · MoDOT · 250516-G01 · $100.00 per EA · qty 15.0 · bid tab
  • 2025-05-16 · MoDOT · 250516-G02 · $100.00 per EA · qty 8.0 · bid tab
  • 2025-05-16 · MoDOT · 250516-G02 · $100.00 per EA · qty 20.0 · bid tab
  • 2025-05-16 · MoDOT · 250516-G02 · $100.00 per EA · qty 21.0 · bid tab
inlet headwallFT13$1,100.00$700.00 to $2,628.40
Bids
  • 2025-11-14 · MoDOT · 251114-G02 · $800.00 per FT · qty 3.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $700.00 per FT · qty 83.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $1,150.00 per FT · qty 53.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $800.00 per FT · qty 3.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $1,100.00 per FT · qty 252.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $1,020.00 per FT · qty 73.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $1,100.00 per FT · qty 37.0 · bid tab
  • 2025-05-16 · MoDOT · 250516-G01 · $1,330.00 per FT · qty 24.0 · bid tab
  • 2025-05-16 · MoDOT · 250516-G01 · $1,290.00 per FT · qty 13.0 · bid tab
  • 2025-05-16 · MoDOT · 250516-G02 · $1,618.40 per FT · qty 4.0 · bid tab
(10 most recent of 13 shown; all in the Hubstake feed)
inlet headwallLF27$1,080.00$800.00 to $1,200.00
Bids
  • 2025-11-14 · MoDOT · 251114-G02 · $1,100.00 per LF · qty 9.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $800.00 per LF · qty 16.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $800.00 per LF · qty 4.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $1,000.00 per LF · qty 79.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $1,100.00 per LF · qty 22.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $1,020.00 per LF · qty 195.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $1,150.00 per LF · qty 43.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $900.00 per LF · qty 5.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $900.00 per LF · qty 10.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $1,100.00 per LF · qty 8.0 · bid tab
(10 most recent of 27 shown; all in the Hubstake feed)
lime cement stabilizationSQFT4$85.80$80.00 to $121.50
Bids
  • 2025-11-14 · MoDOT · 251114-G02 · $80.00 per SQFT · qty 137.0 · bid tab
  • 2025-05-16 · MoDOT · 250516-G01 · $121.50 per SQFT · qty 2229.0 · bid tab
  • 2024-03-15 · MoDOT · 240315-G01 · $87.20 per SQFT · qty 2805.0 · bid tab
  • 2024-03-15 · MoDOT · 240315-G01 · $84.40 per SQFT · qty 3211.0 · bid tab
storm pipe 15-inchLF1$80.00$80.00 to $80.00
Bids
  • 2025-11-14 · MoDOT · 251114-G02 · $80.00 per LF · qty 78.0 · bid tab
storm pipe 18-inchLF1$85.00$85.00 to $85.00
Bids
  • 2025-11-14 · MoDOT · 251114-G02 · $85.00 per LF · qty 89.0 · bid tab
storm pipe 34-inchFT1$290.00$290.00 to $290.00
Bids
  • 2025-11-14 · MoDOT · 251114-G02 · $290.00 per FT · qty 403.0 · bid tab
storm pipe (diameter not stated)LF2$1,100.00$700.00 to $1,500.00
Bids
  • 2025-11-14 · MoDOT · 251114-G02 · $700.00 per LF · qty 510.0 · bid tab
  • 2025-11-14 · MoDOT · 251114-G02 · $1,500.00 per LF · qty 771.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.