Site-work prices, Clinton County, MO

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
concrete pavementCUYD1$37.61$37.61 to $37.61
Bids
  • 2024-10-18 · MoDOT · 241018-A04 · $37.61 per CUYD · qty 5689.0 · bid tab
concrete pavementSQYD1$73.43$73.43 to $73.43
Bids
  • 2024-10-18 · MoDOT · 241018-A04 · $73.43 per SQYD · qty 62279.2 · bid tab
curb gutterEA2$2,500.00$1,500.00 to $3,500.00
Bids
  • 2025-10-17 · MoDOT · 251017-A03 · $1,500.00 per EA · qty 1.0 · bid tab
  • 2024-10-18 · MoDOT · 241018-A04 · $3,500.00 per EA · qty 6.0 · bid tab
curb gutterLF5$48.00$45.00 to $55.00
Bids
  • 2025-10-17 · MoDOT · 251017-A03 · $48.00 per LF · qty 82.0 · bid tab
  • 2025-10-17 · MoDOT · 251017-A03 · $45.00 per LF · qty 136.0 · bid tab
  • 2025-10-17 · MoDOT · 251017-A03 · $45.00 per LF · qty 260.0 · bid tab
  • 2025-10-17 · MoDOT · 251017-A03 · $48.00 per LF · qty 126.0 · bid tab
  • 2025-10-17 · MoDOT · 251017-A03 · $55.00 per LF · qty 58.0 · bid tab
excavation embankmentCUYD2$14.77$14.68 to $14.86
Bids
  • 2024-10-18 · MoDOT · 241018-A04 · $14.86 per CUYD · qty 4224.0 · bid tab
  • 2024-10-18 · MoDOT · 241018-A04 · $14.68 per CUYD · qty 48744.0 · bid tab
lime cement stabilizationSQYD1$7.40$7.40 to $7.40
Bids
  • 2024-10-18 · MoDOT · 241018-A04 · $7.40 per SQYD · qty 76829.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.