Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.
| Category | Unit | Winning items | Median | Range | Receipts |
|---|
| concrete pavement | SQYD | 2 | $62.98 | $9.97 to $116.00 | Bids- 2024-12-13 · MoDOT · 241213-H01 · $116.00 per SQYD · qty 4722.2 · bid tab
- 2024-12-13 · MoDOT · 241213-H01 · $9.97 per SQYD · qty 5626.0 · bid tab
|
| curb gutter | EA | 2 | $3,869.99 | $3,800.00 to $3,939.98 | Bids- 2024-12-13 · MoDOT · 241213-H01 · $3,800.00 per EA · qty 9.0 · bid tab
- 2024-01-19 · MoDOT · 240119-H03 · $3,939.98 per EA · qty 2.0 · bid tab
|
| excavation embankment | CUYD | 4 | $28.88 | $5.00 to $72.09 | Bids- 2024-11-15 · MoDOT · 241115-H01 · $5.00 per CUYD · qty 630.0 · bid tab
- 2024-11-15 · MoDOT · 241115-H01 · $40.00 per CUYD · qty 4315.0 · bid tab
- 2024-01-19 · MoDOT · 240119-H03 · $17.76 per CUYD · qty 611.0 · bid tab
- 2024-01-19 · MoDOT · 240119-H03 · $72.09 per CUYD · qty 930.0 · bid tab
|
| inlet headwall | EA | 2 | $12,500.00 | $10,000.00 to $15,000.00 | Bids- 2024-11-15 · MoDOT · 241115-H01 · $10,000.00 per EA · qty 4.0 · bid tab
- 2024-11-15 · MoDOT · 241115-H01 · $15,000.00 per EA · qty 4.0 · bid tab
|
| storm pipe 18-inch | LF | 1 | $200.00 | $200.00 to $200.00 | Bids- 2024-11-15 · MoDOT · 241115-H01 · $200.00 per LF · qty 64.0 · bid tab
|
| storm pipe 21-inch | LF | 1 | $250.00 | $250.00 to $250.00 | Bids- 2024-11-15 · MoDOT · 241115-H01 · $250.00 per LF · qty 68.0 · bid tab
|
| storm pipe 30-inch | LF | 1 | $300.00 | $300.00 to $300.00 | Bids- 2024-11-15 · MoDOT · 241115-H01 · $300.00 per LF · qty 108.0 · bid tab
|