Site-work prices, Boone County, MO

Winning-bid unit prices from public bid tabs, last 36 months, from Hubstake. Median and range across all winning line items; each bid links to the agency's own bid tab. Unit prices are per the unit printed on the tab; thickness, class and spec can differ within a category, so use the range, not just the median.

CategoryUnitWinning itemsMedianRangeReceipts
concrete pavementGAL2$2.97$2.76 to $3.19
Bids
  • 2023-11-17 · MoDOT · 231117-D08 · $2.76 per GAL · qty 48672.0 · bid tab
  • 2023-11-17 · MoDOT · 231117-D09 · $3.19 per GAL · qty 5785.0 · bid tab
concrete pavementSQYD5$92.59$63.33 to $110.00
Bids
  • 2026-02-20 · MoDOT · 260220-D01 · $107.35 per SQYD · qty 354.0 · bid tab
  • 2024-05-17 · MoDOT · 240517-D07 · $85.99 per SQYD · qty 4710.0 · bid tab
  • 2024-05-17 · MoDOT · 240517-D07 · $92.59 per SQYD · qty 1010.0 · bid tab
  • 2024-01-19 · MoDOT · 240119-D05 · $63.33 per SQYD · qty 984.0 · bid tab
  • 2023-11-17 · MoDOT · 231117-D07 · $110.00 per SQYD · qty 746.7 · bid tab
curb gutterEA7$3,600.00$3,500.00 to $3,900.00
Bids
  • 2025-11-14 · MoDOT · 251114-D05 · $3,814.05 per EA · qty 4.0 · bid tab
  • 2024-10-18 · MoDOT · 241018-D4A · $3,500.00 per EA · qty 8.0 · bid tab
  • 2024-10-18 · MoDOT · 241018-D4A · $3,500.00 per EA · qty 4.0 · bid tab
  • 2024-09-20 · MoDOT · 240920-D06 · $3,600.00 per EA · qty 4.0 · bid tab
  • 2023-11-17 · MoDOT · 231117-D07 · $3,600.00 per EA · qty 8.0 · bid tab
  • 2023-11-17 · MoDOT · 231117-D08 · $3,900.00 per EA · qty 1.0 · bid tab
  • 2023-11-17 · MoDOT · 231117-D09 · $3,750.00 per EA · qty 1.0 · bid tab
curb gutterLF17$65.00$18.00 to $165.00
Bids
  • 2026-06-18 · MoDOT · 260618-D01 · $92.55 per LF · qty 71.0 · bid tab
  • 2026-06-18 · MoDOT · 260618-D01 · $92.55 per LF · qty 91.0 · bid tab
  • 2026-06-18 · MoDOT · 260618-D01 · $134.05 per LF · qty 2.0 · bid tab
  • 2026-04-17 · MoDOT · 260417-D03 · $47.39 per LF · qty 1060.0 · bid tab
  • 2026-04-17 · MoDOT · 260417-D03 · $73.79 per LF · qty 666.0 · bid tab
  • 2026-04-17 · MoDOT · 260417-D03 · $63.64 per LF · qty 75.0 · bid tab
  • 2026-02-20 · MoDOT · 260220-D01 · $18.00 per LF · qty 912.0 · bid tab
  • 2025-03-14 · MoDOT · 250314-D07 · $65.00 per LF · qty 35.0 · bid tab
  • 2025-03-14 · MoDOT · 250314-D07 · $65.00 per LF · qty 18.0 · bid tab
  • 2025-03-14 · MoDOT · 250314-D07 · $165.00 per LF · qty 19.0 · bid tab
(10 most recent of 17 shown; all in the Hubstake feed)
excavation embankmentCUYD2$21.97$6.05 to $37.90
Bids
  • 2024-05-17 · MoDOT · 240517-D07 · $6.05 per CUYD · qty 1301.0 · bid tab
  • 2024-05-17 · MoDOT · 240517-D07 · $37.90 per CUYD · qty 516.0 · bid tab
excavation embankmentCY2$18.75$17.50 to $20.00
Bids
  • 2026-07-23 · Boone County (MO) · 30-23JUL26-RIPPETO ROAD BRIDGE APPROACH & · $17.50 per CY · qty 360.0 · bid tab
  • 2026-07-23 · Boone County (MO) · 30-23JUL26-RIPPETO ROAD BRIDGE APPROACH & · $20.00 per CY · qty 360.0 · bid tab
flexible baseSY4$27.50$20.00 to $40.00
Bids
  • 2026-07-23 · Boone County (MO) · 30-23JUL26-RIPPETO ROAD BRIDGE APPROACH & · $40.00 per SY · qty 90.0 · bid tab
  • 2026-07-23 · Boone County (MO) · 30-23JUL26-RIPPETO ROAD BRIDGE APPROACH & · $20.00 per SY · qty 90.0 · bid tab
  • 2026-07-23 · Boone County (MO) · 30-23JUL26-RIPPETO ROAD BRIDGE APPROACH & · $35.00 per SY · qty 90.0 · bid tab
  • 2026-07-23 · Boone County (MO) · 30-23JUL26-RIPPETO ROAD BRIDGE APPROACH & · $20.00 per SY · qty 90.0 · bid tab
inlet headwallEA5$130.00$55.00 to $181.39
Bids
  • 2026-06-18 · MoDOT · 260618-D01 · $175.00 per EA · qty 6.0 · bid tab
  • 2026-04-17 · MoDOT · 260417-D03 · $55.00 per EA · qty 7.0 · bid tab
  • 2026-02-20 · MoDOT · 260220-D01 · $130.00 per EA · qty 40.0 · bid tab
  • 2025-03-14 · MoDOT · 250314-D07 · $100.00 per EA · qty 43.0 · bid tab
  • 2024-01-19 · MoDOT · 240119-D05 · $181.39 per EA · qty 36.0 · bid tab
inlet headwallFT3$668.64$626.97 to $905.97
Bids
  • 2024-01-19 · MoDOT · 240119-D05 · $626.97 per FT · qty 10.0 · bid tab
  • 2024-01-19 · MoDOT · 240119-D05 · $668.64 per FT · qty 5.0 · bid tab
  • 2024-01-19 · MoDOT · 240119-D05 · $905.97 per FT · qty 4.0 · bid tab
sidewalkLF1$65.00$65.00 to $65.00
Bids
  • 2026-02-20 · MoDOT · 260220-D01 · $65.00 per LF · qty 40.0 · bid tab

Source file sitework_prices.csv, sha256 60519bdd47f6. Engineer's estimates are excluded. Not a quote.